Hopkins v. Jamieson-Dixon Mill Co.

39 P. 815, 11 Wash. 308, 1895 Wash. LEXIS 299
CourtWashington Supreme Court
DecidedMarch 1, 1895
DocketNo. 1622
StatusPublished
Cited by3 cases

This text of 39 P. 815 (Hopkins v. Jamieson-Dixon Mill Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hopkins v. Jamieson-Dixon Mill Co., 39 P. 815, 11 Wash. 308, 1895 Wash. LEXIS 299 (Wash. 1895).

Opinion

The opinion of the court was delivered by

Dunbar, J.

This is an action in equity to foreclose seven material and labor liens upon a shingle mill and dry house. The lien claimants are respondents Hopkins, Strohl, McMaster, Potts, Seattle Brick & Tile Company, Galt Bros. & Co. and Stimson Mill Co. Jamieson-Dixon Mill Company owned the building and a lease-hold interest in the land subject to the claims of appellant, J. M. Arthur & Co. This latter company claimed to own the machinery; and is also the holder of certain notes secured by a mortgage upon all the estate and interest of the Jamieson-Dixon Mill Company in the buildings, machinery and land.

Upon the trial, plaintiff's having introduced certain proofs and rested, appellant moved by separate motions addressed to each claimant to each cause of action, that said claims and causes of action and each of them be dismissed, and for a non-suit against each on certain specified grounds; each of which motions was denied.

The work and materials for which these liens were [311]*311claimed were performed and furnished prior to the time the lien act of 1893 (Laws, p. 32) went into effect; but the actions were brought subsequent to that time; so that the first question to be determined in the investigation of this case is, does the law of 1893, or do the prior acts, control the procedure in the foreclosure of these liens. If it is concluded that the law of 1893 controls, then many of the objections raised by the appellant need not be discussed. ‘

The act of 1893, entitled “An act creating and providing for the enforcement of liens for labor and material,” seems to be an independent code on the subject embraced in the title of the act, defining liens and making full provision for their enforcement; but the last section of the act (Laws 1893, p. 38, § 19) is as follows:

“All rights acquired under any existing law of this state are hereby preserved, and all actions now pending shall be proceeded with under the law as it exists at the time this act shall take effect. All acts or parts of acts in conflict with the provisions of this act are hereby repealed.”.

It is conceded, and must he under the ruling of this court in Garneau v. Port Blakely Mill Co., 8 Wash. 467 (36 Pac. 463), that the right to a lien when the labor had been performed was preserved by § 19 just quoted. It is, however, insisted by appellant that while the right to the lien may be preserved, the mode of enforcing the lien is the mode prescribed by the act repealed, or the act which was in force at the time the labor was performed or the materials furnished; that the provisions of the law, so far as the act of 1893 is concerned, were prospective, and had it not. been for the saving provisions of § 19 these rights themselves would have been lost; and that, consequently, the provisions of [312]*312the new act for enforcing the liens do not apply to any liens the right to which accrued before the passage of the act.

It does not seem to us that this contention can be sustained. The new act provides that all actions now pending shall be proceeded with under the law as it exists at the time this act shall take effect,” meaning, of course, the old law. Had it been the intention that all liens which were in existence prior to the passage of the act of 1893 should be enforced under the provisions of the old law, it doubtless would have so expressed it; but it has seen fit to restrict the cases which shall proceed under the old law to actions which were already pending at the time the new law went into effect; not actions where the right of action had accrued by reason of the furnishing of labor or material, but to cases where the enforcement of those rights had already been commenced by action. Under the ordinary rule of construction, that the expression of one excludes the other, it cannot be held that the legislature intended that any actions should be proceeded with under the old law except actions already commenced, according to its expressed terms.

The general proposition is laid down in § 24 of Phillips on Mechanic’s Liens (2d ed.), that “the rights of parties under mechanic’s lien laws are to be ascertained and fixed by the law in force when the contract was made; but such rights are to be established and enforced by the law existing at the bringing of the suit.” This general proposition exactly meets the requirements of this case, and while it is conceded by the appellant, it urges that the same author, in the same section, announces the further rule that “ when, however, a new lien law is entirely prospective in its operation, prior cases must be construed according to [313]*313the acts in force when the liens accrued.” An investigation of the cases cited in support of this proposition, however, convinces us that it in no way conflicts with the proposition first announced, but that it has reference to rights and not remedies. In other words, that where a right existed under the old law, and most of the cases are with reference to questions of limitation, the right would not be curtailed by the provisions of the new law.

Church v. Davis, 9 Watts, 304, was one of the cases cited to sustain the text. The opinion is very brief, the court simply holding that where a time was given for enforcing the lien, a new statute which was prospective in its operation did not affect the time provided by the old law. This rule does not go beyond the holding of this court in the case of Garneau v. Port Blakely Mill Co., supra.

This is substantially what is decided in the Minnesota cases cited by appellant. It seems that, according to the opinion in the case of Nelson v. Sykes, 44 Minn. 68 (46 N. W. 207), § 19 of the new law provided that the new act should not affect any rights existing or suits pending when the new act should take effect, and provided further that proceedings taken to enforce liens after the new act should take effect should conform as far as practicable to the provisions of the new act; and the court in passing upon the case where the question involved was, as in the case at bar, a question of limitation, said, after quoting the statute as above noticed:

“And so careful was the legislature to avoid touching prior liens, that pending suits to enforce such liens are not to be affected, but are to go on — of course, according to the procedure under the prior law; and even future suits to enforce such prior liens are not required to conform, except so far as practicable, to the proced[314]*314ure established by the new law. In view of the exceeding care shown by the legislature in these provisos to avoid affecting existing rights, it is impossible to conclude that it intended to cut down the time allowed by the prior law to record the statement for the purpose of preserving and continuing the lien from six months to ninety days.”

It will be seen that our statute makes no provision, as did the Minnesota statute, that such prior liens are not required to conform, except so far as practicable, to the procedure established by the new law, and that is really the provisions upon which this case and the succeeding cases from Minnesota cited by appellant were based. The author, Phillips, however, after laying down the rule which we have just mentioned, proceeds in conformity with the proposition first announced by him:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joplin Sash & Door Works v. Shade
118 S.W. 1196 (Missouri Court of Appeals, 1909)
Blumauer v. Clock
64 P. 844 (Washington Supreme Court, 1901)
Greene v. Finnell
60 P. 144 (Washington Supreme Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
39 P. 815, 11 Wash. 308, 1895 Wash. LEXIS 299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hopkins-v-jamieson-dixon-mill-co-wash-1895.