Homer Laughlin Engineers Corp. v. J. W. Leavitt & Co.

2 P.2d 511, 116 Cal. App. 197, 1931 Cal. App. LEXIS 319
CourtCalifornia Court of Appeal
DecidedAugust 20, 1931
DocketDocket No. 7685.
StatusPublished
Cited by9 cases

This text of 2 P.2d 511 (Homer Laughlin Engineers Corp. v. J. W. Leavitt & Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Homer Laughlin Engineers Corp. v. J. W. Leavitt & Co., 2 P.2d 511, 116 Cal. App. 197, 1931 Cal. App. LEXIS 319 (Cal. Ct. App. 1931).

Opinion

PARKER, J., pro tem.

This action was brought by plaintiff against defendant to recover damages for an alleged breach of contract. The cause was tried by the court, sitting without a jury, and from an adverse judgment plaintiff prosecutes this appeal. The record is voluminous and comes to us through a bill of exceptions. The contentions advanced cover almost the entire law of contracts and appellant urges that the most fundamental principles governing were ignored to its prejudice. There is one important fact, however, upon which both parties agree. It is conceded that the contract in question was never fully performed. *199 Appellant contends that the failure of performance was oil the part of respondent, which failure excused further performance on the part of appellant; respondent, on the other hand, argues that the failure was on the side of appellant. And added to this feature of the case is the claim of respondent that the contract was abandoned by mutual consent. The findings of the trial court upon which rest the judgment, were in favor of respondent.

The contract involved was entered into, between the parties on October 31, 1918. By the terms thereof appellant agreed to manufacture tractors as speedily as possible and to deliver to respondent, as the same should be ordered, at least seventy per cent of the tractor output of the factory, not exceeding five hundred tractors in one year. Respondent agreed to immediately place an order for ten tractors then being manufactured by appellant and to pay down the sum of $21,200, which amount was paid and receipt acknowledged. If appellant should make said tractors or proceed with the work thereon to the satisfaction of respondent, then the latter should from month to month thereafter place orders for more tractors and make payment of a similar sum for each ten tractors ordered. After April 1, 1919, respondent should place orders for and pay for ten tractors or more and thereafter each tractor should be paid for as ordered. Respondent agreed to distribute the said tractors throughout the territory, advertise the same in trade journals, carry parts for the tractors and further agreed to advance to appellant, as might be required, sufficient funds for material and labor sufficient for the manufacture and completion of not less than ten tractors at any one time provided that at all times the appellant should have, to the satisfaction of respondent, well and truly proceeded with all diligence to the manufacture and completion of any orders for tractors placed and should on demand furnish a satisfactory statement of assets and liabilities. The appellant in said contract agreed to manufacture the tractors, using the best of materials and workmanship, and embodying therein all new and improved features as might from time to time be invented by appellant or its designing engineer. Appellant further agreed to manufacture and keep on hand in its factory sufficient repair parts to supply the respondent or its agents with such *200 "repair parts as might be necessary. The respondent was given the exclusive agency for the territory for a term of five years. It was mutually agreed that, as prices were revised, the selling price to respondent should not exceed twenty per cent above the cost of manufacture. The contract further provided for abitration in case of dispute. Here it might be noted, while on the subject of the contract, that there was an apparent ambiguity or uncertainty in that portion thereof providing: “If said party of the first part (appellant) shall make said tractors or proceed with the work thereon to the satisfaction of the party of the second part (respondent), said party of the second part shall from month to month hereafter place with the party of the first part orders for tractors . . . and shall make payment,” etc. (Italics ours.) The trial court construed this provision to mean and intended to mean: “If said party . . . shall malee said tractors and proceed with the work thereon,” etc. (Italics ours.)

A specific finding was made to the effect that the contract should be read as the parties so intended. Appellant contends that such a finding is erroneous for two reasons. First, that the pleadings contain no prayer for reformation and, second, that the evidence does not support the finding. We are of the opinion that it was within the province of the trial court to construe the con-. tract from a reading of the whole- thereof- and, where any word or phrase was subject to different meanings, then such meaning should be given as would harmonize with the provisions of the instrument in its entirety and, in arriving at a true construction of the instrument, all of the surrounding circumstances should be considered. It is obvious that the subject of the particular section under present consideration was the satisfaction of the respondent, and it might be noted that the term satisfaction, broadly yet sufficiently defined in similar cases, means the absence of reasonable grounds for dissatisfaction. A strict interpretation of the disputed clause in the disjunctive would result in a construction that would bind respondent in the event that tractors were not being made, if there were no grounds for reasonable dissatisfaction as to the progress of the work; and likewise would respondent be held if tractors were actually being made and yet no effort at all being made to *201 insure output. As will more fully appear hereinafter, such a construction would do violence to the general intent and purpose of the entire transaction. And there is almost an unanimity of holding to the effect that the terms “and” and “or” may be construed as interchangeable when necessary to effect the apparent meaning of the parties. (Arnold v. Hopkins, 203 Cal. 563 [265 Pac. 223]; Willis v. Robinson, 291 Mo. 650 [237 S. W. 1030, 1033]; Pochlman v. Leinweber, 288 Ill. 58 [122 N. E. 834]; Kales v. Houghton, 190 Cal. 294-298 [212 Pac. 21].) And the application of the rule announced will be apparent upon a review of the conditions surrounding the parties at the time the contract was executed.

The date of the contract is likewise significant, for many reasons. In October of 1918 the United States was at war and the usual war-time conditions prevailed in every industry. Particularly, was there an era of unprecedented prosperity in farming. All farm products were at the peak price with the supply limited. Every acre of tillable land throughout the United States was being turned into productivity, with a constant and unsatisfied demand for farm machinery of every type. The appellant corporation was in the experimental stage of manufacturing a light farm tractor. The defendant was a distributor of automobiles, with branches throughout the state, and with a well-organized and successful outlet for distribution. A short time before the execution of the contract there had been a farm and tractor exhibition near Los Angeles. As a part of the exhibit was the tractor of appellant. One Bierlein, a visitor at the exhibition, noticed the tractor and seemed pleased with its performance and hopeful of the possibilities offered in its promotion. Pursuing this interest, Bierlein made contract with the officials of appellant company and obtained from it a contract and authority empowering him to secure capital for the manufacture and distribution of the tractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Szoboszlay v. Glessner
664 P.2d 1327 (Supreme Court of Kansas, 1983)
Hennigan v. United Pacific Insurance
53 Cal. App. 3d 1 (California Court of Appeal, 1975)
Adams v. Williams Resorts, Inc.
210 Cal. App. 2d 456 (California Court of Appeal, 1962)
Steller v. Thomas
45 N.W.2d 537 (Supreme Court of Minnesota, 1950)
McNeil v. Graner
206 P.2d 38 (California Court of Appeal, 1949)
Universal Sales Corp. v. California Press Manufacturing Co.
128 P.2d 665 (California Supreme Court, 1942)
Murphy v. Kendall
123 P.2d 129 (California Court of Appeal, 1942)
Ghirardelli v. Peninsula Properties Co.
107 P.2d 41 (California Supreme Court, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
2 P.2d 511, 116 Cal. App. 197, 1931 Cal. App. LEXIS 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/homer-laughlin-engineers-corp-v-j-w-leavitt-co-calctapp-1931.