Holtzclaw v. Model Construction Co.

14 Fla. Supp. 94
CourtCircuit Court of the 4th Judicial Circuit of Florida, Duval County
DecidedMay 25, 1959
DocketNo. 58475
StatusPublished

This text of 14 Fla. Supp. 94 (Holtzclaw v. Model Construction Co.) is published on Counsel Stack Legal Research, covering Circuit Court of the 4th Judicial Circuit of Florida, Duval County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holtzclaw v. Model Construction Co., 14 Fla. Supp. 94 (Fla. Super. Ct. 1959).

Opinion

WILLIAM H. MANESS, Circuit Judge.

The complaint herein was first filed in the civil court of record of Duval County by plaintiffs, Troy F. Holtzclaw and Jimelle Holtzclaw, his wife, hereinafter referred to as “owners”, against defendant, Model Construction Company, a Florida corporation, hereinafter referred to as “contractor,” alleging the breach of an oral contract for the construction of a 16' x 24' addition to the owners’ property and seeking recovery for damages resulting therefrom not exceeding $3,000, the jurisdictional limit of that court. Along with its answer denying the essential allegations of the complaint and asserting that the oral contract was a “costs plus 10% agreement”, the contractor filed a counterclaim by which it claimed a lien for labor and materials furnished in accordance with its version of the contract and sought to invoke the equity jurisdiction of this court for the foreclosure of said lien. On proper motion, the entire cause was transferred to this court and the chancellor has heard the testimony presented by the parties on the issues made by the pleadings, considered the same and the exhibits filed in evidence, and now makes the following findings of fact and conclusions of law based thereon—

Findings of Fact

Over a period of several weeks, or more, prior to September of 1957, the owners had been considering the addition of a “Florida room” to their home at 2851 Myra Street, Jacksonville, and had talked with at least two builders about their desires and got estimates on the cost thereof ranging from $1,700 up. Finally, through a friend, Ed Palmer, they were put in touch with Benjamin Speetor, the president, owner and sole stockholder of the defendant corporation, also referred to as “contractor”. No plans or specifications were prepared by the owners but the contractor (Speetor) was told that they wanted a 16' x 24' room added, of concrete block construction, 11 windows, built-up roof (asphalt felt, tar and gravel), concrete floor with floor covering of wood-paneled interior and ceiling. The owners told the contractor what others had estimated the cost to the owners to be and the contractor said it could be built for $1,200 or “not over $1,500”. The owners said, “If you can do it for that figure, go to work”, with none of the more essential details of a valid contract specified than are above set forth.

[96]*96The contractor knew that price was the paramount consideration in the owners authorizing him to “go to work”. The contractor had plans prepared showing sufficient details to obtain a permit as required by the building department of the city of Jacksonville but such plans were not put in evidence and apparently did not even specify such details as the kind of wood paneling, number of windows, starting or completion date, contract price or quality of lalbor and materials. As to such details as were specified, such plans were apparently submitted solely for the purpose of obtaining a permit, since later developments show they were not strictly complied with. The contractor attempted to do the job and keep the costs down to $1,500, but from the beginning it is obvious that the owners and the contractor did not have a sufficient “meeting of the minds” to support a finding by this court as to the existence of a valid contract. Either in its effort to reduce costs, or through neglect, or both—

(a) The contractor failed to dig and pour the “footings” to the depth required by the city of Jacksonville, but this was overlooked by the inspector.
(b) The concrete workers left the concrete floor so rough that before the owners could have tile laid thereon, it had to be “stoned” to make it smooth.
(c) As the concrete block walls were put up the mortar joints were so uneven and so completely failed to match the mortar joints on the existing house that this work was condemned by the city inspector and had to be torn out and redone. Even when the work had been re-done, while it was passed by the inspector, there were still imperfections that show that the concrete block work was not done in a “good and workmanlike” manner.
(d) The carpenter work was subcontracted to one whose workmanship was so unsatisfactory that the owners finally stopped the work, but not until the roof was on and the interior walls were 90% paneled with V-joint paneling. There was a dispute as to the quality of the V-joint paneling and as to whether it should have been “pick-wick” paneling but since the V-joint paneling was not put up in a “good and workmanlike” manner, was out of plumb, and, because it was not properly attached to the concrete block walls, came loose and some fell off, it is not necessary to resolve this conflict because it had to be replaced.
[97]*97(e) Instead of 11 windows, only 5 were installed and these were set into the walls without sufficient clearance to operate the “levers” or “cranks,” which open and close the windows, after the paneling was installed. Special woodwork had to be made at owners’ expense to make the windows usable.

The contractor also had its troubles with the owners, who, after the work got underway, saw that their dreams and the contractor’s ideas and promises did not coincide. This friction no doubt kept Mr. Spector away from the job when he should have been present and led him to make promises he knew could not be fulfilled at later stages of construction. On the other hand, the'owners felt re-assured by Mr. Spector’s frequent statements that they would be pleased when the work was finished “if you’ll just let the men alone.” For this reason and blind faith, the owners suffered through the various stages of construction, still hoping that somehow the job would turn out all right, as the points of dissatisfaction grew to the breaking point on or about the last of October, 1957, when they stopped the carpenter-subcontractor when the paneling was 90% complete.

Finally, on October 31,1957, a notice was placed on the premises by the city building department that “part of this work is not according to law and is therefore condemned,” and further stated— “approved plans not being followed, windows and paneling out of -and plumb, workmanship is bad.” (Pit’s, exh. no. 1). That this is true is further evidenced by looking at plaintiffs’ exhibit no. 4.

Apparently, the owners still had some hope that the job would be satisfactorily completed as late as October 27, 1957, at which time they made a voluntary payment to the contractor in the amount of $605.68. This payment was actually made to Benjamin Spector personally but by stipulation is to be considered as having been made to the contractor.

After the notice of condemnation, the contractor offered to send another carpenter to “do everything needed” but the owners refused in order to obtain advice of counsel. Without making any further attempt to get the work corrected and underway again, several weeks later the contractor sent someone to pick up the materials left on the job but said nothing to the owners who turned the person away not knowing who he was or what authority he had to remove the contractor’s materials. Neither did the owners call on the contractor to do anything further and undertook to complete the work themselves.

[98]*98Expert testimony showed that the reasonable value of the project ranged from an actual cost of $2,500 to $3,500, including a reasonable profit.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
14 Fla. Supp. 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holtzclaw-v-model-construction-co-flacirct4duv-1959.