Holcomb v. Fender

101 A.2d 814, 203 Md. 480
CourtCourt of Appeals of Maryland
DecidedJanuary 8, 1954
Docket[No. 52, October Term, 1953.]
StatusPublished
Cited by6 cases

This text of 101 A.2d 814 (Holcomb v. Fender) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holcomb v. Fender, 101 A.2d 814, 203 Md. 480 (Md. 1954).

Opinion

*482 Hammond, J.,

delivered the opinion of the Court.

The Circuit Court for Harford County determined that the appellee, W. Glenn Fender, was entitled to a mechanics lien against three houses which he had built for the respective owners, two brothers and a sister, and their- spouses, who are the appellants. From its decree declaring the indebtedness of each owner to the builder for the balance found by the Chancellor to be due and unpaid on the houses involved, and establishing the existence of a lien to secure payment, this appeal is taken. No questions are raised as to procedure or matters of form.

The appellants make two contentions, the answers to which control the case. First, they say that for each house there was a contract for a fixed sum, or, at least, a set ceiling price and that the lien is allowed improperly because the cost of the houses exceeded the agreed amount. Second, they assert that the testimony produced does not reasonably permit a finding that all of the materials charged for were delivered to the site and went into the houses.

The builder first discussed the erection of a house at a time when Raymond Howard Morris, one of the appellants, had entered into a contract to purchase a prefabricated house. The initial discussion was whether Fender would erect the house. Morris previously had been given an estimate of $6,175.00 for the house erected, but without a basement. In the course of the first discussion on the subject, Fender said he could build them a better house and save them some money. Finally, Morris agreed to have Fender build a house for him from plans procured from a lumber company. Thereafter, the two brothers-in-law of Morris, Glenn Holcomb and Gene Holcomb, arranged for Fender to build houses for them. Two were substantially the same and the third had a garage, which was first used as living quarters, and a breeze-way. Grimes Holcomb, the father of Gene and Glenn and of Mrs. Morris, was to advance *483 the cost of the houses for his children. He procured a loan for them from a local bank, which he guaranteed, and each paid Fender $6,000.00 when the houses were partially completed. When the houses were complete, Fender billed the owners and Mr. Grimes Holcomb for additional amounts on each for labor and material, claiming that the $6,000.00 paid by each was only part payment. The bills being unpaid, he filed mechanics liens against each of the properties, claiming a balance due from Glenn Holcomb of $4,433.24; from Gene Holcomb of $2,395.27; and from Morris, of $2,395.27. The Chancellor, after hearing, disallowed a ten per cent builder’s commission on the finding that Fender had expressly agreed to accept a discount from the lumber man in lieu of his commission, and reduced the unpaid balance due by Glen Holcomb in the amount of $938.20, and that due by the other two by $718.84 each.

The Chancellor found that there was no contract to build any house for any specific sum. Each of the owners, in answer to direct and explicit questions from the Court, admitted that this was so. Some thought that each house was to cost not more than $6,000.00; others, not more than $6,100.00; and others, not more than $6,175.00. The Chancellor said in his opinion: “A contract to build a house is not different from any other contract. To be enforceable, it must be definite and certain in its terms. Surely the testimony offered by the owners in support of their position in this matter is indefinite and lacking in many of the essential particulars necessary to establish a binding contract. It seems clear to me that, in the conferences between the owners and the builder preceding the actual building operations, some discussions as to the probable costs took place; and it may well be that the owners believed that a ceiling cost was established. Yet such a belief could become binding on the builder only when and if he agreed to it; but I find no adequate support for that proposition in the testimony. The statements attributed to the builder seem to me at most to be estimates.” *484 We think there is ample support in the record for the finding of the Chancellor.

No plans or specifications for the prefabricated houses were produced and it is undisputed that the houses which were built were different, and in some respects, larger and more complete than the prefabricated house. The appellants, or their wives, in some cases, personally selected various items of materials which were to go into the houses, choosing in each case the most expensive and best kinds available. If the builder had been working under a ceiling, it is unlikely he would have acquiesced in this procedure. Several of the owners, when questioned by the Court as to what would have happened if the cost had been less than $6,000.00, were unable to say. One answered as to the supposition: “I guess I thought, — I suppose we were to get it, but at that time no one even thought of it.” An owner ordinarily does not pay the full price of a house long before it is finished. There was also in the record testimony that when Grimes Holcomb (the father, who participated in many of the discussions and was as familiar with the understanding and agreement as any of his children) received the bills for the additional sums claimed to be due, he made no protest that there was to be a ceiling but rather, requested the representative of the lumber company to go over the bills with him so that he could be sure that all of the material had been delivered and charged for at the proper rate. He was concerned only with being sure that he was responsible for the amounts claimed.

In an effort to show that all of the materials charged for did not go into the house, the appellants produced a witness who had had experience with a lumber company for some years as an estimator of the cost of building and of the cost of material which would go into them. He had examined the houses and plans and testified that his estimate of the cost of construction would be $6,000.00. He estimated that by figuring cubic footage and applying a cost of construction per cubic *485 foot which he thought was accurate. Upon cross-examination, he revealed that he had estimated the cost of the houses at what they would have cost to build in 1947, which was the year in which his experience in that line of work had ceased. He also testified that from his measurements of one of the houses, he believed that there should have been used some thirteen hundred lineal feet of two by fours in one of the houses. The bills for the material, which were filed, showed that substantially more footage had been used in the house. The effect of this type of testimony is discussed in the case of Dente v. Bullis, 196 Md. 238. There, there were several expert witnesses who testified as to the proper ratio between labor costs and costs of raw material, and who estimated the material used. The Court said: “Bullis built the house and the only testimony to contradict his statement as to time and material consists of abstract calculations based on the ratio between time and material, and testimony of persons who examined the house after it was built and calculated what it should have cost.” The reasoning of the Court in that case applies with full force in the present case. The appellee, W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lazenby v. F. P. Asher, Jr. & Sons, Inc.
296 A.2d 699 (Court of Appeals of Maryland, 1972)
S. & G. Realty Co. v. Woodmoor Realty Corp.
259 A.2d 281 (Court of Appeals of Maryland, 1969)
Polansky v. Orlove
251 A.2d 201 (Court of Appeals of Maryland, 1969)
Causey v. Gray
243 A.2d 575 (Court of Appeals of Maryland, 1968)
Austin v. Austin
199 A.2d 380 (Court of Appeals of Maryland, 1964)
Lancaster v. Gardiner
170 A.2d 181 (Court of Appeals of Maryland, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
101 A.2d 814, 203 Md. 480, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holcomb-v-fender-md-1954.