Hoffman v. St. Louis Refrigerator & Cold Storage Co.

97 S.W. 619, 120 Mo. App. 661, 1906 Mo. App. LEXIS 434
CourtMissouri Court of Appeals
DecidedNovember 13, 1906
StatusPublished
Cited by1 cases

This text of 97 S.W. 619 (Hoffman v. St. Louis Refrigerator & Cold Storage Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoffman v. St. Louis Refrigerator & Cold Storage Co., 97 S.W. 619, 120 Mo. App. 661, 1906 Mo. App. LEXIS 434 (Mo. Ct. App. 1906).

Opinion

GOODE, J.

This action was to recover the amount of $400 alleged to be due plaintiffs by the following contract :

“St. Louis, Mo., May 30, 1905.
“Fred Hoffman & Co.,
“301 Benoist,
St. Louis, Mo.
“Gentlemen: We have this day made the following contract with your Mr. Hogan. In consideration of the-payment to you of $400, you contract and agree so to contruct the sewer you are about to build in the alley between Pine and Olive and Twelfth and Thirteenth streets, running north, that it will not affect or cause to settle our conduit that at present is located in the alley, according to the tracing we have this day given to your Mr. Hogan; and you further agree that if, in constructing this sewer, you' do cause us any damage, that you will pay all losses to which we are put by reason of the damage.
“The $400 is to be paid to you when you have finished the sewer and the same has been accepted by the city of St. Louis.
“It is understood that your acceptance of this contract is on the condition that the board of public improvements shall stake out the sewer west of our conduit.
“If you are prepared to confirm this contract please sign and return to us one copy of this letter, which is issued in duplicate, you retaining the other.
“Yours truly,
“St. Louis Eefrigerator & Cold Storage Co.,
“Accepted: “T. S. McPheeters, President.
“Fred H. Hoffman & Co.,
“T. F. Hogan.”

The action was originally instituted before a justice of the peace and a statement filed which, after declaring on the instrument just copied, averred that plaintiffs constructed and finishel the sewer between Pine and [664]*664Olive and Twelfth and Thirteenth streets in the city of St. Lonis, so that the work did not affect defendant’s conduits or cause them to settle; that after the sewer was finished, it was accepted by the city and plaintiffs subsequently demanded payment of the $400 from defendant and defendant refused to pay. The case went to the circuit court on appeal and when called for trial in that court, one of the attorneys for defendant stated to the jury that defendant admitted Mr. Hogan (one of the plaintiffs) was to be paid $400 for taking care that defendant’s pipes were not injured; admitted that when the sewer was built and plaintiffs called on defendant for their money, defendant refused to pay because its mechanical department, on investigating the ground in which the sewer was built, discovered several large holes which endangered the pipes; that thereupon defendant* agreed to pay the $400 if plaintiffs would give a bond to secure the payment of any damage which might happen, which the plaintiffs refused to do. The attorney further stated that the work had not been performed as the contract provided; that the testimony would so show and if it did, the verdict should be for defendant.

Plaintiffs were under contract with the city of' St. Louis to lay a large sewer pipe in an alley. The defendant had three conduits or pipes laid in the alley about three feet below the surface. One of those pipes was filled with ammonia, one with ammonia gas and the other was a vacuum to be used if either of the others got out of order. The pipes were employed in connection with the system of refrigeration furnished to various business establishments in the city; among others the Jefferson Hotel. Defendant’s pipes carried a pressure of one hundred and twenty-five to one hundred and eighty-five pounds, and the testimony goes to show that if they sagged it would be easy for the ammonia or ammonia gas to escape. The sewer was to be constructed seventeen feet below the surface of the alley and fourteen feet below defendant’s pipes. The tes[665]*665timony of defendant’s president was that after plaintiffs had finished the work and demanded their money, he ordered a check to be sent them, but before this was done defendant’s mechanical department reported that the work was defective; wherefore defendant demanded a bond of $800 before it would pay and plaintiffs refused to execute the bond, contending they were not required to do so under the contract. The evidence is that plaintiffs are financially responsible. Some of defendant’s workmen testified that on examining the sewer they found three cavities above it; one eighteen or twenty feet long and from one to to two feet high, another about four feet square and a foot below defendant’s pipes and a third two and a half feet long, two inches wide and six feet deep underneath and alongside the pipes; that the cavities below the conduits would cause the latter to settle. Evidence was given for plaintiffs tending to show there were no such cavities and that the sewer was pnt in so as to safeguard defendant’s conduits. There was a conflict of evidence on this question presenting an issue of fact for the jury. The court directed a verdict for defendant, doubtless in consequence of another defense. The contract between plaintiffs and the city of St. Louis for laying the sewer contained this clause:

“Whenever underground pipes or conduits, either public or private, are encountered during the progress of the work, the contractor shall sustain them by timber and chains, or otherwise, so as to keep them in position and free from injury. Any damage to underground pipes, or conduits, resulting from any work done under this contract, from any neglect or carelessness of the contractor, may be repaired by the proper party, and the costs thereof shall be paid by the contractor on demand, and in default of payment may be recovered by said party in any court of competent jurisdiction, of the contractor and his securities, or any one of them hereunder; or if the claim is for work done by the city of [666]*666St. Louis, no certificate of the completion of the work done under this contract shall be given by the sewer commissioner until payment is made.”

There were other clauses in the city’s contract providing in substance, that plaintiffs should be governed by the orders of the city sewer commissioner, who should have the right to determine the amount, quantity and. classification of the several kinds of materials to be paid for under the agreement with the city, and to decide all questions in relation to the agreement; that plaintiffs should give a bond with the National Security Company, as surety, in the sum of more than six thousand dollars, conditioned that, in the event plaintiffs faithfully performed their work according to contract with the city and paid all proper parties for materials and labor used, the obligation should be void; otherwise should remain in full force and to be sued on in the name of the city at the instance of any materialman, laborer or mechanic who was injured by a breach of its conditions. The theory on which the verdict was ordered for defendant was, that the contract between plaintiffs and defendant bound the former to do no more than they were reasonably bound to do under their contract with the city and, hence, there was no consideration for defendant’s agreement to pay $400 if the work of laying the sewer was performed so as not to affect defendant’s conduits or cause them to settle.

Further reference needs to be made to the testimony regarding the execution of the contract in suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rollins v. Schawacker
133 S.W. 409 (Missouri Court of Appeals, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
97 S.W. 619, 120 Mo. App. 661, 1906 Mo. App. LEXIS 434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoffman-v-st-louis-refrigerator-cold-storage-co-moctapp-1906.