Hoover General Contractors-Homewood, Inc. v. Key

201 So. 3d 550, 2016 Ala. LEXIS 22
Supreme Court of Alabama·Decided February 19, 2016·No. 1141208·Published·Cited by 11 cases

Opinion

STUART, Justice.

Hoover General Contractors—Home-wood, Inc. (“HGCH”), appeals an order of the Winston Circuit Court denying HGCH’s motion to compel arbitration of its dispute with Gary Key regarding work performed by HGCH on Key’s house in Jasper after that house was damaged by a fire. We reverse and remand.

I.

On August 16, 2013, Key’s house was damaged by a fire. At the time of the fire, Key held a homeowner’s insurance policy issued by Trinity Universal Insurance Company providing coverage for the house, the personal property in the house, and any associated loss of use of the house. On January 13, 2014, Key executed a contract with HGCH providing that HGCH would repair Key’s house for a cost of $83,234. That contract also contained the following arbitration clause:

“Any dispute arising out of or relating to this agreement or the breach, thereof, and if said dispute cannot be settled through direct discussion,., the parties agree to participate in binding arbitration. The BBB Community Mediation Center, an independent, neutral, third party is named as the binding arbitration service. A volunteer BBB arbitrator will render a decision he/she considers to be fair and just. The fee for arbitration will be paid by both parties at the current rate of the BBB of North Alabama Community Mediation Center. ■This agreement affects legal rights of both parties as they are agreeing to resolve the dispute between them described above by binding arbitration, rather than litigation in any court other than for claims that fall within the jurisdiction of small claims court. The arbitrators are empowered to award damages in accordance with Section 1.5 (Limitations of Liability) and may not award punitive damages.”

HGCH thereafter began the work on Key’s house.

. At some point, Key became dissatisfied with HGCH’s work. Key was also dissatisfied with the service and valuation of his loss provided by Trinity Universal and, on September 4, 2014, Key sued HGCH and Trinity Universal, asserting breach-of-contract, negligence/ wantonness, suppression, conversion, and tort-of-outrage claims against both defendants, as well as a bad-faith-failure-to-pay claim against Trinity Universal. On September 9, 2014, HGCH sent counsel for Key a letter denying that it had failed to perform work it had been paid for and denying that it had allowed building materials intended to be used in Key’s house to be damaged. HGCH also stated that it had met with Key that same day, that Key wanted it to resume work on his house, and that HGCH was ready to do so, but that Key was “having difficulty managing the payment process to [HGCH] that is necessary to continue the repairs.” Accordingly, HGCH asked counsel to contact it to discuss possible solutions to managing the payment process so it could finish the repairs to Key’s house. On September 16, 2014, HGCH, acting pro se, filed a copy of this letter with the trial court. On October 16, 2014, HGCH filed notice with the trial court that [552]*552it had retained counsel, as well as a separate answer providing, in toto: “Comes now the defendant, [HGCH], by and through counsel and for answer to the complaint states as follows: 1. The defendant pleads general denial.”

On November 20, 2014, Key amended his complaint to assert a slander-of-title claim against HGCH resulting from a lien HGCH had recorded on Key’s house with the Walker County Probate Judge on October 28, 2014. On December 8, 2014, HGCH filed an answer to Key’s amended complaint in which it again stated, in whole, that “[t]he defendant pleads general denial.”

On March 4, 2015, HGCH, asserting for the first time that an arbitration agreement existed that encompassed its dispute with Key, moved the trial court to compel Key to arbitrate his claims pursuant to the terms of the arbitration clause in their contract. On May 28, 2015, Key filed his opposition to HGCH’s motion to compel arbitration, arguing that HGCH had waived any right to rely on the arbitration clause in their contract inasmuch as HGCH had failed to assert any right to arbitration or to plead arbitration as an affirmative defense in any of its three previous “answers”—the September 9 letter filed with the trial court, the October 16 answer, or the December 3 answer to Key’s amended complaint. That same day, HGCH filed an amended answer asserting various affirmative defenses, including arbitration. Subsequently, on June 2, 2015, Key moved the trial court to strike that amended answer.

On June 5, 2015, HGCH filed counterclaims against Key, including a breach-of-contract claim and a claim seeking to enforce the lien previously recorded with the Walker County Probate Judge. HGCH also separately filed a second motion to compel arbitration, and both parties thereafter filed additional memoranda with the trial court arguing the arbitration issue. On June 26, 2015, the trial court denied HGCH’s motion to compel arbitration; HGCH now appeals that order.

II.

Our standard of review of a ruling denying a motion to compel arbitration is well settled:

“ ‘This Court reviews de novo the denial of a motion to compel arbitration. Parkway Dodge, Inc. v. Yarbrough, 779 So.2d 1205 (Ala.2000). A motion to compel arbitration is analogous to a motion for a summary judgment. TranSouth Fin. Corp. v. Bell, 739 So.2d 1110, 1114 (Ala.1999). The party seeking to compel arbitration has the burden of proving the existence of a contract calling for arbitration and proving that the contract evidences a transaction affecting interstate commerce. Id. “[A]fter a motion to compel arbitration has been made and supported, the burden is on the non-movant to present evidence that the supposed arbitration agreement is not valid or does not apply to the dispute in question.” Jim Burke Automotive, Inc. v. Beavers, 674 So.2d 1260, 1265 n. 1 (Ala.1995) (opinion on application for rehearing).”’

Elizabeth Homes, L.L.C. v. Gantt, 882 So.2d 313, 315 (Ala.2003) (quoting Fleetwood Enters., Inc. v. Bruno, 784 So.2d 277, 280 (Ala.2000)). In this case, it is undisputed that a contract calling for arbitration exists and that the transaction that is the subject of that contract affects interstate commerce. Accordingly, the sole issue in this appeal is whether Key established that the subject arbitration clause does not apply to his dispute with HGCH because HGCH allegedly waived its right to invoke that clause.

[553]*553III.

Key argues that HGCH has waived its right to enforce the arbitration clause in their contract because 1) HGCH did not assert arbitration as an affirmative defense in any of its first three pleadings, and 2) HGCH, he argues, has substantially invoked the litigation process so that he would now be prejudiced if forced to submit his claims to arbitration. With regard to Key’s first argument, we note that Rule 8(c), Ala. R. Civ. P., does list “arbitration and award” as an affirmative defense that should be asserted when “pleading to a preceding pleading.” Inasmuch as arbitration is an affirmative defense, Key argues that HGCH waived that affirmative defense by not asserting it in its first three pleadings. In support of this argument, Key cites Ex parte Liberty National Life Insurance Co., 858 So.2d 950, 953 (Ala.2003), in which this Court stated that “[tjypically, if a party fails to plead an affirmative defense, that defense is deemed to have been waived.” (Citing Robinson v. Morse,

Free access — add to your briefcase to read the full text and ask questions with AI

Hoover General Contractors-Homewood, Inc. v. Key, 201 So. 3d 550, 2016 Ala. LEXIS 22 (Ala. 2016).

201 So. 3d 550 (Hoover General Contractors-Homewood, Inc. v. Key) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related