Homann v. Huber

228 P.2d 466, 38 Wash. 2d 190, 1951 Wash. LEXIS 419
CourtWashington Supreme Court
DecidedMarch 9, 1951
Docket31310
StatusPublished
Cited by18 cases

This text of 228 P.2d 466 (Homann v. Huber) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Homann v. Huber, 228 P.2d 466, 38 Wash. 2d 190, 1951 Wash. LEXIS 419 (Wash. 1951).

Opinion

Robinson, J.

— The principal, and practically only serious, question presented by this appeal involves the priority of liens.

The action was tried upon the first amended complaint of A. G. Homann and the answer thereto, and cross-complaint of James Construction Company and Homann’s reply thereto. In his complaint, Homann alleged: (1) that H. H. Huber, Harold Schmitt, and G. I. Griffith, at the time the complaint was filed, and prior thereto, were owners of certain lands in Thurston county (particularly describing *191 them) upon which they, as copartners, did business under the name of Midfield Packers; (2) that, during the year 1945, the partnership entered into an oral cost plus contract with him in which he agreed to construct a cold storage and warehouse and frozen food processing plant on their lands; (3) that he commenced the construction early during the year, paying for all labor and materials used, in the amount of $95,696.86, of which the defendants paid on account the sum of $44,795.31; (4) that he ceased to furnish labor and materials on September 18, 1946; (5) that, on November 12, 1946, within ninety days from the last day he furnished labor and materials, he claimed a lien on the Midfield Packers’ premises and filed a statutory notice of such claim in the office of the auditor of Thurston county. Thereafter, the defendants paid on account the sum of $1,755.95, leaving still due on such lien the sum of $49,145.60, plus interest from November 12, 1946. Plaintiff ■ further alleged that numerous other defendant parties and firms claimed some right to liens on the land, particularly mentioning the James Construction Company and the United States, but that all of such claims were subsequent and inferior to his lien.

Plaintiff prayed for judgment against the copartners, Midfield Packers, in the sum of $49,145.60, with interest from November 12, 1946, and for the allowance of attorney’s fees and costs, and that his lien be adjudged to be a first and prior lien on the premises of the Midfield Packers.

Defendant James Construction Company denied a number of the allegations of the plaintiff’s complaint, and, by way of cross-complaint, alleged (1) that, on June 4, 1946, it entered into a written contract with the copartners of Midfield Packers to construct 759 feet of railway track upon its premises; (2) that it began to perform labor and furnish materials for the construction of the track on July 1, 1946; (3) that the reasonable cost of the labor and materials amounted to $7,308.16; (4) that the copartnership should be allowed an offset of sixty dollars, leaving a sum still due and owing of $7,248.16, with interest thereon at the rate of six per cent per annum from the 16th day of October, 1946, *192 until fully paid; (5) that the furnishing of labor and materials ceased on October 16, 1946; (6) that, within ninety days after the date of the last delivery of materials and performing labor, to-wit, on the 2nd day of January, 1947, it filed its notice of claim of lien with the auditor of Thurston county; (7) that no part of the sum of $7,248.16 had been paid, and that the lien therefor is a valid and subsisting first lien upon the real property of the Midfield Packers described therein; and (8) that the plaintiff, Homann, and most of the defendants, including the United States, claimed to have some right or interest in the lands, 'but that the liens of all of them, if any, were subsequent and inferior to its lien. It was also alleged:

“That all the above claims of the United States Government by and through its Internal Revenue Service of its Treasury Department were filed subsequent to the time when the cross complainant, James Construction Company, a corporation, commenced to perform labor and furnish materials for employment of the premises above described in this complaint and said claims are for special taxes and not general taxes and hence are subsequent and inferior to the claim of this complainant.”

