Hodges v. Bankers Surety Co.

152 Ill. App. 372, 1910 Ill. App. LEXIS 739
Appellate Court of Illinois·Decided December 7, 1909·No. Gen. No. 14,650·Published·Cited by 10 cases

Opinions

Mr. Justice Smith

delivered the opinion of the court.

This case comes here upon appeal from a judgment of the Municipal Court of Chicago in favor of the defendant, appellee. The case was tried before a jury on the first count of the amended declaration, a demurrer to the second count having been sustained by the court, and the plaintiff having elected to stand by the count. The verdict of the jury was in favor of appellee by direction of the court.

The suit is in assumpsit for the recovery of damages growing out of an alleged agreement of appellee to pay the plaintiff, appellant, whatever the cost and expenses of furnishing materials and performing work and labor relative to the mason, concrete and carpenter work on the Eugene Dietzgen factory building at Sheffield and Fullerton avenues, Chicago, exceeded the amount payable to the Federal Concrete Steel Company, hereafter called the Federal Company for convenience. Appellant Hodges was a general contractor for the construction of the building, and had sub-let the mason, concrete and carpenter work to the Federal Company. The appellee had given its bond to appellant guaranteeing the faithful performance of the contract by the Federal Company. The Federal Company failed to perform its contract, and the agreement sued on was made after such failure, and in view of the situation produced thereby. 1

The first' count of the amended declaration avers that the “plaintiff, Stewart Hodges, being a general contractor, for the purpose of carrying out an agreement entered into between him and a corporation known as the Eugene Dietzgen Company, by and under which said agreement the said Stewart Hodges, for the certain consideration of forty-seven thousand, five hundred dollars ($47,500) agreed, among other things, to complete on or before the 1st day of September, 1906, certain building work and construction of a proposed fireproof factory building for the said Eugene Dietzgen Company at the northeast corner of Fullerton and Sheffield avenues in the City of Chicago, did make and enter into an agreement with a corporation known as the Federal Concrete Steel Company; that by and under said agreement the Federal Concrete Steel Company, for the certain consideration of thirty-three thousand dollars ($33,000) agreed, among other things, to complete on or before the 1st day of July, 1906, at the northeast corner of Fullerton and Sheffield avenues in the City of Chicago, certain building work and construction of certain portions of a proposed fireproof factory building, which said building work and construction the said Stewart Hodges was required to do under his agreement with the said Eugene Dietzgen Company; that the said agreement provided, among other things, that if the work should be delayed beyond the stipulated time, provided no general strike interfered, there should be a deduction from the contract of twenty-five dollars ($25) for each and every day the work remained unfinished after July 1, A. D. 1906.

“The plaintiff further avers that The Bankers Surety Company, having given its bond for fifteen thousand dollars ($15,000) for the faithful performance by the said Federal Concrete Company of its part of the contract with the said Stewart Hodges, and the said Federal Concrete Company, having been in default on, to wit: May 15, 1906, in the performance of its part of the contract with the said Stewart Hodges, the plaintiff immediately thereupon, in accordance with a condition of the said bond, notified the said The Bankers Surety Company of the default in performance of the said Federal Concrete Steel Company; that subsequent to said, to wit: 15th day of May, 1906, under the authority and hy the direction of the said defendant, said plaintiff did procure and invite bids for the completion of the work contemplated under the said agreement dated, to wit: the 4th day of April, A. D. 1906, in accordance with the drawings, plans and specifications therefor; that the lowest of the said bids procured as aforesaid was for a price and consideration for the completion of the work so provided to be done under the contract aforesaid, to wit: the sum of four thousand dollars ($4,000) in excess of the balance provided to be paid to the said Federal Concrete Steel Company under the said contract of, to wit: April the 4th, A. D. 1906; that the. said The Bankers Surety Company, upon the request of the said plaintiff, refused to itself complete or re-let the completion of the work to be done under the contract of the said Federal Concrete Steel Company with the said Stewart Hodges, which privilege was secured to the said The Bankers Surety Company by a condition of its bond, or to authorize the plaintiff to let the completion of the said work to the lowest bidder that plaintiff had procured to bid upon the completion of the contract; but believing that the said plaintiff could himself furnish the labor and materials to complete the said work cheaper than the said work could be completed by letting its completion to the lowest bidder procured as aforesaid, said defendant authorized and directed the said plaintiff to proceed to complete the work contemplated under the said agreement by himself furnishing the labor and materials to complete and do the work provided under the said agreement; and the said defendant then and there agreed to pay the said plaintiff whatever aniount the costs and expenses of completing the said contract and the work provided to be done under the said contract in furnishing labor and materials therefor exceeded on its completion the balance payable under the said contract of, to wit: April 4, A. D. 1906, to the said Federal Concrete Steel Company; and the said plaintiff then and there agreed to pay to the said Federal Concrete Steel Company whatever amount the balance payable under the said contract of, to wit: April 4, A. D. 1906, to the Federal Concrete Steel Company exceeded on the completion of the said work the costs and expenses of the plaintiff in completing the said work provided to be done as aforesaid.

“And the plaintiff further avers that, further relying upon the said authority of, direction of and agreement with the said defendant, The Bankers Surety Company, the said plaintiff did, on, to wit: June 1, A. D. 1906, enter upon the completion of the work provided to be done under the said contract of, to wit: April 4, A. D. 1906,- between him and the said Federal Concrete Steel Company, and did then and there hire such superintendents as was necessary to carry on the said work to completion.

Free access — add to your briefcase to read the full text and ask questions with AI

Hodges v. Bankers Surety Co., 152 Ill. App. 372, 1910 Ill. App. LEXIS 739 (Ill. Ct. App. 1909).

152 Ill. App. 372 (Hodges v. Bankers Surety Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Terminal Freezers, Inc. v. Roberts Frozen Foods, Inc.
354 N.E.2d 904 (Appellate Court of Illinois, 1976)
General Refrigeration & Plumbing Co. v. Goodwill Industries
333 N.E.2d 607 (Appellate Court of Illinois, 1975)
Freeport Journal-Standard Publishing Co. v. Frederic W. Ziv Co.
103 N.E.2d 153 (Appellate Court of Illinois, 1952)
Gasco v. Tracas
155 N.E. 179 (Indiana Court of Appeals, 1927)
Foley v. Wolfie, Steffelin & Co.
232 Ill. App. 333 (Appellate Court of Illinois, 1924)
Edwards & Deutsch Lithographing Co. v. Hildmann Printing Co.
221 Ill. App. 61 (Appellate Court of Illinois, 1921)
Adam v. Columbian National Life Insurance
218 Ill. App. 54 (Appellate Court of Illinois, 1920)
American Hominy Co. v. Millikin Nat. Bank
273 F. 550 (S.D. Illinois, 1920)
Mellish-Hayward Co. v. R. Haas Electric & Manufacturing Co.
181 Ill. App. 664 (Appellate Court of Illinois, 1913)
Tyrrell v. Robinson
180 Ill. App. 286 (Appellate Court of Illinois, 1913)