Holbrook v. Massachusetts Turnpike Authority

154 N.E.2d 605, 338 Mass. 218, 1958 Mass. LEXIS 598
CourtMassachusetts Supreme Judicial Court
DecidedDecember 8, 1958
StatusPublished
Cited by10 cases

This text of 154 N.E.2d 605 (Holbrook v. Massachusetts Turnpike Authority) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holbrook v. Massachusetts Turnpike Authority, 154 N.E.2d 605, 338 Mass. 218, 1958 Mass. LEXIS 598 (Mass. 1958).

Opinion

Wilkins, C.J.

This petition for the assessment of damages, brought pursuant to G. L. (Ter. Ed.) c. 79, has been reported upon questions of law following a verdict for the petitioner. G. L. (Ter. Ed.) c. 231, § 111.

Prior to June 6, 1955, the petitioner was the owner of a tract of land in Palmer containing about thirteen acres developed as a recreation area. There were a club house and a bath house. A dam and dike had been erected to impound waters of a brook to form a pond, a filter bed, and a swimming pool.

On June 6 the respondent, acting pursuant to St. 1952, c. 354, made a valid taking in fee of about one acre, occupied by the easterly end of the pond. Damages for this taking were recovered by the petitioner in another petition under c. 79 which was tried with the one now before us.

The present petition alleges that the respondent, in pursuance of constructing a turnpike and without any formal taking, entered upon the petitioner’s land with tractors, “bulldozers,” and other large pieces of earth moving machinery, broke and opened dikes and otherwise damaged the land.

In July, 1955, a contractor in performance of a contract with the respondent came upon the land taken and began construction of an -access way to the turnpike. On adjacent property to the east was an ice pond, impounded by a dam belonging to an ice company and located along the petitioner’s easterly boundary. An eighteen inch pipe was in the base of that dam and a spillway on the top discharged water onto the petitioner’s property.

The contractor began dumping fill on the land taken from the petitioner and on the ice pond dam, thus blocking the eighteen inch pipe. When the level of the fill reached the *220 elevation of the spillway, the contractor laid an eighteen inch temporary pipe along the spillway and across the top of the fill. The contractor continued to raise the level of the fill, and by August 11 its surface was about four feet higher than the top of the ice pond dam. At that time the temporary pipe was the only means of discharging water from the ice pond to the petitioner’s remaining land.

A sustained rainy period, due to hurricane “Connie,” began on August 11 and continued until August 14. In the Palmer area at least 4.22 inches of rain fell. An expert witness called by the petitioner characterized this storm as a “one year storm,” that is, one to be expected on an average of once a year over an extended period. In the course of this storm the flow of water made a breach in the fill, and gouged a channel in the area of the temporary pipe. Fill from this channel was deposited in the petitioner’s pond, filter bed, and swimming pool. The petitioner’s dam and spillway and a bridge near the dam were left intact, but a breach had been made in a dike between the swimming pool and the pond.

On August 15, 16, and 17 the weather was fair. On August 15 the water in the swimming pool had receded to normal level. The contractor began replacing the washed out fill, and by August 18 fill and pipe had been restored to their former condition.

On August 18 and 19 occurred a second storm, known as hurricane “Diane," which caused extensive damage throughout western Massachusetts. Bridges, roads, and railroad embankments were washed out. The petitioner’s expert witness characterized “Diane” as most unusual, as “a one hundred year storm, ” of the like of which there was no record. During “Diane,” water built up behind the fill, and on August 19 began- to flow over the top of the fill “along its entire length.” Late that afternoon the contractor’s workmen began to “bulldoze” a channel in the vicinity of the temporary pipe. When the channel reached a length of about thirty feet, water rushed across the fill, gouging a deeper and wider channel. Water entered the *221 pond and filter bed, and surged over spillways on the dike between the pond and the swimming pool and on the dam at the end of the pool. The entire area was inundated. The petitioner’s dam, bridge, and swimming pool were destrayed, and there was an accumulation of fill in the pond.

The questions of law reported are: (1) Whether the petitioner may recover in this form of proceeding for the damage to his property which occurred in August. (2) Whether the damage occurring in August was damage “in the carrying out” or “in the exercise of” the powers granted to the respondent by St. 1952, c. 354. (3) Whether there was error in the charge. These questions are so interrelated that we shall consider them together.

The judge charged that the basis of the petition is St. 1952, c. 354, which created the respondent. He referred particularly to § 15, which reads: “pTj All private property damaged or destroyed in carrying out the powers granted by this act shall be restored or repaired and placed in its original condition as nearly as practicable, or adequate compensation made therefor, out of funds provided under the authority of this act. . . . pi] Any person damaged in his property by the exercise of any of the powers granted by this act may recover his damages from the Authority under chapter seventy-nine of the General Laws.”

General Laws (Ter. Ed.) c. 79, § 10, reads in part: “When the real estate of any person has been taken for the public use or has been damaged by the construction, maintenance, operation, alteration, repair or discontinuance of a public improvement or has been entered for a public purpose, but such taking, entry or damage was not effected by or in accordance with a formal vote or order of the board of officers of a body politic or corporate duly authorized by law . . . and by such taking, damage, entry, seizure, destruction or use he has suffered an injury for which he is entitled to cornpensation, the damages therefor may be recovered under this chapter.”

The respondent relies upon G. L. (Ter. Ed.) c. 79, § 12, the portions reading, “The damages for property taken *222 under this chapter shall be fixed at the value thereof before the taking, and in case only part of a parcel of land is taken there shall be included damages for all injury to the part not taken caused by the taking or by the public improvement for which the taking is made .... In determining the damages to a parcel of land injured when no part of it has been taken, regard shall be had only to such injury as is special and peculiar to such parcel . . . .” It is argued that the only taking was in June, for which the petitioner has been fully compensated; that the taking could not have caused the inundation in August, the damage from which was not to be foreseen by a “hypothetical willing buyer”; 1 and that an injury caused by the act or omission of a contractor is not caused by a taking or by the public improvement for which the taking is made. The respondent takes the position that its liability, if any, is in tort.

That c. 79 itself confers no right to damages upon an owner whose property is not taken by eminent domain, but that the c. 79 procedure mavJbe ma.de available by appropriate provision in another statute creating a right to such damages is clear from Sullivan v. Commonwealth, 335 Mass. 619, 622-626, and Webster Thomas Co. v. Commonwealth, 336 Mass. 130, 137-138. “The Legislature ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Town of Millbury
21 Mass. L. Rptr. 460 (Massachusetts Superior Court, 2006)
Soeder v. County Commissioners
805 N.E.2d 1026 (Massachusetts Appeals Court, 2004)
McSorley v. Town of Hancock
417 N.E.2d 982 (Massachusetts Appeals Court, 1981)
Kane v. Town of Hudson
389 N.E.2d 737 (Massachusetts Appeals Court, 1979)
Betty Corporation v. Commonwealth
237 N.E.2d 26 (Massachusetts Supreme Judicial Court, 1968)
Massachusetts Turnpike Authority v. Perini Corp.
208 N.E.2d 807 (Massachusetts Supreme Judicial Court, 1965)
Murray Realty, Inc. v. Berke Moore Co.
175 N.E.2d 366 (Massachusetts Supreme Judicial Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
154 N.E.2d 605, 338 Mass. 218, 1958 Mass. LEXIS 598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holbrook-v-massachusetts-turnpike-authority-mass-1958.