Holland Constr. Co. v. Lampson

CourtMontana Supreme Court
DecidedDecember 10, 1974
Docket12676
StatusPublished

This text of Holland Constr. Co. v. Lampson (Holland Constr. Co. v. Lampson) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holland Constr. Co. v. Lampson, (Mo. 1974).

Opinion

No. 12676

I N THE SUPREME COURT O THE STATE O M N A A F F OTN

HOLLAND CONSTRUCTION COMPANY,

P l a i n t i f f and A p p e l l a n t ,

-vs - NEIL F. LAMPSON,

Defendant and Respondent.

Appeal from: D i s t r i c t Court of t h e T h i r t e e n t h J u d i c i a l D i s t r i c t , Honorable A. B. Martin, Judge p r e s i d i n g .

Counsel of Record:

For Appellant :

Evalyn B. Carson argued, B i l l i n g s , Montana

For Respondent :

Moulton, Bellingham, Longo and Mather, B i l l i n g s , Montana Ward Swanser argued, B i l l i n g s , Montana

- - -

Submitted: November 14, 1974

Decided: DEC 1 0 1974 Filed : M r . J u s t i c e John C. Harrison d e l i v e r e d t h e Opinion of t h e Court.

This i s an appeal from a judgment adverse t o p l a i n t i f f entered i n t h e d i s t r i c t c o u r t , Yellowstone County. The matter was t r i e d by t h e c o u r t s i t t i n g without a jury. P l a i n t i f f Holland Construction Company, Inc. a l l e g e d an indebtedness t o i t by defendant N e i l F. Lampson, Inc. f o r l a b o r , p a r t s and m a t e r i a l s furnished on t h e r e p a i r of equipment owned by Lampson. On appeal, p l a i n t i f f Holland b r i n g s t h r e e i s s u e s :

