MOISE, Justice.

The appellant, Paul Pruitt, was sued by the appellees, Home Plumbing and Contracting Company, a partnership, and Home Lumber Company, a corporation, to foreclose two mechanics liens, one filed by each, which grew out of construction of a swimming pool on appellant’s property by one Jack Brown, pursuant to contract between appellant and Brown. Brown was made a third party defendant, and failed to answer, or otherwise plead and appellant was given a judgment against him for the amounts adjudged due to appellees.

By his answer, appellant, among other issues, raised the question of whether or not the instruments filed by appellees created liens against his property; and denied that the materials sold by appellees were furnished to him.

The court, having ruled at the trial in favor of appellees and against appellant, this appeal was perfected and these issues presented as two of the points relied on for reversal. In addition, appellant asserts that appellee failed to introduce the liens in evidence, failed to produce substantial evidence of the amount due, and that a personal judgment for the amount claimed and for attorney fees was improperly entered against appellant.

The claim of lien filed by Home Plumbing and Contracting Company was signed in the name of the company by W. C. Bur-ran, Partner, and bears an acknowledgment in the form generally provided by § 43-1-9, N.M.S.A.1953, for acknowledging instruments affecting real estate. It recited that on the date shown therein “be-' fore me (the subscribing. notary public) personally appeared W. C. Burran, to me known to be the person who executed the foregoing instrument as a partner of the co-partnership of Home Plumbing and Contracting Company, and said W. C. Bur-ran acknowledged that he executed the same as his free act and deed, and as the free act and deed of the said co-partnership, Home Plumbing and Contracting Company, and as the free act and deed of W. C. Burran, partner of said co-partnership.” This was followed by the signature, statement of expiration date of commission and seal of the notary public.

The claim of lien of Home Lumber Company was signed by W. C. Burran, Secretary-Treasurer, below which appears the following:

“State of New Mexico 1 The County of Curry j SS “W. C. Burran, Being duly sworn, says: That he is the Secretary-Treasurer of the Home Lumber Company, a corporation, named in the foregoing claim; that he has read said claim and knows the contents thereof; and that the matters and facts therein started (sic) are true and correct.
“W. C. Burran”

This was subscribed and sworn to before a notary public whose signature, seal and date of expiration of commission appear thereon.

Our statute (§ 61-2-6, N.M.S.A.1953) requires that a claim of lien “must be verified by the oath of’” the person claiming the benefit of the lien statute “or of some other person.” Accordingly, we must determine if the two claims here in issue are verified by oath.

In the early days of our history, this court was disposed to hold that the mechanics lien law was in derogation of the common law and should be strictly construed, Finane & Elston v. Las Vegas Hotel & Improvement Company, 3 N.M. 411, 5 P. 725. In Minor v. Marshall, 6 N.M. 194, 27 P. 481, it was held, while adhering to the strict construction rule, that strict construction did not contemplate arbitrary or' inequitable meaning but that the requirements were met by substantial compliance with the statute. However, it was .not long until it was determined that the law was in fact remedial in nature and should be liberally construed. Ford v. Springer Land Association, 8 N.M. 37, 41 P. 541. The prior contrary holding was expressly overruled.

.In Lyons v. Howard, 16 N.M. 327, 117 P. 842, this court applied the rule of liberal construction to a verification there under attack and concluded that it was a sufficient compliance with the statute. In Hot Springs Plumbing & Heating Co. v. Wallace, 38 N.M. 3, 27 P.2d 984, the development of the law was again discussed and the rule of liberal construction adhered to, and in this case the following language of Justice Freeman in his dissent in Minor v. Marshall, supra, was quoted as the law:

“I think the better rule may be stated as follows, to-wit: That where it appears that the miner or mechanic has used words which by plain intendment were designed to operate as a verification, and where it is evident that the miner or mechanic was endeavoring to secure the benefit of the statute provided for such cases, and where such statement is sworn to, it ought to be regarded as a verification, within the meaning of the statute.”

Applying the law as thus announced, we are clear that the verification to the claim of lien of Home Lumber Company is sufficient and that appellant’s attack thereon must fail.

However, as to the Home Plumbing and Contracting Company claim, we fail to find any words whatsoever which by intendment, plain, or otherwise, “were designed to operate as a verification.” Neither do we find where the statement of claim was in any manner sworn to.

In Black’s Law Dictionary, “verification” is defined as:

“Confirmation of correctness, truth, or authenticity by affidavit, oath or deposition.”

See 44 Words and Phrases for other definitions.

. While reiterating our adherence to the rule of liberal construction, we are convinced that with a total absence of any words confirming correctness, truth or authenticity by affidavit, oath, deposition or otherwise, to conclude that the acknowledgment to the instant claim of lien was a sufficient compliance with the requirements of a verification would be stretching the rule of liberal construction beyond recognition, and would approach judicial repeal of the legislative mandate that claims should be verified by oath. Compare Ross v. Marberry & Company, 66 N.M. 404, 349 P.2d 123. Accordingly, the court erred in its conclusion that the claim of lien of Home Plumbing and Contracting Company was enforceable..

Appellant’s additional points will be discussed insofar as they apply to the claim of Home Lumber Company.

Concerning appellant’s arguments that there was no allegation or proof that the materials were actually used in the construction of the pool, it is sufficient answer to point out that appellee’s witness testified without objection on appellant’s part that the materials furnished were used in the swimming pool being built for appellant. Proof having thus been made, the complaint should be treated as amended to conform thereto. Hall v. Bryant, 66 N.M. 280, 347 P.2d 171. It is apparent that the requirement of both pleading and proof of the use of the materials in the job as announced in Tabet v. Davenport, 57 N.M. 540, 260 P.2d 722

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sonida, LLC v. Spoverlook, LLC
2016 NMCA 026 (New Mexico Court of Appeals, 2015)
Kelly Inn No. 102, Inc. v. Kapnison
824 P.2d 1033 (New Mexico Supreme Court, 1992)
White v. Diamond International Corp.
665 P.2d 463 (Wyoming Supreme Court, 1983)
First Security Mortgage Co. v. Hansen
631 P.2d 919 (Utah Supreme Court, 1981)
New Mexico Properties, Inc. v. Lennox Industries, Inc.
618 P.2d 1228 (New Mexico Supreme Court, 1980)
Pineland Lumber Co. v. Robinson
382 A.2d 33 (Supreme Judicial Court of Maine, 1978)
State v. Cessna International Finance Corp.
559 P.2d 417 (New Mexico Supreme Court, 1977)
Matter of One Cessna Aircraft, Etc.
559 P.2d 417 (New Mexico Supreme Court, 1977)
Crescent Electric Supply Co. v. Nerison
232 N.W.2d 76 (South Dakota Supreme Court, 1975)
Starkovich v. Noye
529 P.2d 698 (Arizona Supreme Court, 1974)
Daughtrey v. Carpenter
477 P.2d 807 (New Mexico Supreme Court, 1970)
Rutledge v. Johnson
465 P.2d 274 (New Mexico Supreme Court, 1970)
Blueher Lumber Company v. Springer
1967 NMSC 034 (New Mexico Supreme Court, 1967)
Dunson Contractors, Inc. v. Koury
418 P.2d 66 (New Mexico Supreme Court, 1966)
Martinez v. Research Park, Inc.
410 P.2d 200 (New Mexico Supreme Court, 1965)
Allsop Lumber Co. v. Continental Casualty Co.
385 P.2d 625 (New Mexico Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
372 P.2d 378, 70 N.M. 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/home-plumbing-and-contracting-company-v-pruitt-nm-1962.