Hollerbach v. United States

47 Ct. Cl. 236, 1912 U.S. Ct. Cl. LEXIS 117, 1901 WL 933
CourtUnited States Court of Claims
DecidedFebruary 12, 1912
DocketNo. 29952
StatusPublished
Cited by2 cases

This text of 47 Ct. Cl. 236 (Hollerbach v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hollerbach v. United States, 47 Ct. Cl. 236, 1912 U.S. Ct. Cl. LEXIS 117, 1901 WL 933 (cc 1912).

Opinion

Barney, J.,

delivered the opinion of the court:

This is a suit for balances alleged to be due upon a contract for repair work on Dam No. 1, Green River, Ky. The following is a summary of the several claims made by the plaintiffs:

Loss oí profits by deficiency in eartli excavation furnished
them_ $896. 60
Cost of obtaining material warranted by paragraph 33 to be ■ present at the site- 2,184. 08
[242]*242Excess of cost of excavating sediment over excavation of material warranted by paragraph 33- $.295. 89
Excess of cost of excavating crib in the backing over the cost of excavating material warranted by paragraph 33_ 5, 827. 52 Deduction for inspection_ 800. 00
Total_ 10,004.09

Before proceeding to discuss the merits of the case it is necessary to dispose of the point raised by the defendants that this suit should be dismissed because, as it is claimed, the contract upon which it is founded was transferred within the provision of section 3737 of the Revised Statutes, which is as follows:

“No contract or order, or any interest therein, shall be transferred by the party to whom said contract or order is given to any other party, and any such transfer shall cause the annulment of the contract or order transferred, so far as the United States are concerned. All rights of action, however, for any breach of such contract by the contracting parties are reserved to the United States.”

The findings upon this subject show that in April, 1903, but after the execution of the contract on question, a corporation called the Hollerbach & May Contract Co. was organized under the laws of the State of Indiana, 90 per cent of the stock'of which was taken by the plaintiffs and the balance by relatives. This corporation performed the work called for under the contract to the extent that the accounts relating to its performance were carried on in its books of account; but the claimants continued in active personal charge of the work until its conclusion; all of the correspondence with the Government relating to it was carried on in their name, and all payments were made to them. The partnership of Hollerbach & May continued, at least so far as this contract was concerned, until its completion, and the corporation did all that was done by it for and under the direction of the partnership. We do not think these facts show any transfer of said contract or any' interest therein within the meaning of section 3737 of the Revised Statutes, or, in fact, of any transfer of any interest in the contract whatsoever. . The plaintiffs never relinquished the complete control and management nor any of the emolu-[243]*243merits of the contract, and the work done by the corporation was not different in character or effect from that of any other employee. We do not think the cases cited by the Government upon this question have any application to a case like this, but rather that it is controlled by the reasoning in Hobbs v. McLean (117 U. S., 567-575).

We will now consider the several items of the plaintiffs’ claim in the order as hereinbefore given.

The first item claimed is for loss of profits by reason of the deficiency in the earth excavation furnished. The amount of earth excavation required by the contract was 3,970 cubic yards, with a permissible increase or decrease of 20 per cent, thus leaving a minimum of 3,176 cubic yards. The findings show that the plaintiffs were furnished 1,183.55 cubic yards of earth excavation and 633.5 cubic yards of other material classified as crib excavation, for which they were paid at the contract price, thus making in all 1,817.05 cubic yards excavated, and this amount deducted from the minimum as provided in the contract leaves 1,358.95 cubic yards’ deficiency, on account of which the plaintiffs are entitled to recover the profit which they would have made if the earth excavation had been as represented, and which profit the findings show to be $475.63, and this item is allowed in that sum.

The next three items of the plaintiffs’ claim are for damages alleged on account of what is contended to be a breach of warranty under paragraph 33 of the specifications, and can be grouped and considered together, as they all depend upon the construction of the same provisions in the specifications. The following are the paragraphs of the specifications which are to be considered in the decision as to these items:

“ 20. It is understood and agreed that the quantities given are approximate only, and that no claim shall be made against the United States on account of any excess or deficiency, absolute or relative, in the same. Bidders, or their authorized agents, are expected to examine the maps and drawings in this office, which are open to their inspection, to visit the locality of the work, and to make their own estimates of the facilities and difficulties attending the exe[244]*244cution of the proposed contract, including local conditions, uncertainty of weather, and all other contingencies.
' sfc % $ %
“33. The present dam, a wooden crib structure, is 528 feet long between abutments and about 52 feet wide at its base. The expected depth of concrete work is shown on the blue prints, but it may be made greater as the condition of the old timber may render it necessary. The work shall be carried out in sections, generally from 50 to 100 feet long, and no more of the old work shall be torn out than, can lie rebuilt in a few days in case of necessity. 'All the exterior surfaces of the concrete shall be faced with the facing described in paragraph 59, which shall be placed before the concrete below has set, and shall be smoothly finished off. The dam is now backed for about 50 feet with broken stone, sawdust, and sediment to a height of within 2 or 3 feet of the crest, and it is expected that a cofferdam can be constructed with this stone, after which it can be backed with sawdust or other material. The excavation behind the dam will be required to go to the bottom, and it is thought that a slope of 1 horizontal to 1.2 vertical will give ample room.
»[! í
“60. Blue prints. Blue-print drawings showing the method of construction may be seen at this office; they shall form a part of these specifications and shall not lie departed from except as may be found necessary by the condition of the old timber encountered.
$ $ * * *
“70. Investigation. It is expected that each bidder will visit the site of this work, the office of the lock master, and the office of the local engineer and ascertain the nature of the work, the general character of the river as to floods and low water, and obtain the information necessary to enable him to make an intelligent proposal.” ■
‡ $

It is contended by the plaintiffs that the following extract, from paragraph 33 above quoted, is a representation amounting to a warranty:

“The dam is now backed for about 50 feet with broken stone, sawdust, and sediment to a height of within 2 or 3 feet of the crest.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mortenson v. United States
29 Cont. Cas. Fed. 82,005 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ct. Cl. 236, 1912 U.S. Ct. Cl. LEXIS 117, 1901 WL 933, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hollerbach-v-united-states-cc-1912.