Holmgren v. Werner

26 So. 384, 51 La. Ann. 1476, 1899 La. LEXIS 584
CourtSupreme Court of Louisiana
DecidedJune 12, 1899
DocketNo. 12,884
StatusPublished

This text of 26 So. 384 (Holmgren v. Werner) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holmgren v. Werner, 26 So. 384, 51 La. Ann. 1476, 1899 La. LEXIS 584 (La. 1899).

Opinion

The opinion of the court was delivered by

Watkins, J.

In the original case the plaintiff, Holmgren, a builder, instituted suit against Robert Werner and Victor Werner, the owners ■of certain real estate situated on Constance street, in the city of New Orleans, for the erection and construction of two houses, for which he demanded judgment for the sum of $2,534.19, with the recognition of lien and privilege on the buildings and grounds upon which same .are situated.

Plaintiff alleges that said work was done and said houses were constructed under and in pursuance of a contract notarial in form, and bearing date July 2nd, 1896; as well as in conformity with plans and .specifications which were part thereof.

That he. constructed, erected and. equipped said structures, as well as furnished the labor and materials /designated in the contract and plans and specifications; and that for said work he was to receive $6000, of which there is still due him $945.00..

That at the verbal request, and under the instructions of the defendants, he performed certain additional extra work to the amount of $1589.19 — die two items making the sum for which judgment is claimed.

The following statement is then made, viz:

“All of same were ordered by said defendants notwithstanding the “stipulation that no extra work was to be done, unless upon the “written order of the owners, the said (defendants) agreeing with “ petitioner, that said clause in the contract should be abrogated, 'and instructing (him) to proceed as verbally requested, etc.”

The contract, plans and specifications are annexed to the petition.

The defendants excepted to the prematurity of the suit, on the [1478]*1478ground, that it was brought within fifteen days from the delivery of the buildings in a state of completion as required by the terms of the-contract; and further on account of vagueness in the allegations as to extra work performed and extra services rendered — no detailed statement thereof having been annexed to the petition.

Eor answer they plead the general issue and aver the truthfulness of their allegations in the suit of Y. & R. Werner vs. 0. Holmgren et al, for damages for non-compliance with and violation of saidbuilding. contract.

Plaintiff filed a supplemental petition in which he claimed an additional sum of $488.24 -on his written agreement; and a further sum of $259.21 for extra work — for all of which he has a lien and privilege on the building and ground.

The claim of plaintiff is then, as follows, viz:

On the building contract................................$1433.24

For extra work.......................................... 1848.40

Total ...............................................$3281.64

The two causes of Holmgren vs. Werner Bros., and Werner Bros, vs. Holmgren, were consolidated; and subsequently the other causes of Hinderer vs. Holmgren; Lewis & Co. vs. Holmgren; Ramos Lumber Co. vs. Holmgren; J. D. Burkhardt vs. Holmgren, and Louisiana Glass and Mirror Works, Limited, vs. Werner Bros., were likewise cumulated therewith, and all were tried and decided as one single litigation — the respective claims being germane to each other.

In V. & R. Werner vs. Holmgren et al. — which was brought within one week after the suit of Holmgren vs. V. & R. Werner was filed— claim is made that Holmgren had violated his contract in several particulars, viz:

1st. That the painting is inferior, the material used of bad quality, and in some cases there were only two coats, whereas three were called for, for which a deduction is claimed of........ $300.00

2nd. For the omission of electric bells.................... 80.00

3rd. For omission of top-bolts on windows................ 25.00

4th. For picture-mouldings in upper stories.............. 20.00

5th. For crooked- eampo-board.........-.................. 750.00'

6th. Bad material in brick work......................... 250.00‘

7th. For unfinished water closets...................... - 50.00

8th. Bad' cement,' etc................................... 30.00

[1479]*14799th. Bad weather-boarding........• ..................... 300.00

10th. Omission of shed, etc.............................. 800.00

11th. Demurrer or liquidated damages.................... 215.00

The whole aggregating......... $2,360.00

They invoke the clause of the building contract which requires Holmgren, as builder and contractor, to. deliver the buildings complete on or before the 1st of October, 1896, and in default of which he was ' obliged to pay five dollars per day as liquidated damages during such period of time as same should remain in an ineompleted condition.

The further allegation is then made that the contractor "'‘made “ it necessary for (them), under the stipulations of the contract, to “take possession of the premises on November 23rd last, (1896), in “ order to protect himself against further damage.”

In Hinderer vs. Holmgren, claim is made for $115.00, for constructing and erecting upon the aforesaid premises fifty feet of iron fence; and having made the Werner Bros, parties, he prays judgment against them and Holmgren. '

In Lewis & Co. vs. Holmgren, claim is made for $123.00 for building a cistern, and he asks for judgment therefor against the Werner Bros, and Holmgren.

In Ramos Lumber Co. vs. Holmgren, claim is made against the Werner Bros, and Holmgren for $590.00, for factory work of different kinds, and materials used in the building and construction of said houses.

In Louisiana Glass and Mirror Works, Limited, vs. V. & R. Werner, claim is made for $113.00 for goods and merchandise sold them, and which were employed and used in said buildings.

In Burkhardt vs. Holmgren, claim is made for a balance of $196.60, for work and materials furnished to and used in said two buildings, and for which he prays a judgment accordingly.

In these consolidated suits, the following judgment was rendered, viz:

1st. In Holmgren vs. Werner Bros., in favor of the plaintiff and against the two defendants jointly, for the sum of $2,362.85.

2nd. In Werner Bros. vs. Holmgren, in "favor of the plaintiff and against the defendant, for the sum of $37.40; and in favor of intervenor, McWilliams, and against Werner Bros, for $52.66.

3rd. In Louisiana Glass and Mirror Works, Limited, vs. Werner [1480]*1480Bros., in favor of the plaintiff and against the defendants jointly for $113.00.

4th. In Hinderer vs. Werner Bros., in favor of the plaintiff and against the defendants jointly, in the sum of $115.00.

5th. In Lewis & Co. vs. Werner Bros., in favor of the plaintiffs, and against the defendants jointly, in the sum of $123.00.

6th. In Ramos Lumber Co. vs. Werner Bros., in favor of the plaintiffs and against the defendants jointly, in the sum of $590.00.

7th. In Burkhardt vs. Werner Bros., in favor of the plaintiff and against the defendants jointly, in the sum of $196.60.

Sth.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
26 So. 384, 51 La. Ann. 1476, 1899 La. LEXIS 584, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holmgren-v-werner-la-1899.