Hobelman v. Mel Krebs Construction Co.

366 P.2d 270, 188 Kan. 825, 1961 Kan. LEXIS 361
CourtSupreme Court of Kansas
DecidedNovember 10, 1961
Docket42,588
StatusPublished
Cited by14 cases

This text of 366 P.2d 270 (Hobelman v. Mel Krebs Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hobelman v. Mel Krebs Construction Co., 366 P.2d 270, 188 Kan. 825, 1961 Kan. LEXIS 361 (kan 1961).

Opinion

The opinion of the court was delivered by

Pabkeb, C. J.:

This is a workmen’s compensation case in which the award to the employee is not in dispute. In this appeal the only questions presented to the court are (1) whether the employers, and their respective insurance carriers, are jointly liable for payment of the award and (2) if so, which of such respondents is primarily liable for the payment.

Counsel for the contesting parties have filed a joint abstract thus simplifying the statement of facts which present the legal questions. The facts, none of which are disputed, may be summarized as follows:

The claimant, Herman Hobelman, regularly worked for the respondent, Joe Kreutzer Construction Company, a general contractor. *827 This company owned a large crane and made a business of renting it to other contractors in the same area. Respondent, Mel Krebs Construction Company was also a general contractor in such area.

On the date claimant sustained his accidental injuries the Krebs Construction Company was erecting a building in Garden City, Kansas, known as the Garden Bowl. Through a telephone conversation between the involved employer respondents, hereinafter referred to in our factual statement as Kreutzer and Krebs, it was arranged for Kreutzer to furnish Krebs with the crane and a crane operator on the morning of July 9, 1960, for the purpose of setting steel beams at the Garden Bowl project. In addition to the crane operator, Kreutzer also sent along the claimant, Hobelman, to help the crane operator in assembling the boom on the crane. Hobelman’s original instructions were to go to another job where Kreutzer was carrying on construction work when -the boom was assembled. Sometime after the arrival of the Kreutzer employees at the Garden Bowl project Krebs’ foreman requested that Hobelman be left with Krebs to help it with setting the steel beams as it was shorthanded. The Kreutzer crane operator replied that he had no authority to allow the claimant to remain with Krebs on its job. Later the Krebs foreman in a conversation with Joe Kreutzer, one of the owners of the Kreutzer Company, renewed the request he had made to the Kreutzer crane operator. Thereupon Joe Kreutzer acceded to the foreman’s request and instructed Hobelman to stay on the Krebs job and assist it in setting the steel beams. In this conversation Joe Kreutzer advised the foreman that Kreutzer would charge Krebs $2.00 an hour for Hobelman’s services.

After Hobelman started working for Krebs, and while engaged in assisting with the setting of the steel beams, Hobelman was injured. At that time the work was being supervised by Krebs’ foreman. Hobelman remained upon the regular payroll of Kreutzer, withholding taxes and other payroll deductions were made from his wages by Kreutzer, his wages were to be paid by Kreutzer, and its workmen’s compensation insurance premiums were based as though Hobelman remained on its payroll.

Following Hobelman’s accidental injury he filed his claim for workmen’s compensation against both Kreutzer and its insurance carrier, the Western Casualty and Surety Company, and Krebs and its insurance carrier, the Tri-State Insurance Company. Ultimately an award was rendered in his favor.

*828 On appeal the district court, in harmony with the findings and conclusions of the Examiner, as described by its journal entry of judgment concluded as follows:

“1. That the relationship of the claimant to the two respondents was that of a general employee of the Joe Kreutzer Construction Company and that of a special employee of the Mel Krebs Construction Company.
“2. That the Joe Kreutzer Construction Company was not a sub-contractor of the Mel Kreb’s Construction Company as that term is used in Section 44-503, G. S. 1949.
“3. That both respondents and their respective insurance carriers are jointly and severally liable to the claimant for the payment of all Workmen’s Compensation, medical expenses, and other items due him under the Workmen’s Compensation Law.
“4. That as between themselves, the two respondents and their insurance carriers are each equally liable for the payment of said items and that if either should fail to pay its one-half share of the same and the other be required to pay all, that the one being required to pay all would then be entitled to recover of and from the other the one-half it paid upon the other’s behalf; but that as between themselves, so long as each pays its one-half share of said compensation, there is no primary and secondary liability and neither is entitled to recover from the other any of the compensation and other items that it is hereby required to pay.”

