Hoff v. Mountain Construction, Inc.

102 P.3d 816, 124 Wash. App. 538
CourtCourt of Appeals of Washington
DecidedDecember 7, 2004
DocketNo. 30728-6-II
StatusPublished

This text of 102 P.3d 816 (Hoff v. Mountain Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoff v. Mountain Construction, Inc., 102 P.3d 816, 124 Wash. App. 538 (Wash. Ct. App. 2004).

Opinion

¶1

Hunt, J.

— Mountain Construction, Inc., appeals the trial court’s grant of partial summary judgment to David Hoff, a subcontractor’s employee, who was injured when he fell into a deep pit at a construction site for which Mountain was general contractor. Mountain argues the trial court erred in (1) finding that Mountain breached its duty to provide fall restraint protection required by the Washington Industrial Safety and Health Act of 1973 (WISHA), chapter 49.17 RCW, as a matter of law on summary judgment; (2) excluding defense testimony in the subsequent trial on the remaining issues; (3) instructing the jury that Mountain violated WISHA; and (4) denying Moun[541]*541tain’s motion to reconsider the summary judgment ruling that Mountain had violated WISHA as a matter of law. Holding that the trial court did not err, we affirm.

FACTS

I. The Accident

¶2 Mountain Construction hired a subcontractor to excavate a 20-foot-deep pit at a renovation site. When the excavation encountered water, Mountain was unable to pump out the water in order to continue digging. Mountain hired Everson’s Econo-Vac to vacuum the water out of the pit.

¶3 Econo-Vac employees David Hoff and Ed Bertash conferred with David Douglas, the site foreman. The pit was cordoned off with movable poles and yellow caution tape.1 Parts of the barricade were moved out of the way to allow the Econo-Vac truck to access the pit. Hoff and Bertash began vacuuming water from the pit, using their truck and equipment parked at the lip of the pit, while the subcontractor’s track hoe continued excavating within the pit. According to Bertash, they had no harness or fall restraint system.2

¶4 Hoff and Bertash removed two loads of water from the pit without difficulty. As they continued to vacuum, Hoff retrieved an extension for the vacuum from the back of their truck, put down the extension, turned to retrieve a clamp, lost his footing, fell into the pit, and landed on the track-hoe bucket, injuring his foot and hip. The track-hoe operator entered the pit and assisted Hoff up a ladder. Hoff’s foot injury required surgery.

[542]*542II. Procedure

¶5 Hoff sued Mountain and the excavation subcontractor, alleging that Mountain breached its duty to make the site safe, to warn against potentially dangerous conditions, and to maintain the premises in a safe condition according to the law. Hoff moved for summary judgment, citing Mountain’s violations of WISHA.3 Mountain did not mention anything about a guardrail along the pit’s edge.

A. Partial Summary Judgment on WISHA Violation

¶6 The trial court granted partial summary judgment to Hoff, finding “no genuine issues as to any material fact regarding [Mountain’s] breach of its duty to [Hoff] to provide a safe workplace (i.e. failure to have in place safety/fall restraint devices).” Clerk’s Papers (CP) at 379-80. The trial court did find genuine issues of material fact as to causation and Hoff’s potential comparative negligence.

¶7 Mountain moved for clarification, asking the court to specify which section of WISHA Mountain had violated. The trial court specified WAC 296-155-24510.4

¶8 Hoff moved for reconsideration, asking the trial court to find Mountain 100 percent liable. In response, Mountain filed a reply, which included a declaration from its general superintendent, John O’Connor. O’Connor’s declaration mentioned, for the first time, a two-by-four wooden guard[543]*543rail in front of the access point to the pit.5 The trial court denied reconsideration, leaving the proximate cause and comparative negligence issues for the jury.

B. Trial of Remaining Issues

¶9 Douglas testified at trial that (1) Mountain had failed to prepare a fall protection plan;6 (2) Mountain did not obtain a variance, required for inability to comply with general WISHA requirements;7 (3) the guardrail served as a warning line, and it would not stop anyone who slipped and fell; and (4) there was nothing in place at the site to arrest or to prevent a fall into the pit. Douglas was unable to place the guardrail in the area where Hoff had been working in the pit.

¶10 Hoff moved to prevent Mountain from offering testimony suggesting that the wooden guardrail conformed to WISHA fall-arrest/restraint requirements. He argued such testimony would contradict the court’s partial summary judgment order. The trial court suppressed this testimony, ruling that the time for Mountain to have argued that the guardrail complied with WAC 296-155-24510 was at the summary judgment motion.

¶11 In Mountain’s offer of proof,8 O’Connor admitted on cross-examination he could not testify under oath that the [544]*544guardrail could have withstood a force of 200 pounds with minimal deflection, as required by WISHA,9 or that the guardrail had ever been inspected. After its offer of proof, Mountain asked the court to allow O’Connor’s testimony and to reconsider its ruling on the WISHA violation. The trial court ruled that O’Connor’s testimony did not show compliance with WISHA requirements and O’Connor could not testify about the guardrail.

¶12 The trial court accepted Hoff’s proposed jury instructions about Mountain’s responsibility for complying with WISHA fall-arrest/restraint requirements. The jury found Mountain 99 percent liable and Hoff 1 percent contributorily negligent. Mountain appeals.

ANALYSIS

I. Partial Summary Judgment
A. Standard of Review

f 13 When reviewing an order of summary judgment, we engage in the same inquiry as the trial court. Wilson v. Steinbach, 98 Wn.2d 434, 437, 656 P.2d 1030 (1982). Summary judgment is appropriate only if the pleadings, affidavits, depositions, and admissions on file demonstrate the absence of any genuine issues of material fact and that the moving party is entitled to judgment as a matter of law. CR 56(c). The court must consider all facts submitted and all reasonable inferences from them in the light most favorable to the nonmoving party. Wilson, 98 Wn.2d at 437. The nonmoving party may not rely on speculation, argumentative assertions that unresolved factual issues remain, or having its affidavits considered at face value. Seven Gables Corp. v. MGM/UA Entm’t Co., 106 Wn.2d 1, 13, 721 P.2d 1 (1986).

[545]*545fl4 After the moving party has submitted adequate affidavits, the burden shifts to the nonmoving party to set forth specific facts sufficiently rebutting the moving party’s contentions and disclosing the existence of a material issue of fact. Seven Gables, 106 Wn.2d at 13. The trial court should grant summary judgment only if, from all the evidence, reasonable persons could reach but one conclusion. Wilson, 98 Wn.2d at 437. Applying these standards here, we hold that the trial court properly granted partial summary judgment.

B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seven Gables Corp. v. MGM/UA Entertainment Co.
721 P.2d 1 (Washington Supreme Court, 1986)
State v. Blackwell
845 P.2d 1017 (Washington Supreme Court, 1993)
Stute v. P.B.M.C., Inc.
788 P.2d 545 (Washington Supreme Court, 1990)
Wilson v. Steinbach
656 P.2d 1030 (Washington Supreme Court, 1982)
Tortes v. King County
84 P.3d 252 (Court of Appeals of Washington, 2003)
Kinney v. Space Needle Corp.
85 P.3d 918 (Court of Appeals of Washington, 2004)
Tortes v. King County
84 P.3d 252 (Court of Appeals of Washington, 2003)
Kinney v. Space Needle Corp.
85 P.3d 918 (Court of Appeals of Washington, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
102 P.3d 816, 124 Wash. App. 538, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoff-v-mountain-construction-inc-washctapp-2004.