Holder Construction Group, LLC v. Georgia Tech Facilities, Inc.

640 S.E.2d 296, 282 Ga. App. 796, 2006 Fulton County D. Rep. 3099, 2006 Ga. App. LEXIS 1230
CourtCourt of Appeals of Georgia
DecidedOctober 3, 2006
DocketA06A1386
StatusPublished
Cited by5 cases

This text of 640 S.E.2d 296 (Holder Construction Group, LLC v. Georgia Tech Facilities, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holder Construction Group, LLC v. Georgia Tech Facilities, Inc., 640 S.E.2d 296, 282 Ga. App. 796, 2006 Fulton County D. Rep. 3099, 2006 Ga. App. LEXIS 1230 (Ga. Ct. App. 2006).

Opinion

ANDREWS, Presiding Judge.

Holder Construction Group, LLC appeals from the trial court’s order granting summary judgment to Georgia Tech Facilities (GTF) on Holder’s claims under a construction contract. For reasons that follow, we affirm.

The record shows that Holder and GTF entered into a contract for the construction of the Georgia Tech Family Apartments project. The contract was of a type known as “fast-track” construction, under which construction is begun before the designs are completed. Under the contract at issue, Holder, the construction manager, assumed the obligation to construct the project for a stipulated sum or guaranteed *797 maximum price. This is known as a construction-manager-at-risk contract, under which the construction manager holds the trade contracts and is at risk for performance deficiencies, construction delays, and cost overruns. John I. Spangler III and William M. Hill, The Evolving Liabilities of Construction Managers, Construction Lawyer, January, 1999 at 30.

After construction on the project had begun, Holder experienced difficulties due to an increase in steel prices and the late delivery of steel materials. Because of these problems, Holder requested a 67-day time extension. GTF denied the request.

In September 2004, Holder filed a declaratory judgment action, contending that it was entitled to an upward adjustment of over $1 million in the contract price to account for differences between the allowances in the contract and the actual costs of the project; and was also entitled to an extension of time of not less than 63 days for completion of the project. Holder amended this complaint in December 2004 to add claims of over $3 million for breach of contract and quantum meruit/unjust enrichment.

GTF filed a motion for partial summary judgment and, after a hearing, the trial court granted the motion in part and denied it in part. The trial court reasoned that the intent of the parties was to enter into a contract whose purpose was to complete the project “in a timely fashion within the limit of available funds.” To that end, the parties, who were both “sophisticated business entities,” had entered into a contract that assigned the risk of loss for delays and escalated costs to Holder, the construction manager. The court held that Holder was not entitled to a time extension under the contract and had no claim for quantum meruit because an express contract controlled all of the claims at issue. With regard to requests for allowances and for change orders, the trial court held that GTF was entitled to summary judgment on all but 13 of these because Holder failed to follow the claim-filing procedure required under the contract. This appeal followed.

In order to prevail at summary judgment under OCGA § 9-11-56, the moving party must demonstrate that there is no genuine issue of material fact and that the undisputed facts, viewed in the light most favorable to the nonmoving party, warrant judgment as a matter of law. Lau’s Corp. v. Haskins, 261 Ga. 491 (405 SE2d 474) (1991).

Mustaqeem-Graydon v. SunTrust Bank, 258 Ga. App. 200, 205 (573 SE2d 455) (2002). When reviewing the grant of a motion for summary *798 judgment, we conduct a de novo review of the law and evidence. Northside Hosp. v. Ruotanen, 246 Ga. App. 433, 434 (541 SE2d 66) (2000).

1. We first address Holder’s claim that the trial court erred in granting summary judgment on its entitlement to a time extension and its acceleration costs claims. Holder claims that it is entitled to $3.1 million of acceleration costs attributable to GTF’s failure to grant its request for a time extension due to the steel crisis.

Section 3.1.18, the “Force Majeure” clause of the contract, addresses extensions due to late delivery of materials. This section provides:

If Construction Manager shall be unable to perform or shall be delayed in the performance of any of the terms and provisions of this Agreement as a result of (i) governmental preemption of materials in connection with a national emergency declared by the President of the United States; (ii) riot, insurrection, or other civil disorder affecting performance of the Work; or (iii) unusual and extreme weather conditions constituting Acts of God, then, and in any such event, such inability or delay shall be excused, and the time for completing the affected portions of the Project... shall be extended____

It is undisputed that the late delivery of the steel was not the result of any of the causes stated in the “Force Majeure” clause.

The contract goes on to state that late deliveries of materials, for reasons other than those set out in the “Force Majeure” clause, “do not constitute reason for extending the Date for Final Completion” and it is the construction manager’s responsibility to make adequate provision for this when scheduling the work. Sections 3.1.18.2 and 3.1.18.2.2.

Accordingly, under the contract, Holder bore the risk of the late delivery of the steel because it was not due to any of the reasons set out in the “Force Majeure” clause. In addition, the contract also provides that Holder was responsible for the failure of its steel suppliers to perform and could not assert this nonperformance as an excuse “either as to timely performance or as to compliance with methods and materials designated in the Contract Documents.” Section 3.7.22.

But, Holder argues that there were other delays caused by the owner which were apart from the steel crisis and for which it should have been granted extensions of time. Specifically, Holder contends that it should have been granted a time extension under Section 1.4.5. This section provides: “If the construction manager is delayed at any time in the progress of the work by an act or neglect of the owner, its *799 employees, the architect, or by other causes beyond the construction manager’s control which the architect determines may justify delay, then the contract time will be extended.”

However, Holder does not point to anywhere in the record, and we do not find, that it asked for extensions of time due to these owner-caused delays before the steel crisis. Further, the record shows that on March 10, 2004, Holder notified GTF of problems due to the delay in receiving materials, and the only reason given for requesting an extension of time was the late delivery of the steel.

In addition, Holder has introduced no evidence that but for these delays, there would have been no escalation in costs and the steel would have been delivered on time. Holder’s representative was consistently unable to point out the length of any owner-caused delays. Further, Holder provides only one citation to the record in support of this claim, the affidavit of James Fry, the operations manager for Holder on the GTF project. Fry states that

[b]ut for numerous delays caused by GTFI and the Architect, Holder may have been able to purchase and procure some or all of the steel material required for the project before the steel prices dramatically escalated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graybill v. Attaway Construction & Associates, LLC
802 S.E.2d 91 (Court of Appeals of Georgia, 2017)
Dan J. Sheehan Co. v. Fairlawn on Jones Homeowners' Ass'n
720 S.E.2d 259 (Court of Appeals of Georgia, 2011)
Georgia Real Estate Properties, Inc. v. Lindwall
692 S.E.2d 690 (Court of Appeals of Georgia, 2010)
Bollers v. Noir Enterprises, Inc.
677 S.E.2d 338 (Court of Appeals of Georgia, 2009)
Ellison v. Burger King Corp.
670 S.E.2d 469 (Court of Appeals of Georgia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
640 S.E.2d 296, 282 Ga. App. 796, 2006 Fulton County D. Rep. 3099, 2006 Ga. App. LEXIS 1230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holder-construction-group-llc-v-georgia-tech-facilities-inc-gactapp-2006.