Homecraft Builders, Inc. v. Samos

446 A.2d 1054, 1982 R.I. LEXIS 909
CourtSupreme Court of Rhode Island
DecidedJune 18, 1982
DocketNo. 79-341-Appeal
StatusPublished
Cited by1 cases

This text of 446 A.2d 1054 (Homecraft Builders, Inc. v. Samos) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Homecraft Builders, Inc. v. Samos, 446 A.2d 1054, 1982 R.I. LEXIS 909 (R.I. 1982).

Opinion

OPINION

MURRAY, Justice.

The plaintiff, Homecraft Builders, Inc., brought this action in Superior Court against the defendant, Oscar Samos. The plaintiff claimed damages in the amount of $100,000 which included (a) $8,000, plus interest, lent to the defendant; (b) the unpaid balance owed for the renovation of the defendant’s residence; and (c) reimbursement for the partial construction of an office building for the defendant. The defendant, in turn, filed a counterclaim against the plaintiff, seeking damages for the cost of repairs to a portion of the construction and for the increased cost occasioned by his subsequent hiring of another contractor to complete the office building.

[1055]*1055After the trial, the jury denied defendant’s counterclaim and returned a verdict of $37,572.75 for plaintiff. The defendant then moved for a new trial on all issues. The trial justice, finding that the verdict was excessive and that defendant’s counsel had prejudiced his client, ordered a new trial on the issue of damages only. The plaintiff and defendant have both appealed to this court from the order of the trial justice.

In 1974, plaintiff performed several home-renovation projects for defendant and his wife at their residence in Cranston. Ralph N. Sweet (hereinafter referred to as “plaintiff”), the manager, sole stockholder, and officer of plaintiff corporation, testified at trial that defendant and his wife had agreed to pay $2,150 for the last of these projects. According to plaintiff, only $1,000 of this was paid, and defendant orally promised to include the remaining $1,150 in the price of a construction contract for a medical office building that defendant proposed to have plaintiff build in Pawtucket.

The contract entered into by the parties was the subject of lengthy, conflicting, and often confusing testimony. However, a careful review of the transcript reveals the essential elements of plaintiff’s claim.

In September 1974, plaintiff borrowed a total of $8,000 which he in turn lent to defendant to enable him to meet the $23,-000 purchase price of the land for the proposed office building. On September 30, plaintiff and defendant signed an agreement in which defendant promised to pay $100,000 for a one-story, L-shaped office building. Upon presentation by plaintiff of a written request for payment, a proportionate amount of the contract price was to be paid every two weeks, starting from the commencement of construction.

According to plaintiff’s testimony, the actual construction costs and anticipated profit amounted to only $87,000. The remaining $13,000 was intended to reimburse plaintiff for (a) the $1,150 that defendant still owed for the renovations on his home; (b) the $8,000 loan by plaintiff to defendant for the purchase of the land for the office building; (c) any interest on that loan paid by plaintiff to the lending bank; and (d) a future renovation project at defendant’s home. Regrettably, the parties failed to incorporate, or even to refer to, their understanding with respect to these points in the written agreement itself.

The difficulties between the parties began in earnest with plaintiff’s inability to obtain a performance bond which was required by defendant’s bank as a prerequisite to mortgage approval. This failure to obtain a bond caused defendant to experience difficulty in obtaining financing. According to plaintiff’s testimony, defendant finally gave him a written waiver of the bond requirement. The defendant then instructed plaintiff to begin construction, despite plaintiff’s warning that the lack of a performance bond might jeopardize defendant’s chance of obtaining mortgage financing.1 The defendant reassured plaintiff, promising that he would allow plaintiff to finance the construction if bank financing did in fact prove unobtainable. In return for plaintiff’s financial assistance, defendant would then agree to form a corporation with plaintiff for the ownership as well as the construction of the building.

The plaintiff accordingly began construction and, after about two weeks had elapsed, he orally requested payment of $23,000. The plaintiff testified that this figure included the $8,000 loan and the unpaid $1,150 bill, as well as the cost of the work done and a portion of the anticipated profits and of the contingency fund.

The defendant, who was still experiencing difficulty obtaining financing, requested more time. During the next two weeks plaintiff frequently spoke to defendant about his need for payment; when about a month from the start of construction had expired, the difficulties between plaintiff and defendant came to a head. The build[1056]*1056ing foundation had been completed, and plaintiff needed funds to purchase the materials to continue construction. The plaintiff testified that defendant again requested more time and repeated his promise to form a corporation with plaintiff for the ownership of the building if he could not raise the money in the next few days. The plaintiff further testified that defendant was not in fact able to pay within the specified time. Nevertheless, defendant reneged on his promise to give plaintiff an interest in the building in return for continuing construction at his own expense.

At this point, plaintiff notified defendant that he refused to proceed with the construction until he received payment. The plaintiff did, however, visit the construction site again in late November and noticed that the foundation was beginning to crack because of the onset of frost. He advised defendant that serious damage to the foundation would result if the floor and supports were not soon installed. The plaintiff testified that he was still waiting for payment in December when another visit to the site revealed that another contractor was at work. The plaintiff thereupon brought this action against defendant.

The testimony of defendant and his wife conflicts sharply with that of plaintiff in several essential respects. The defendant’s wife denied owing $1,150 for home renovations and insisted that the $1,000 that she had paid plaintiff was the full agreed price. The defendant himself claimed that he knew nothing of the disputed $1,150 until plaintiff demanded payment of the $23,000 bill. Both defendant and his wife did, however, acknowledge having borrowed $8,000 from plaintiff.

The defendant also testified that although he did initially experience difficulty in obtaining financing, he had always intended to have plaintiff complete the construction. He only hired another contractor, Catallozzi Brothers Construction Company (Catallozzi Brothers), because of plaintiff’s refusal to go back to work. The defendant further explained that he had refused to make the $23,000 payment requested by plaintiff because he considered it excessive, not because he intended to terminate his contractual relationship with plaintiff.

The defendant testified that he paid Ca-tallozzi Brothers $3,352.71 to repair the damaged foundation. Catallozzi Brothers also agreed to complete the construction for a price in excess of that agreed to by plaintiff. The testimony on this point is conflicting, but Richard Catallozzi testified that the price was $111,000 in addition to the cost of repairing the foundation. The repair cost and the increased amount of this second contract was the amount sought by defendant in his counterclaim.

In its verdict the jury specifically denied the counterclaim and returned a verdict for plaintiff in the amount of $37,572.75.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cannone v. New England Telephone & Telegraph Co.
471 A.2d 211 (Supreme Court of Rhode Island, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
446 A.2d 1054, 1982 R.I. LEXIS 909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/homecraft-builders-inc-v-samos-ri-1982.