Hominy Creek Preservation Ass'n v. West Virginia Department of Environmental Protection

737 S.E.2d 48, 230 W. Va. 151, 2012 WL 5192593, 2012 W. Va. LEXIS 718
CourtWest Virginia Supreme Court
DecidedOctober 19, 2012
DocketNo. 11-0749
StatusPublished

This text of 737 S.E.2d 48 (Hominy Creek Preservation Ass'n v. West Virginia Department of Environmental Protection) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hominy Creek Preservation Ass'n v. West Virginia Department of Environmental Protection, 737 S.E.2d 48, 230 W. Va. 151, 2012 WL 5192593, 2012 W. Va. LEXIS 718 (W. Va. 2012).

Opinion

PER CURIAM:

Petitioner Hominy Creek Preservation Association, Inc. (“the Association”) appeals an order from the Circuit Court of Kanawha County. On April 16, 2010, the Surface Mine Board ordered the West Virginia Departs ment' of Environmental Protection (“DEP”) to pay the Association’s attorney fees and costs for work performed in two administrative appeals.1 Following the entry of this order, the DEP filed a “Motion for Clarification” with the Surface Mine Board requesting that it “clarify and reconsider” its order awarding attorney fees to the Association. The Surface Mine Board denied the motion for clarification, finding that “a supplemental order is not necessary.”

On July 7, 2010, eighty-two days after the Surface Mine Board granted the fee award to the Association, the DEP appealed the Board’s order to the Circuit Court of Kanawha County. The circuit court reversed the Surface Mine Board’s order, finding that the Association was not entitled to recover attorney fees from the DEP. The Association subsequently filed the present appeal arguing that: (1) the DEP failed to file a timely appeal of the Surface Mine Board’s April 16, 2010, order; and (2) the circuit court’s order is based on a clear mistake of law and- includes a number of erroneous factual conclusions.

After thorough review, we find that the DEP failed to file a timely appeal of the Surface Mine Board’s April 16, 2010, order. We therefore reverse the circuit court’s order reversing the fee award, and reinstate the Surface Mine Board’s April 16, 2010, order.

I. Facts & Background

The first of two administrative appeals underlying the fee award began in 2003 when the DEP granted Green Valley Coal Company’s (“Green Valley Coal”) request for an “incidental boundary revision” to an existing mining permit (“permit revision”). Green Valley Coal sought permission to extend a refuse disposal area, relocate a stream, and construct two ponds as part of its disposal operations adjacent to Hominy Creek in Nicholas County, West Virginia. Hominy Creek Preservation Association, Inc., an interested citizen’s group, appealed the DEP’s approval of Green Valley Coal’s permit revision to the Surface Mine Board. The Surface Mine Board held a hearing and determined that: (1) Green Valley Coal failed to provide an accurate and complete statement of the probable hydrologic consequences that would result from its actions; and (2) the DEP should not have accepted Green Valley Coal’s application. However, the Surface Mine Board found that additional evidence presented at the hearing cured the deficiency and affirmed the DEP’s approval of Green Valley Coal’s permit revision.

After the Surface Mine Board’s ruling, the United States District Court for the Southern District of West Virginia vacated two regulations that the DEP relied on in approving Green Valley Coal’s permit revision.2 The Association moved the Surface Mine Board to reconsider and vacate its order affirming the DEP’s approval of the permit revision in light of the District Court’s ruling. On January 10,2007, the Surface Mine Board vacated the DEP’s approval.

While the permit revision appeal was pending, the Association filed a second appeal with the Surface Mine Board. This [153]*153appeal concerned alleged iron pollution in Hominy Creek that was being caused by a Green Valley Coal refuse area. The DEP ordered Green Valley Coal to prepare a probable hydrologic consequences report to “address specifically the apparent increase in iron levels in Hominy Creek[.]” In response to this order, Green Valley Coal filed a revision (“Revision No. 5”) to an existing permit in which it addressed the concerns raised by the Association. The DEP accepted Green Valley Coal’s “Revision No. 5,” and approved the permit.

The Association appealed the approval of Revision No. 5 to the Surface Mine Board arguing that it should not have been approved because (1) it failed to contain adequate data or analysis concerning the role of subsurface water flow through the refuse area; and (2) it erroneously concluded that Green Valley Coal needed to take no remedial action to address or monitor the effect of the subsurface flow on Hominy Creek. Before the Surface Mine Board ruled on the Association’s appeal concerning Revision No. 5, the District Court issued its ruling vacating the two regulations that the DEP relied upon in the permit revision appeal. Following the District Court’s ruling, the Surface Mine Board consolidated the permit revision and Revision No. 5 appeals.

These consolidated appeals resulted in a comprehensive settlement agreement of all litigation between the Association and Green Valley Coal in 2009.3 The settlement agreement recited the parties’ conclusion that applicable law did not authorize an award of attorney fees from Green Valley Coal to the Association for work incurred in the two administrative appeals. Green Valley Coal agreed that it would not oppose any request by the Association for a fee award from any other party. The DEP did not file a motion opposing this settlement agreement, nor did it appeal the Surface Mine Board’s final order accepting the settlement agreement.4

Following the settlement agreement, the Association sought a fee award from the DEP for the fees it incurred in the two administrative appeals pursuant to Surface Mine Board regulations. The Association relied on this Court’s holding in Louden v. West Virginia Division of Environmental Protection, 209 W.Va. 689, 692, 551 S.E.2d 25, 28 (2001), where this Court stated that the “West Virginia Surface Mining regulations governing administrative proceedings sets forth five distinct situations in which costs and expenses may be awarded when judgment is entered.” These situations set forth in the Board’s regulations include the following:

20.12.a. Request for Fees. Any person may on request be awarded by the appropriate board or court a sum equal to costs and expenses including attorneys’ fees and expert witness fees as determined to have been reasonably incurred ... Costs and expenses, including attorneys’ fees may be awarded to:
20.12.a.2. [A]ny participating party other than the violator or his representative from the Division of Environmental Protection upon a determination that the party made a significant contribution to a full and fair determination of the issues[.]

38 C.S.R. 2-20.12.a.2.5

Both the DEP and the Association filed briefs with the Surface Mine Board and par[154]*154tieipated in oral argument before the Board. The Surface Mine Board thereafter issued a detailed 20-page order explaining its finding that the Association was entitled to an award of attorney fees from the DEP pursuant to 38 C.S.R. 2-20.12.a.2. The Board determined that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moten v. Stump
648 S.E.2d 639 (West Virginia Supreme Court, 2007)
James M.B. v. Carolyn M.
456 S.E.2d 16 (West Virginia Supreme Court, 1995)
Schultz v. Consolidation Coal Co.
475 S.E.2d 467 (West Virginia Supreme Court, 1996)
West Virginia Division of Environmental Protection v. Kingwood Coal Co.
490 S.E.2d 823 (West Virginia Supreme Court, 1997)
Tennant v. Callaghan
490 S.E.2d 845 (West Virginia Supreme Court, 1997)
Louden v. West Virginia Division of Environmental Protection
551 S.E.2d 25 (West Virginia Supreme Court, 2001)
Bostic v. American General Finance, Inc.
87 F. Supp. 2d 611 (S.D. West Virginia, 2000)
Johnson v. Georgia Highway Express, Inc.
488 F.2d 714 (Fifth Circuit, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
737 S.E.2d 48, 230 W. Va. 151, 2012 WL 5192593, 2012 W. Va. LEXIS 718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hominy-creek-preservation-assn-v-west-virginia-department-of-wva-2012.