Holloway v. Wilson, Unpublished Decision (8-4-2000)

CourtOhio Court of Appeals
DecidedAugust 4, 2000
DocketC.A. Case No. 99 CA 76, T.C. Case No. 96 CV 599.
StatusUnpublished

This text of Holloway v. Wilson, Unpublished Decision (8-4-2000) (Holloway v. Wilson, Unpublished Decision (8-4-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holloway v. Wilson, Unpublished Decision (8-4-2000), (Ohio Ct. App. 2000).

Opinion

OPINION
Defendant-Appellant Barton Wilson appeals the trial court's judgment ordering him to pay Plaintiffs-Appellees Dwight and Dennis Holloway the sum of $6,994.98 plus interest, which sum was determined by the court to be the amount in default on a land contract between the parties. For the following reasons, we agree with Wilson, and reverse the judgment of the trial court.

The land contract at issue was originally entered into by the Holloways' partnership, HH Auto, the vendor, and Dome, Inc., the vendee. On January 22, 1995, Dome assigned its right, title, and interest in the land contract to Wilson; the Holloways consented to the assignment and their signatures appear on the assignment document. The assignment agreement does not contain any language showing Wilson assumed Dome's obligation to make the monthly installment payments on the land contract, but practically speaking, Wilson was aware that if he failed to make the payments he would be placing his interest in the land at risk. The land contract provided, in pertinent part, as follows:

INTEREST ON UNPAID BALANCE — the interest rate shall be calculated at Ten percent (10.0%) on the unpaid balance. In the event any monthly payments set forth in paragraph five (5) hereunder are more than Sixty (60) days delinquent, the interest rate shall escalate to Thirteen Percent (13%) per annum on the entire unpaid principal together with any unpaid interest which is due on said monthly installment.

PAYMENT PROVISIONS — the vendee shall make monthly payments to the vendors of principal and interest, which monthly payments shall be made before the 1st of each month, with the first payment due on or before December 1, 1994, and continuing for a period of sixty (60) successive payments. Said monthly payments shall be $2,643.01 which includes both principal and interest, with the interest being paid first from said sum and the balance being used to reduce the outstanding principal. This payment is based upon a ten (10) year amortization. On or before December 1, 1999 all unpaid principal and interest shall be due. This 61st payment is a balloon payment.

* * *

GRACE PERIOD — the vendee has a sixty (60) day grace period in which to make any payments provided herein except for the down payment. Any payment not made when due or within the sixty (60) day grace period immediately following, is a default in the contract and will permit the vendor to take such legal actions as may be available to him, including but not limited to foreclosure on the land contract.

Neither the contract nor the assignment agreement included an acceleration clause.

The dispute between the parties centers primarily on the payment that was due on July 1, 1996. That payment was placed in the mail on August 29, 1996, postmarked August 30, 1996, and received by the Holloways on September 3, 1996. The Holloways accepted the late payment without protest and then filed a complaint for foreclosure against Wilson and others not relevant to this appeal on September 11, 1996. Wilson continued to make the monthly installments on the land contract, and the Holloways continued to accept the payments until the Spring of 1998.

At trial, the Holloways claimed that even after their acceptance of the late July payment, additional interest had accrued due to the delinquency and that the accrued interest would have had to have been paid in addition to the monthly installment amount in order to cure the default. According to the Holloways, Wilson's failure to pay more than the monthly installment amount due for July meant that there remained a deficiency on the land contract equal to the amount of the accrued interest caused by the late payment. In addition, the principal amount owing on the land contract after the September 3 payment was $6,994.98 more than what an amortization schedule showed the balance should be on that date. In light of those facts and because the July 1 payment was allegedly made sixty-one days late and thereby put the contract into default, the Holloways claimed to be entitled to foreclosure.

Wilson testified that he had never agreed, in writing or orally, to assume responsibility for the monthly installments on the land contract. As such, the Holloways' lawsuit against him personally was improper as it sought from him something he had no legal obligation to pay. Wilson also claimed that any discrepancy between the principal balance shown on the amortization schedule and the actual principal balance of the account on any one date is irrelevant for purposes of determining whether the account was in default because the amortization schedule was never incorporated into the land contract or the assignment agreement. Moreover, Wilson argued that the Holloways were not the real parties in interest since the lawsuit had been filed by them in their personal capacities, and the land contract and assignment agreement had been signed by them in their capacities as partners in HH Auto Parts. Wilson also contended that as soon as the Holloways accepted the payment on September 3, any default was cured thus depriving the Holloways of the right to pursue foreclosure.

On August 13, 1999, the trial court found as follows:

* * * [T]he Plaintiffs['] continued acceptance of payments from the Defendant has resulted in a waiver of Plaintiffs['] right to foreclose.

Regarding the amount of money owed to the Plaintiff, the Defendant owes the amount due and owing under the terms of the contract. On September 3, 1996, there was a delinquent balance of $6,994.98. Since that date, the Defendant has paid the contracted monthly installment of $2,643.01. The contract does not contain an acceleration clause. Therefore, the Plaintiffs cannot demand the total balance due under the contract, but only the amount which is delinquent.

Based on the foregoing, IT IS * * * ORDERED, that the Plaintiffs recover from the Defendant, Barton L. Wilson, the sum of $6,994.98 plus interest at the rate of 13 per cent per annum from September 3, 1996.

The parties are now before us on Wilson's timely appeal in which he asserts four assignments of error. The Holloways have also asserted a cross assignment of error relating to the trial court's determination that they had failed to bring forth sufficient evidence to warrant a judgment against Wilson for their expenses and fees incurred in pursuing the foreclosure. We will address Wilson's assigned errors in an order that facilitates our discussion. Because we sustain each of Wilson's four assignments of error, it is unnecessary for us to address the Holloways' cross assignment of error.

Assignments of Error
Wilson's fourth assignment of error is presented as follows:

The lower court erred in granting judgment to the Appellees who were not proper parties plaintiff in the action before the lower court.

In this assignment of error, Wilson argues that the Holloways, who initiated suit against him in their personal capacities, are not the real parties in interest because they were not signatories to the contract or the assignment agreement in that capacity. Instead, both documents were signed by the Holloways in their representative capacities as partners in HH Auto Parts. We agree.

As the Ohio Supreme Court has repeatedly stated, "[i]t is elementary that every action shall be prosecuted in the name of the real party in interest." Papiernik v. Papiernik (1989),45 Ohio St.3d 337, 344; State ex rel. Dallman v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cleveland Paint & Color Co. v. Bauer Manufacturing Co.
97 N.E.2d 545 (Ohio Supreme Court, 1951)
Oda v. Davis
611 N.E.2d 933 (Ohio Court of Appeals, 1992)
State ex rel. Dallman v. Court of Common Pleas
298 N.E.2d 515 (Ohio Supreme Court, 1973)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Papiernik v. Papiernik
544 N.E.2d 664 (Ohio Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Holloway v. Wilson, Unpublished Decision (8-4-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/holloway-v-wilson-unpublished-decision-8-4-2000-ohioctapp-2000.