Home Builders Ass'n of Greater St. Louis, Inc. v. City of Wildwood

107 S.W.3d 235, 2003 Mo. LEXIS 99, 2003 WL 21386309
CourtSupreme Court of Missouri
DecidedJune 17, 2003
DocketSC 84647
StatusPublished
Cited by14 cases

This text of 107 S.W.3d 235 (Home Builders Ass'n of Greater St. Louis, Inc. v. City of Wildwood) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Home Builders Ass'n of Greater St. Louis, Inc. v. City of Wildwood, 107 S.W.3d 235, 2003 Mo. LEXIS 99, 2003 WL 21386309 (Mo. 2003).

Opinion

MICHAEL A. WOLFF, Judge.

The Home Builders Association of Greater St. Louis, Inc., (HBA) brought a declaratory action challenging the validity of a Wildwood city ordinance that requires subdivision developers to post bonds to assure subdivision improvements.

*237 The trial court held that the city ordinance was void because it is inconsistent with section 89.410 as amended in 1999. 1 The trial court granted summary judgment to the HBA.

The trial court held that the ordinance, No. 675 of the city of Wildwood, exceeded the authority in section 89.410. 2 On appeal, the city argues that the statute gave it the authority, within the bounds of reasonableness, to require developers to post bonds in an amount that exceeded the estimated construction costs of improvements. The city also argues that the section, which by its own language does not apply to maintenance bonds, does not preclude it from requiring developers to post a separate maintenance bond. In the alternative, the city asserts that the current version of section 89.410 was unconstitutionally enacted by the legislature. 3

This Court has exclusive jurisdiction because this case involves the validity of a state statute. Mo. Const, art. V, sec. 3. The judgment of the trial court is reversed. The city of Wildwood did not go beyond its statutory authority under section 89.410 in adopting Ordinance 675.

Section 89.410 and Ordinance 675

Wildwood’s ordinance was adopted to comply with section 89.410 as amended by Senate Bill 20 in 1999. Prior to the amendment, section 89.410.2 provided that the council could accept a bond “in an amount and with surety and conditions satisfactory to it, providing for and securing the actual construction and installation of the improvements....” 4 After the 1999 amendment, section 89.410.2 provides that the council may accept a bond “in an amount and with surety and other reasonable conditions, providing for and securing the actual construction and installation of the improvements.... ” Section 89.410.2 (emphasis added). In addition, subsection 3 of section 89.410 now requires a city to release any escrow amount within 30 days of completion of each category of improvement or utility except a maximum retention of 5 percent, which the city must release upon completion of all improvements and utility work.

Ordinance 675, codified as section 1005.080 of the Wildwood city ordinances, provides that a developer must post a “construction deposit” of 110 percent of the Wildwood Department of Public Works’ estimated cost of construction, completion and installation of required improvements. Upon completion of all the improvements in a particular category of improvements, the city releases all but 5 percent of the deposit, which the city retains until all improvements of the subdivision are completed.

The ordinance also requires developers to post separately a “maintenance deposit” to secure the maintenance of improvements, including undeveloped lots, streets, *238 sidewalks, common areas, and storage and drainage facilities. The deposit is 10 percent of the department of public works’ estimate of the cost of construction, completion and installation of the improvements. Under the ordinance, the city holds the deposit until the sooner of the expiration of 18 months after acceptance for public dedication of the specific improvement by the city or the expiration of 18 months after occupancy permits have been issued on 95 percent of all lots in the subdivision.

Procedural History

After Wildwood adopted the ordinance, the HBA filed a petition on behalf of its members seeking a declaratory judgment that the ordinance was void because it was in direct conflict with section 89.410. The trial court dismissed HBA’s suit finding that HBA lacked standing to bring the lawsuit on behalf of its members. The Court of Appeals, Eastern District, reversed and remanded holding that HBA did have standing. Home Builders Ass’n. of Greater St. Louis, Inc. v. City of Wildwood, 3 2 S.W.Sd 612 (Mo.App.2000).

On remand, the trial court granted summary judgment in favor of HBA holding that the ordinance conflicted with a state statute. The court found that Wildwood did not have authority under section 89.410 to require developers to post deposits in an amount 10 percent above the estimated actual construction costs because section 89.410 limits subdivision bonds to the amount of actual construction. Further, the court found that section 89.410 expressly prohibits maintenance deposits; thus, Wildwood could not require maintenance deposits in an amount of 10 percent of the estimated actual construction costs. The court also found that Wildwood was without authority to retain these maintenance deposits for 18 months because section 89.410 requires that 95 percent of any amount deposited be released within 30 days of the completion of the categories of improvements.

The court invalidated the offending provisions of the ordinance and ordered the city to return all escrow amounts held in excess of those authorized by section 89.410. The city appealed, and HBA cross-appealed for attorneys’ fees.

Our review on appeal from summary judgment is essentially de novo. ITT Commercial Fin. Corp. v. Mid-America Marine Supply Corp., 854 S.W.2d 371, 376 (Mo. banc 1993). After reviewing the record in a light most favorable to the party against whom summary judgment was entered, we reverse. Id. For reasons stated below, Wildwood is within its authority under section 89.410 to adopt the challenged provisions of Ordinance 675.

Actual Construction Costs

Section 89;410 does not prevent Wildwood from collecting subdivision bonds in an amount exceeding the estimated actual cost of construction. The statute provides that the council “may accept a bond or escrow in an amount and with surety and other reasonable conditions. ...” Thus, within the bounds of reasonableness, the city may require a bond that accounts for factors such as inflation and prevailing wage so that it can “provide for and secure the actual construction and installation of improvements.” Section 89.410.2.

An ordinance must be construed to uphold its validity unless it is “expressly inconsistent or in irreconcilable conflict” with the statute. McCollum v. Director of Revenue, 906 S.W.2d 368, 369 (Mo. banc 1995). In reviewing for conflict, this Court looks to the plain language of the statute and determines whether the ordinance prohibits what the statute permits or permits what the statute prohibits. Morrow *239 v. Kansas City, 788 S.W.2d 278, 281 (Mo. banc 1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Copeland v. City of Union
534 S.W.3d 298 (Missouri Court of Appeals, 2017)
Olga Despotis Trust v. Cincinnati Insurance Company
867 F.3d 1054 (Eighth Circuit, 2017)
Patty Sue, Inc. v. City of Springfield
381 S.W.3d 360 (Missouri Court of Appeals, 2012)
State v. McCabe
345 S.W.3d 311 (Missouri Court of Appeals, 2011)
State v. Davis
318 S.W.3d 618 (Supreme Court of Missouri, 2010)
Turner v. School District of Clayton
318 S.W.3d 660 (Supreme Court of Missouri, 2010)
Ross v. Director of Revenue
311 S.W.3d 732 (Supreme Court of Missouri, 2010)
Vance Bros., Inc. v. Obermiller Construction Services, Inc.
181 S.W.3d 562 (Supreme Court of Missouri, 2006)
Adams v. Squibb
128 S.W.3d 149 (Missouri Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
107 S.W.3d 235, 2003 Mo. LEXIS 99, 2003 WL 21386309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/home-builders-assn-of-greater-st-louis-inc-v-city-of-wildwood-mo-2003.