Holmes v. Boydston

1 Neb. 346
Nebraska Supreme Court·Decided July 1, 1871·Published·Cited by 3 cases

Opinion

Crounse, J.

On the trial of this cause in the District Court several exceptions were taken to the allowance and rejection of testimony, as well as to the charge of the judge; the more important of which will be noticed.

The action was originally begun by Arba Holmes as sole plaintiff. Subsequently, by an order of the court, Gould and Powell, his former partners, were joined with him. Exception was taken to the reading of certain depositions taken in the cause prior to this amendment as to parties. The testimony ta,ken in the depositions related to the value, in Chicago, of certain burr millstones, and was alike applicable to the case after, as well as before the amendment, and there is no substantial reason for excluding the deposition. — Vincent v. Conklin, 1 E. D. Smith, 203.

By the terms of the written contracts under which the plaintiffs below were to furnish the machinery and place the same in the mill building of the defendants, the defendants v;ere to have the building completed,- with floors and [355] stairs ready for the machinery, by the first day of July, 1868. When the plaintiff closed his testimony, it clearly appeared that the building was not completed till long after the first of July, and .that the defendants told Powell, one of the plaintiffs, that they were disappointed in getting the stone work done ; that the plaintiffs had been there a month or more before the stairs and floors were all in; that not until the election in October was the mill building completed, and that the plaintiffs got the mill running by the last of November, or the early part of December. With a view, no doubt, to establish a claim for damages' for not having the machinery put up by the first day of September, as required by the contract, among the first questions asked by defendant’s counsel was : “When were Holmes, Gould and Powell first ready to go to Boydston and Heth’s mill with the machinery, and to put it up ?” The question was excluded, the court remarking that under the contract and the case as then made, the defendants were not entitled to show what the mill might have earned if running by September first. This is correct. As the case-then stood, the defendants appeared as having failed to complete the building till a month or more after the time even when the machinery was to be in. They could not lay a foundation for damages upon their own wrong. Until this showing of the plaintiffs was questioned and a foundation laid, the court was right in excluding this testimony as immaterial.

Further along in the course of the trial the defendant’s counsel asked of a witness : “ What would have been the average profit of that mill, fully completed according to contract, from the first day of September to the time when the plaintiffs turned the same over to the defendants ?” This was objected to “ as incompetent on the ground that it was immaterial under the written contract offered in evidence.” With the written contract requiring Holmes, [356] Gould & Co. to have the machinery in running order by September first, I cannot understand the force of this peculiar objection. But as being wholly immaterial in the case as then made, the court correctly rejected it, as it might have done on his own motion in accordance with the prior holding, the case remaining unchanged with respect to the defendant’s failure to have the mill in readiness for the machinery.

Again, a witness is asked by the defendant’s counsel, “ How much did the defendants pay for hauling machinery from the mill back to the foundry to be finished and completed, and for hauling the same from the foundry to the mill the second time ?” The question was asked for the purpose of establishing a claim for extra hauling done by the defendants in taking- a shaft back to the foundry to be refitted. Without stopping to inquire whether, under the plain terms of the contract, wherein they obligate themselves “ to do or have done all the hauling of said machinery as is necessary for the completion of the works,” they could make any charge for extra hauling, it is enough that proof of what they may have paid for such hauling is not evidence of its value. They could, m any event, claim only what such labor was worth. What was paid might be more or less. The court was right in sustaining the objection.

The same may be remarked in reference to the ruling upon the question as to “what was paid” for extra board of hands employed in replacing imperfect machinery.

Free access — add to your briefcase to read the full text and ask questions with AI

Holmes v. Boydston, 1 Neb. 346 (Neb. 1871).

1 Neb. 346 (Holmes v. Boydston) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Salmer v. Lathrop
72 N.W. 570 (South Dakota Supreme Court, 1897)
Denver, T. & G. R. v. Hutchins & Hyatt
48 N.W. 398 (Nebraska Supreme Court, 1891)
Union Pacific Railway v. Ogilvy
18 Neb. 638 (Nebraska Supreme Court, 1886)