Neither of the respondents question the right of the claimant to file his claim against them jointly. The respondent, Krebs, and its insurance carrier, have appealed contending that the trial court erred in finding that the relationship of the claimant to respondents was that of a general employee of Kreutzer and that of a special employee of Krebs. It further contends that the court should have found that Kreutzer was the subcontractor of Krebs within the meaning of the term “subcontractor” as used in G. S. 1949, 44-503, and that Kreutzer and its insurance carrier were primarily liable to claimant for all compensation and that no compensation was due him from Krebs or its insurance carrier, unless Kreutzer and its insurance carrier failed to pay all compensation due.

The respondent, Kreutzer and its insurance carrier have filed a cross-appeal contending that the court, having found the relationship between the respondents to be that of general employer and special employer, should have found the special employer primarily liable for the award.

We have no difficulty in concluding, under the facts of this case, that the status of the respondents is that of general employer and special employer and not that of contractor and sub-contractor. Neither do we have difficulty in concluding that the respondents *829 are jointly liable for the award to claimant under the Workmens Compensation Act.

In the case of Mendel v. Fort Scott Hydraulic Cement Co., 147 Kan. 719, 78 P. 2d 868, under very similar facts, we stated that the relationship of the respondents to the claimant was that of general employer and special employer and there held:

“Where a general employer loans his workman to another and directs him to do certain work which is being done under the supervision and control of such other or special employer, and which work is also a part of the general employer’s trade or business in which injuries are compensable under the compensation act, and the workman continues at all times in the employ of the general employer who pays his compensation and who remains vested with full power to discharge him for refusal to do the work for the special employer which he was directed to do, such employee, if injured while engaged in such work, may look to both employers and their respective insurance carriers for compensation.” (Syl. ¶ 4.)

The extension of this opinion to include the reasons and the authorities for our conclusion in the Mendel

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lamb v. Southwest Commodities, LLC
Court of Appeals of Kansas, 2017
Mitchell v. Petsmart, Inc.
239 P.3d 51 (Supreme Court of Kansas, 2010)
Tull v. ATCHISON LEATHER PRODUCTS, INC.
150 P.3d 316 (Court of Appeals of Kansas, 2007)
Scott v. Altmar, Inc.
38 P.3d 673 (Supreme Court of Kansas, 2002)
BB & B Transportation v. Industrial Commission
893 P.2d 611 (Court of Appeals of Utah, 1995)
Helms v. Tollie Freightways, Inc.
889 P.2d 1151 (Court of Appeals of Kansas, 1995)
Workers Compensation Fund v. Silicone Distributing, Inc.
809 P.2d 1199 (Supreme Court of Kansas, 1991)
American States Insurance v. Hanover Insurance
794 P.2d 662 (Court of Appeals of Kansas, 1990)
Antonini v. Hanna Industries
573 P.2d 1184 (Nevada Supreme Court, 1978)
Drennon v. Braden Drilling Co., Inc.
483 P.2d 1022 (Supreme Court of Kansas, 1971)
Shinkle v. State Highway Commission
448 P.2d 12 (Supreme Court of Kansas, 1968)
Kuhn v. Grant County
439 P.2d 155 (Supreme Court of Kansas, 1968)
Atwell v. Maxwell Bridge Co.
409 P.2d 994 (Supreme Court of Kansas, 1966)
Leggette v. J. D. McCotter, Inc.
144 S.E.2d 849 (Supreme Court of North Carolina, 1965)
Landes v. Smith
368 P.2d 302 (Supreme Court of Kansas, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
366 P.2d 270, 188 Kan. 825, 1961 Kan. LEXIS 361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hobelman-v-mel-krebs-construction-co-kan-1961.