1. I s t h e r e s u b s t a n t i a l evidence t o support t h e f i n d i n g s of f a c t and conclusions of law of t h e t r i a l judge who found t h a t t h e reasonable value of t h e s e r v i c e s of Holland Construction Co. was $18,292.45? 2. Did t h e t r i a l c o u r t err i n r e f u s i n g t o allow any testimony o f f e r e d by p l a i n t i f f ? 3. Was t h e c o u r t c o r r e c t i n applying t h e r u l e t h a t p l a i n t i f f was e n t i t l e d t o recover only t h e reasonable value of t h e s e r v i c e s performed? Holland a l l e g e d t h a t Lampson was indebted t o Holland f o r $33,557.82. Lampson i n i t s answer admitted c e r t a i n work was per- formed on i t s equipment; t h a t t h e r e was no c o n t r a c t between t h e p a r t i e s f o r t h e work performed; and t h e r e f o r e Holland was e n t i t l e d t o recover only f o r reasonable s e r v i c e s rendered. The t r i a l c o u r t found t h e amount owed Holland t o be $18,292.45. P r i o r t o submission of i t s statement f o r t h e t o t a l c o s t of t h e r e p a i r work t o t h e Lampson crane t h e r e was no d i s c u s s i o n of t h e t o t a l c o s t , o r hourly c o s t f o r t h e work done between t h e p a r t i e s , u n l e s s i t could be s a i d t h a t ~ o l l a n d ' sstatement t h a t t h e shop was It competitive i n t h e area", was a d i s c u s s i o n of c o s t . The work took approximately 30 days of shop work. When t h e statement was submitted t o Lampson, it was considered e x o r b i t a n t and Lampson refused t o pay. Holland a l l e g e s i t i s e n t i t l e d t o recover f o r a l l time spent by i t s s t a f f of t h i r t e e n employees, plus o f f i c e s t a f f , spent on t h e job. Lampson a l l e g e s t h e work could have been performed i n f a r l e s s t i m e and t h a t Holland i s only e n t i t l e d t o recover f o r t h e reasonable number of hours it would t a k e t o perform t h e job. A t t r i a l Holland introduced time c a r d s t o show t h e number of hours worked by i t s personnel t o e s t a b l i s h what was a reasonable hourly f i g u r e . N o t h e r testimony was introduced t o support t h e o reasonableness of t h e statement submitted. A problem a r o s e as t o t h e t i m e c a r d s i n t h a t they w e r e d i s c r e d i t e d because of t h e manner i n which they were kept and t h e obvious e r r o r s which appeared on t h e f a c e of t h e cards. One d i f f i c u l t y was t h a t due t o t h e inclement weather t h e time clock f r o z e and had t o be r e p a i r e d . Another was t h a t t h e workers were supposed t o keep t h e i r job time a l l o c a t e d t o t h e various jobs they worked on during t h e day, b u t when t h e c a r d s were checked t h e t i m e s w r i t t e n i n on t h e various c a r d s ap- peared t o be i n only one person's handwriting. A s a r e s u l t , the t r i a l c o u r t r e j e c t e d t h e time card evidence a s proof of reason- ableness of t h e t o t a l job c o s t inasmuch a s Holland o f f e r e d no o t h e r explanation f o r t h e time required t o perform t h e work on t h e crane. I n an e f f o r t t o a s c e r t a i n a proper f i g u r e f o r t h e amount owed Holland, t h e c o u r t viewed ~ o l l a n d ' smachine shop o p e r a t i o n ; checked t h e crane i t s e l f t o determine t h e work performed; and, a f t e r s o doing concluded t h e time charged was excessive, although i t accepted ~ o l l a n d ' sf i g u r e s on t h e proper hourly charge. Lampson introduced a s a witness one Draper, i t s foreman, who was present when most of t h e work was done. Draper t e s t i f i e d t h a t 80% of t h e work was done on t h e crane within t e n days, a f t e r about 313 man hours. The b i l l submitted showed 1300 man hours. Lampson a l s o introduced t h e testimony of an e x p e r t , one Peterson from an independent machine shop i n Portland, Oregon, who t e s t i f i e d a s t o , i n h i s opinion,the number of hours reasonable t o do t h e worksre- quired. Lampson introduced o t h e r testimony t o support P e t e r s o n ' s testimony and compared t h e number of hours charged by Holland with hours charged by o t h e r machine shops f o r s i m i l a r work. Appellant ~olland's first issue questions the sufficiency of the evidence to support the trial court's findings of fact and con- clusions of law. This Court has long held that it will uphold a trial court's findings unless the evidence decidedly and with decisive clarity predominates against them, Christensen v Hunt, . 147 Mont. 484, 414 P.2d 648. Further, we have held that in reviewing the record in the trial court it is not within our province to determine whether we agree with the conclusions reached if they are supported by the evidence. Stromberg & Brown v Seaton Ranch Co., 160 Mont. 293, 502 P.2d 41; Hellickson . v Barrett Mobile Home Transport, Inc., 161 Mont. 455, 507 P.2d . 523; Nissen v. Western Const. Equip. Co., 133 Mont, 143, 320 P. 2d 997, The question here is whether Holland has shown there was an insufficiency of evidence to support the judgment. We find appellant failed to overcome the presumption of the correctness of the trial court's findings (1) by failing to introduce evidence to support the reasonableness of the hours charged to the Lampson job, and (2) that Lampson's witnessesf testimony supports the court ' s findings. As noted heretofore, the validity of the time cards was questioned and at best they only show the number of hours charged to the job and not the hours necessary to accomplish it, Holland totally failed to show by the time cards the number of hours necessary or reasonable to perform the work. The only real evidence before the trial court to assist in determining the reasonable number of hours to do the necessary work was introduced by amps son's witness Peterson, who testified without objection. Peterson was qualified,through years of experience in bidding on similar jobs, to testify on the reason- able number of hours necessary to accomplish the work performed by Holland. His testimony took into consideration the type of work, Holland's equipment, and the new parts used. He inspected the work done on the crane and testified he could have done the same work, using new parts, for $12,750.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stromberg v. Seaton Ranch Company
502 P.2d 41 (Montana Supreme Court, 1972)
Hellickson v. Barrett Mobile Home Transport, Inc.
507 P.2d 523 (Montana Supreme Court, 1973)
Christensen v. Hunt
414 P.2d 648 (Montana Supreme Court, 1966)
Nissen v. Western Construction Equipment Co.
320 P.2d 997 (Montana Supreme Court, 1958)
Higby v. Hooper
221 P.2d 1043 (Montana Supreme Court, 1950)
Hawkins v. Delta Spindle of Blytheville, Inc.
434 S.W.2d 825 (Supreme Court of Arkansas, 1968)
Smith v. Gunniss
144 P.2d 186 (Montana Supreme Court, 1943)
Braden Winch Co. v. Surface Equipment Co.
1945 OK 360 (Supreme Court of Oklahoma, 1945)
Delaware Engineering Co. v. Pusey & Jones Co.
112 A. 371 (Superior Court of Delaware, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
Holland Constr. Co. v. Lampson, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holland-constr-co-v-lampson-mont-1974.