The cause came on for trial on July 7, 1948, and, after numerous hearings, the trial judge, on August 18, 1949, rendered a memorandum opinion in which he carefully stated the issues in the case as follows:

“Defendant James Construction Company and intervenor Trustee in Bankruptcy contend among other things that (1) that plaintiff is not operating under a cost plus contract, (2) that plaintiff’s lien was not timely filed, (3) that plaintiff waived his right to file a lien by agreement entered into between plaintiff and Midfield Packers under date of October 8th, 1946, and plaintiff and Trustee contend that the lien of James Construction Company was not filed in time.”

As to these issues, he said:

“Upon these issues after considering the evidence and the authorities I find as follows: (1) the contract of plaintiff was a cost plus contract so regarded and acted upon by the parties themselves. (2) that plaintiff’s lien was filed within the time fixed by the statute. (3) plaintiff did *193 not waive his rights to file a lien by reason of the agreement of October 8th, 1946, or at all. (4) the lien of James Construction Company was filed within the statutory time.”

He then stated his conclusions as follows:

“That there is a distinction between the rights of parties under a contractors’ lien and a mechanics’ or laborers’ lien is settled by the case of Willett vs Davis, 30 Wash., 2nd 632, and it is there held that many of the items challenged here by the trustee and James Construction Company are proper lienable items. Under this and supporting authorities the contractor plaintiff is entitled to a lien for the legitimate costs of the performance of the contract plus fifteen percent as provided in the contract. In this is included such costs as equipment, equipment rentals, equipment repairs, supplies and taxes. The contract in the Willett vs Davis case wherein certain items were eliminated was limited to cost of labor and materials and for that reason those items were disallowed. The contract here is not so limited and items such as equipment rentals, supplies and taxes are allowable. Cases like Hamilton vs. Whittaker, 29 Wash., 2nd 173 and United States Rubber Company vs. American Bonding Company, 86 Wash. 180, cited by the trustee are not applicable to the case at bar which is to enforce a cost plus contract. . . .
“James Construction Company seeks foreclosure of its lien for construction of a railroad spur to and upon the premises of the defendant, Midfield Packing Company in the sum of $7,248.16. From the evidence and under the law I find that this lien was timely filed and that it is a lien upon all the real property described in the lien notice. The foreclosure will be granted against such real property. It is claimed that this is a laborers’ lien and therefore entitled to preference over plaintiff’s lien under the provisions of Section 1141, Remington’s Revised Statutes. The pleadings and the evidence show that this claim is based upon a specific contract for a specific price to furnish both labor and materials.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jose Diaz v. Eric Hsueh
Court of Appeals of Washington, 2019
In re the Estate of Jason L. Patton
Court of Appeals of Washington, 2017
Summerhill Village Homeowners Ass'n v. Roughley
270 P.3d 639 (Court of Appeals of Washington, 2012)
Hosea v. Griffin
156 Wash. App. 263 (Court of Appeals of Washington, 2010)
Hosea v. Toth
232 P.3d 576 (Court of Appeals of Washington, 2010)
BNC Mortgage, Inc. v. Tax Pros, Inc.
46 P.3d 812 (Court of Appeals of Washington, 2002)
A.A.R. Testing Laboratory, Inc. v. New Hope Baptist Church
50 P.3d 650 (Court of Appeals of Washington, 2002)
Architects v. 1501 Pacific Associates
809 P.2d 206 (Court of Appeals of Washington, 1991)
Smith v. Simonarson, Visser, Zender, Brandt & Thurston
784 P.2d 552 (Court of Appeals of Washington, 1990)
Jones v. International Land Corporation Ltd.
755 P.2d 184 (Court of Appeals of Washington, 1988)
CH2M Hill, Inc. v. Greg Bogart & Co.
735 P.2d 1330 (Court of Appeals of Washington, 1987)
Mahalko v. Arctic Trading Co.
659 P.2d 502 (Washington Supreme Court, 1983)
Mahalko v. Arctic Trading Co.
628 P.2d 859 (Court of Appeals of Washington, 1981)
Jackson v. Flohr
227 F.2d 607 (Ninth Circuit, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
228 P.2d 466, 38 Wash. 2d 190, 1951 Wash. LEXIS 419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/homann-v-huber-wash-1951.