Holber v. Suffolk Construction Co. (In Re Red Rock Services, Co.)

642 F. App'x 110
CourtCourt of Appeals for the Third Circuit
DecidedMarch 10, 2016
Docket15-1047
StatusUnpublished
Cited by4 cases

This text of 642 F. App'x 110 (Holber v. Suffolk Construction Co. (In Re Red Rock Services, Co.)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holber v. Suffolk Construction Co. (In Re Red Rock Services, Co.), 642 F. App'x 110 (3d Cir. 2016).

Opinion

OPINION *

ROTH, Circuit Judge.

Suffolk Construction Co. challenges .the District Court’s ruling, affirming the orders of the U.S. Bankruptcy Court for the Eastern District of, Pennsylvania in an adversary proceeding with Red Rock Services Co., represented by the Chapter 7 bankruptcy trustee, Robert H. Holber (Red Rock). Suffolk also challenges the District Court’s affirmance of the Bankruptcy Court’s attorneys’ fees award. We will affirm the order of the District Court.

I.

The factual circumstances of this matter are long, intricate, and ably set forth in the *113 opinion of the District Court. Since we write only for the parties, the following is an abbreviated version of the relevant factual circumstances necessary for the resolution of the instant appeal. Suffolk is a general contractor and, until it declared bankruptcy, Red Rock was a demolition services contractor. At issue in this appeal are two contracts between Suffolk, as general contractor, and Red Rock, as subcontractor. Each contract pertained to a distinct project, one involving the conversion of a grain silo to condominiums in Baltimore, Maryland (the Silo Point contract), and one involving the rehabilitation of a federal office building in Boston, Massachusetts (the McCormack contract). Red Rock began demolition services under both contracts and failed to finish either one.

At the Silo Point project, the problems began when one of the vertical storage bins in the silo “detached and fell to a floor below, damaging a portion of the building.” The damage caused Red Rock to change its methods for demolition, resulting in substantially increased expense. Red Rock’s contract with Suffolk required Red Rock to notify Suffolk if it planned to seek an alteration to the contract, referred to as a change order, within ten days of an event giving rise to a claim for a deadline extension or an increase in compensation.

It is undisputed that Red Rock did not notify Suffolk within ten days of its intent to seek a change order. Nevertheless, Red Rock did notify Suffolk on December 20, 2006, and over the next seven months Suffolk worked with Red Rock to prepare a change order request for the owner of the project. This effort culminated in the submission to the owner in July 2007 of Change Order No. 3. The owner rejected Change Order No. 3 as untimely. Shortly thereafter, Suffolk notified Red Rock that it was in default on the subcontract.

At the same time, Suffolk also contracted with Red Rock for demolition services in connection with the McCormack project. On that project, Red Rock fell behind on various deadlines and failed to complete certain contractual duties. Consequently, on April 9, 2007, Suffolk notified Red Rock that it was in default and terminated the contract two days later. Suffolk hired a second contractor to complete the work, but that contractor lacked competence which resulted in significantly increased costs. Ultimately, Suffolk hired a third contractor to complete the work begun by Red Rock.

Red Rock filed for bankruptcy protection in the Eastern District of Pennsylvania on September 13, 2007, one week after it received Suffolk’s default notice on the Silo Point project. As part of that proceeding, Suffolk filed a proof of claim, alleging that it was owed damages for Red Rock’s alleged breach of the Silo Point and McCormack contracts. Red Rock instituted an adversary proceeding against Suffolk, claiming that, to the contrary, Red Rock was owed money by Suffolk for Red Rock’s performance on the contracts. Pri- or to trial, Red Rock voluntarily dismissed its claims as to the McCormack project, but not as to the Silo Point project.

In May 2011, the Bankruptcy Court held an eight-day bench trial. Before the bench trial, Suffolk moved in limine to exclude the testimony of Red Rock’s expert witness on damages as to the McCor-mack project. Suffolk claimed that the expert was an improper rebuttal witness since he was not expected to testify in Red Rock’s case-in-chief. The Bankruptcy Court denied the motion.

Following trial, the Bankruptcy Court (1) awarded damages to Red Rock for Suffolk’s breach of the Silo Point contract, (2) awarded damages to Suffolk for Red Rock’s breach of the McCormack contract, *114 and (3) allowed Suffolk to offset its award against Red Rock’s, resulting in a net recovery for Red Rock. The Bankruptcy Court subsequently ruled on the parties’ motions .for attorneys’ fees and costs, finding that each contract had an identical attorneys’ fees provision mandating the award of reasonable attorneys’ fees to the “prevailing party in any dispute” between the parties. The Bankruptcy Court held that Suffolk had prevailed as to the McCormack contract and Red Rock had prevailed as to the Silo Point project. Since the Bankruptcy Court' found that neither party had differentiated in their motions between the fees and costs incurred as' to each contract — each had submitted only an aggregate accounting — the Bankruptcy Court granted both parties the full amount of their requested fees. In total, after the breach of contract awards, the offsets, and the attorneys’ fees awards, the Bankruptcy Court entered judgment for $934,458.95 in favor of Red Rock.

II.

The District Court had jurisdiction over this bankruptcy appeal pursuant to 28 U.S.C. § 158(a)(1). We have jurisdiction over this appeal from the District Court’s judgment pursuant to 28 U.S.C. § 158(d)(1). Our review of the District Court’s decision, in which it functioned as an appellate court to the Bankruptcy Court, is plenary. 1 We review the courts’ legal conclusions de novo and the Bankruptcy Court’s factual finding for clear error. 2 We review the trial judge’s decisions on whether to exclude testimony and the award of attorneys’ fees for abuse of discretion. 3

III.

Suffolk raises six challenges to the District Court’s decision affirming the Bankruptcy Court. Suffolk challenges (1) the Bankruptcy Court’s jurisdiction of the state law claim, (2) its holding that Red Rock did not waive its right to seek a change order on the Silo Point contract, (3) its holding that Suffolk should be collaterally estopped from challenging the validity or timeliness of the change order, (4) its holding that Suffolk waived any challenge to the change order, (5) its decision denying Suffolk’s motion in limine regarding Red Rock’s damages expert (6) its award of attorneys’ fees to Red Rock following a lodestar method, and (7) its award of full attorneys’ fees requested by each party.

As to the Bankruptcy Court’s authority to decide the state law claim in view of the Supreme Court’s decision in Stern v. Marshall, 4 the District Court correctly found that any state law claims were inextricably interlinked with the claims flowing from the adversary proceeding and, consequently, from the federal bankruptcy statutory regime.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
642 F. App'x 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holber-v-suffolk-construction-co-in-re-red-rock-services-co-ca3-2016.