Hollister Ranch Owners' Ass'n v. Federal Energy Regulatory Commission

759 F.2d 898, 245 U.S. App. D.C. 172
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 16, 1985
DocketNos. 84-1010, 84-1029
StatusPublished
Cited by6 cases

This text of 759 F.2d 898 (Hollister Ranch Owners' Ass'n v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hollister Ranch Owners' Ass'n v. Federal Energy Regulatory Commission, 759 F.2d 898, 245 U.S. App. D.C. 172 (D.C. Cir. 1985).

Opinions

Opinion for the Court filed by Circuit Judge MIKVA.

Opinion concurring in part and dissenting in part filed by Senior Circuit Judge MacKINNON.

MIKVA, Circuit Judge:

At issue in this case is the Federal Energy Regulatory Commission’s conditional approval of a proposal to construct a liquified natural gas (“LNG”) terminal near Point Conception, California. FERC approved the project in 1979, but this court remanded the matter to the Commission in 1980 for further consideration of seismic data. In 1983, following new evidentiary hearings, FERC again found the site “seismically suitable.” Petitioners, all of whom live or own property near Point Conception, challenge the merits of that determination and also contend that the 1979 and 1983 orders should be vacated as moot because of alleged abandonment of the proposal by its original backers.

We agree that the 1979 order must be vacated as moot, and we vacate the 1983 order on different grounds.

I.

In the late 1970’s, a group of companies applied to FERC and to the California Public Utilities Commission (“CPUC”) for permission to construct and operate an LNG terminal at Little Cojo Bay, near Point Conception, California. The terminal was to receive and regassify LNG shipped from Alaska and Indonesia.

Concerns were raised about seismic risks at the proposed site from the very beginning. In April 1978, a geologist hired by the Hollister Ranch Owners’ Association (“Hollister”) found an active earthquake fault on the site, and several other on-site active faults have been discovered since then. In 1978, the CPUC nonetheless approved the project but conditioned its approval on further seismic studies to be conducted by the applicants. Adopting the recommendations of its Administrative Law Judge (“ALJ”), FERC did the same in 1979, despite the position of the Commission’s staff that no LNG terminal should be approved on any site containing an active earthquake fault. The staff adhered to this position throughout the later proceedings on remand. See Pacific Alaska LNG Co., 19 FERC Rep. (CCH) ¶ 63,086, at 65,270 (June 23, 1982).

The staff reasoned that “[t]here is such uncertainty in the phenomenon of surface faulting that the current state-of-the-art is inadequate to allow the safe design of an LNG facility near an active fault.” Pacific [174]*174Alaska LNG Co., 8 FERC Rep. (CCH) ¶ 63,032, at 65,365 (Aug. 13, 1979). The ALJ rejected this “per se or absolutist” position as unacceptable, based in part on his impression of the need for an LNG terminal in California. He found that there was “a pressing need” for the gas volumes at issue, and that there were “no available alternatives” to the LNG proposal. Id. at 65,319. In connection with the staff’s argument that the mere presence of an on-site earthquake fault should disqualify Little Cojo Bay as an acceptable site for an LNG facility, the ALJ noted:

... Staff’s position is based on very remote possibilities and a refusal to consider the geoseismic particulars of a given site location. This is especially disturbing since the entire coast of California is seismically active and Staff’s per se approach threatens to impose on the state of California a no-growth energy policy respecting LNG facilities directly contrary to the interest of the citizens of that state as expressed in the LNG Terminal Act.

Id. at 65,346.

Nevertheless, the AU conditioned his approval of the project on the applicants’ completion of further seismic investigations at the site. He also conditioned his approval on prompt completion of the project: gas sales from the facility had to commence by February 15, 1983. See id. at 65,391. FERC affirmed the ALJ’s conditional approval and adopted his decision without relevant changes. See Pacific Alaska LNG Co., 9 FERC Rep. (CCH) ¶ 61,041 (Oct. 12, 1979).

Several parties, including the current petitioners, sought review in this court of FERC’s 1979 approval of the Point Conception proposal. While the case was pending, additional information became available on the seismic condition of the Little Cojo site. In April 1980, the court granted Hollister’s motion to remand the matter to FERC to allow the Commission to consider the new information in the first instance.

In response to the remand, FERC ordered new evidentiary hearings on the seismic issues. By this point in the proceedings, however, some participants had dropped out of the project, and the applicants had been forced to give up their rights to a dedicated supply of Indonesian gas. The project sponsors nonetheless “remain[ed] committed” to the project, and the Commission therefore decided to proceed with consideration of Little Cojo’s seismic suitability:

The seismic issues at the Little Cojo site ... fall exclusively within the Commission’s jurisdiction, are ripe for decision now, and will entail a significant measure of time for hearing and analysis. Accordingly, ... the Commission will defer consideration of nonseismic issues at this time, pending resolution of the seismic issues by our Commission and the CPUC....

Pacific Alaska LNG Co., Nos. CP75-140 et al., slip op. at 4 (March 2, 1981).

After hearing new evidence, the ALJ determined that “the remand record does not warrant a change in the conclusion of the prior Initial Decision that the potential seismic hazards at the site do not present unacceptable risks to public safety or project reliability.” Pacific Alaska LNG Co., 19 FERC Rep. (CCH) ¶ 63,086, at 65,272 (June 23, 1982). He therefore affirmed the 1979 Initial Decision “to the effect that the Little Cojo Bay site is seismically suitable for the safe and reliable construction and operation of an LNG receiving terminal.” Id. at 65,288.

The Commission affirmed the ALJ’s decision. Pacific Alaska LNG Co., 25 FERC Rep. ¶ 61,005 (Oct. 4, 1983). In response to Hollister’s argument that the proceedings should be dismissed as moot because the industrial sponsors were no longer in a position to go forward, FERC noted that the sponsors might choose to proceed at some time in the future, and concluded that a resolution of the seismic issues could therefore prove useful:

If we find Little Cojo to be seismically suitable, they can proceed with the projects when they are needed in the future; if we find the site to be unsuita[175]*175ble, further efforts to preserve the projects would not be taken____ [A]ll we can say with any certainty now is that the future is uncertain. At some point, LNG may be needed to meet the requirements of gas consumers in California.

Id. at 61,034.

II.

Intervening in this case, the People of the State of California and the California Public Utilities Commission contend that FERC’s 1979 and 1983 orders are not yet ripe for review because they are merely intermediate steps in an ongoing administrative process. In essence, California argues that petitioners should have to wait until a viable . LNG project is actually approved before challenging the 1979 and 1983 orders.

Even assuming that the collateral challenge envisioned by California would not be time-barred, we do not agree that review at this time would be premature. Cf. Baltimore Gas & Electric Co. v. NRDC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
759 F.2d 898, 245 U.S. App. D.C. 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hollister-ranch-owners-assn-v-federal-energy-regulatory-commission-cadc-1985.