Hooven, Owens, Rentschler Co. v. City of Atlantic

144 N.W. 635, 163 Iowa 380
CourtSupreme Court of Iowa
DecidedDecember 15, 1913
StatusPublished
Cited by2 cases

This text of 144 N.W. 635 (Hooven, Owens, Rentschler Co. v. City of Atlantic) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hooven, Owens, Rentschler Co. v. City of Atlantic, 144 N.W. 635, 163 Iowa 380 (iowa 1913).

Opinion

Withrow, J.

I. This is an action in replevin, brought by the appellant to recover one tandem compound condensing engine, valued at $5,160, or to recover the value thereof, and $5,500 damages for the wrongful detention thereof. The appellant claimed to be the absolute owner of the engine in controversy, and that the actual market value thereof was $5,160. That it contracted said property to one J os. A. Bortenlanger, conditionally, appellant retaining the title to or ownership of said property, until full and final payment therefor should be made, according to the terms of said contract, which was as follows: 85 per cent, cash on delivery of engine at Atlantic, balance on completion of contractor’s work for the city, and no part of the consideration has ever been [383]*383paid to it. That appellee the city of Atlantic was and still is in the possession of and using said engine. Before the commencement of this action, demand was made of appellee for the possession of said property, which was refused by the said appellee. In defense, the appellee pleads that appellant is barred and estopped from maintaining this action, because it first clothed Jos. A. Bortenlanger with the indicia of ownership by delivering the property in question to him, and then without objection stood by and permitted appellee, without any notice actual or constructive of the claim made thereto by appellant, to pay Jos. A. Bortenlanger, its contractor, $4,644, or 90 per cent, of the actual market value of said engine. Also, that Jos. A. Bortenlanger, who had agreed with the appellee to furnish the material and build for it an electric light and power plant, had installed in said appellee’s power house on appellee’s land said engine, and the same had become a fixture thereto, and thereby had become and was the absolute property of the appellee. There was a trial to a jury resulting in a verdict for the defendant, from which plaintiff appeals.

II. The appellant is a corporation organized under the laws of the state of Ohio', and the appellee is a municipal corporation, organized under the laws of Iowa. On the 21st day of March, A. D. 1911, the appellee the city of Atlantic, Iowa, entered into a written contract with Joseph A. Bortenlanger Company, which contract provided that Jos. A. Bortenlanger Company was to furnish all labor, material, equipment, and supplies necessary for the construction and completion of an electric light and power plant for the city of Atlantic, Iowa, the terms of which, so far as they have bearing upon the case, will be noted in this opinion. After having entered into the contract with the city of Atlantic, Bortenlanger, who was the company, contracted with the appellant for the engine to be used’in such construction, the title to which is now claimed to be in it because of the failure of Bortenlanger to pay for it as agreed, and because of the [384]*384following provision which was a part of the contract between Bortenlanger and the appellant: “The title or ownership of the machinery called for under the terms of this proposal shall remain with the company (appellant), until full and final payment therefor shall have been made according to the terms herein stated and until notes, if any, shall have matured and have been settled for in full. In case of default of any of the payments above provided for, the company may repossess itself of above-mentioned machinery wherever found. ’ ’ The contract was filed for record in the office of the recorder of Cass county, at Atlantic, on September 7, 1911, and duly recorded. The appellant and Bortenlanger both were nonresidents of the.state of Iowa. After entering into the contract, the appellant shipped the engine to Bortenlanger, and ft was received at Atlantic July 24, 1911. There was evidence showing that the appellant knew the purpose for which the engine was being furnished, and that it was to become a part of the permanent light plant of the city of Atlantic. There also was evidence tending to show that, while formal notice of appellant’s reserved title was not served upon the city of Atlantic through its proper officers, certain of its officers were told by Bortenlanger, and learned prior to the receipt and installation of the engine, that as to all the machinery furnished by him the sellers reserved title until they were paid. This latter claim, however, was not admitted to be true, and it was a question of fact which arose in the case. The city of Atlantic-, employed the W. K. Palmer Company Engineers to prepare the plans and specifications, and to assist in making the contracts, because of their technical knowledge of such matters, and also to supervise the work, and approve estimates upon which payments should be made to the contractor during,, the progress of the work. In estimate No. 4, made in July, 1911, was included the engine in controversy, and tinder the contract payment was made by the city to Bortenlanger of 90 per cent, of the said estimate. Before having completed his contract Bortenlanger became insolvent and unable to [385]*385proceed further with it, and thereupon the city, as was its right under its contract, completed the work, at a total cost largely in excess of that fixed in the Bortenlanger contract. To indemnify the city for failure arising out of his default, Bortenlanger had upon entering into the contract with it given bond as required by its terms.

1. Replevin : fixtures: condi: tional sale: m-er eprioprityhofS" right-III. From the foregoing statement of facts, it will be seen that the case is in many of its features like that of Allis-Chalmers Co. v. Atlantic (Iowa), 144 N. W. Rep. 346, decided by this court at the present term, and the law as there announced must control as to this case> s0 ^ar as ^ is applicable under the facts and the record presented. We restate the governing rule announced in that ease, “where á vendor sells machinery which it is understood will become a part of the realty by being attached to it, and that it cannot be removed without injury, and thereby places it within the power of the vendee to so attach it, and sell or mortgage it to innocent purchasers,” as against the purchaser under such conditions, who in this instance would be the city, without actual notice of the reserved title the vendor must suffer upon failure of the vendee to pay for the same. The cause was tried in the court below in the main, under this theory of the law, and many of the errors now presented are based upon a different and contrary claim of right.

2. Same : instructions. IY. In instruction No. 4, given by the trial court, the jury were told that to entitle the defendant to hold possession of the engine, the burden of proof was upon it to show by the preponderance of the evidence: (l) That the defendant received possession of the engine, relying upon the ownership of Bortenlanger; (2) that Bortenlanger installed the engine upon the foundation prepared for it within the building located on the real estate of defendant, with the intention of Bortenlanger to make it a permanent part of the power plant; (3) that at such time the city had no knowledge or notice of the [386]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Bryon v. Weatherly
206 N.W. 828 (Supreme Court of Iowa, 1926)
Gayle Motor Co. v. Gray-Acree Motor Co.
90 So. 334 (Supreme Court of Alabama, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
144 N.W. 635, 163 Iowa 380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hooven-owens-rentschler-co-v-city-of-atlantic-iowa-1913.