Hodge v. City of Ft. Worth

196 S.W. 583, 1917 Tex. App. LEXIS 706
CourtCourt of Appeals of Texas
DecidedApril 14, 1917
DocketNo. 8589.
StatusPublished

This text of 196 S.W. 583 (Hodge v. City of Ft. Worth) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hodge v. City of Ft. Worth, 196 S.W. 583, 1917 Tex. App. LEXIS 706 (Tex. Ct. App. 1917).

Opinion

BUCK, J.

Suit .was instituted by C. T. Hodge against the city of Ft. Worth to recover the balance alleged to be due for work and labor performed under a contract with said city in the clearing of what is known as the reservoir site up to the 608-foot line above the sea level, and to recover damages from the city for the alleged failure to permit him to clear the remainder of said reservoir site embraced within said measurements.

The cause was tried before the court without the intervention of a jury, and judgment rendered for plaintiff as follows: (1) In the sum of $1,729.61, the amount found to be due on estimates and retained by said city; (2)' the sum of $554.01, the amount found to be due for clearing other land; (3) the amount of $250 found to be due for 5,000 fence posts *584 sold and delivered to tlie city by plaintiff; and (4) the balance found to be due for work in clearing the river channel, in the sum of $161.75, making a total of $2,695.37. A credit thereon of $100 was allowed the city, because by reason of the city’s failure to furnish the material to build a fence which appellant had contracted to build, the appellant was not required to spend for labor in erecting said fence the amount named. Interest was allowed on $2,595.37, from October 12, 1912, amounting at the time of the suit, to wit, April 25, 1916, to $3,145.98: The plaintiff has appealed.

The controversy arises by reason of the wording of the contract between plaintiff and defendant, plaintiff contending that the contract was intended to cover and did cover the work of clearing the entire reservoir site, including all the lands both below and above the nine-mile -bridge inundated by reason of the construction of the dam, up to the 608 flow line. The contention of the city is that it should not be held liable for the clearing of more than approximately 1,250 acres, which both parties agreed and so stated in the contract, constituted the acreage contemplated by the contract, and that in no event could it be held liable for the profits claimed by plaintiff in the way o'f damages on the land above the nine-mile bridge, and which lands the plaintiff was not permitted by the city to clear. On July 24, 1911, the city advertised for bids “for clearing the West Fork reservoir site of trees, undergrowth, etc., according to specifications on file in the board of engineers’ office.” These specifications provided:

“The work to- be done consists of clearing the West Fork reservoir site up to the flow line, as staked out at elevation of 608, of all trees, logs, stumps, brush and other undergrowth, to •the approval and satisfaction of the board of engineers.”

By a proposition in writing dated August 15, 1911, appellant offered to clear the land, in accordance with the specifications with the board of engineers on file, for $19.25 per acre. This bid was recommended for acceptance by the board of engineers on August 22,1911, said recommendation stating:

“It being further understood that O. T. Hodge understands that all of the land is not now purchased, and that the work shall progress under the direction of the board of engineers on such lands as are acquired and as may be acquired from time to time.”

This report was adopted, by the commissioners of the city, and the contract awarded to said Hodge. The contract between the city of Ft. Worth, styled party of the first part, and O. T. Hodge, styled party of the second part, dated September 21, 1911, provided, in part, as follows:

“First. Party of the second part agrees to clear the West Fork reservoir site, belonging to the party of the first part, or hereinafter to be acquired consisting of approximately 1,250 acres up to the flow line as staked out at an elevation of 607 feet [it is agreed that this number should be 608, and will be hereinafter so treated], of all trees, logs, on ground, but not in river channel, brush and other undergrowth (permanent improvements, houses, barns, outhouses, etc., excepted) to the approval and satisfaction of the board of engineers of the party of the first part. * * *
“Sixth. Party of the second part is to furnish bond in the sum of $5,000, conditioned upon the faithful performance of this contract and upon the payment by him to the full satisfaction of all claims for damage of every character whatsoever arising from or connected directly or indirectly with any work done by him or his agents or-employes under the provisions of this contract.
“Seventh. Party of the second part is to begin work clearing said reservoir site within ten days from date of acquiring all said land to be cleared, and all said work is to be completed within eleven months (or September 1, 1912) from said date and all timber and wood of every character belonging to the party of the second part shall be removed by him from said reservoir site above elevation 607 within said period. Extraordinary weather or conditions beyond control of party of second part shall extend the time of completion of this contract and the removal of said timber and wood to the extent of the time that such weather or conditions continue. * * *
“Ninth. Party of first part is to acquire by purchase or condemnation the land to be cleared as expeditiously as possible and consistent, in order that progress of the work may not be delayed.”

Plaintiff filed, his bond, dated September 22, 1911, with the Commonwealth Bonding & Casualty Insurance Company as surety, said bond ¡providing, in part, as follows:

“The condition of the above obligation is such that the said principal herein has entered into a certain contract with the said city of Ft. Worth, bearing date of September 21, 1911, for the performance of certain work in clearing off the West Fork reservoir site.
“Now, if the said principal herein shall faithfully do and perform all the obligations imposed on him in said contract, and shall save the said city harmless from any damage or injuries arising from, or connected directly or indirectly with, any work done by him or his agents or em-ployés under the provisions of said contract, then this obligation shall be null and void; otherwise to remain in full force and effect.”

The court in his findings of fact found that before the signing of any contract for the doing of said work, the timbered area within the lines of the reservoir as then proposed was estimated under the direction of' the board of engineers, and that said estimate showed said timbered area to consist of approximately 1,250 acres; that at the time sai’d contract was made and said work begun there were no stakes indicating where the 608 line extended, but the line of 615 feet elevation was staked' on the ground at said time and showed said 615 line to extend no further than the nine-mile bridge, and no lines had been marked north of said bridge; that said O. T. Hodge cleare'd 1,411 acres of land upon the reservoir site, and within the 608 line, which were accepted and paid for by the city of Ft. Worth, and that said Hodge cleared an additional amount of 590 acres, and that said work of clearing said 599 acres was accepted by the board of engineers. of the city, an'd that proper estimates. *585

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brawley v. United States
96 U.S. 168 (Supreme Court, 1878)
Rib River Lumber Co. v. Ogilvie
89 N.W. 483 (Wisconsin Supreme Court, 1902)
Wolff v. Wells, Fargo & Co.
115 F. 32 (Ninth Circuit, 1902)
Inman Bros. v. Dudley & Daniels Lumber Co.
146 F. 449 (Sixth Circuit, 1906)
Marx v. American Malting Co.
169 F. 582 (Sixth Circuit, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
196 S.W. 583, 1917 Tex. App. LEXIS 706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hodge-v-city-of-ft-worth-texapp-1917.