Hoare v. Glann

168 P. 346, 176 Cal. 309, 1917 Cal. LEXIS 518
California Supreme Court·Decided October 16, 1917·No. S. F. No. 7554. Department One.·Published·Cited by 3 cases

Opinion

SHAW, J.

The defendant appeals from the judgment and from an order denying her motion for a new trial. The action was begun in the lifetime of Nathaniel P. Glann. The complaint states a cause of-action against him for the recovery of $4,463.24, alleged to have been due from him to the plaintiff, for crushed.rock sold and delivered by plaintiff to said Glann. After the trial, but before the decision below, Glann died and the defendant, as administratrix of his estate, was duly substituted as defendant.

The answer alleged as a counterclaim against the plaintiff that the plaintiff was indebted to Glann in the sum of $6,590.64 for crushed rock belonging to Glann, appropriated and used by said plaintiff, upon which, after deducting the amount due to the plaintiff upon the account sued on by him, there remained a balance of $2,127.40, for which the defendant asked judgment against the plaintiff.

The court found that the money was due to the plaintiff from the decedent for the rock sold by plaintiff to said decedent in his lifetime, as alleged in his complaint, but that the plaintiff had not appropriated or used any rock belonging to said decedent and was not indebted to decedent, and that nothing was due upon the counterclaim. Judgment was thereupon given for $4,463.24 due upon the plaintiff’s claim.

The facts are as follows: The plaintiff entered into a contract with the town of Larkspur for the paving of a street -in said town. After making the contract Hoare assigned the same to said Nathaniel P. Glann. The agreement of assignment provided that Glann was to perform the work required by said contract and that if he failed to prosecute the work to the satisfaction of the engineer of the town of Larkspur, or the board of trustees thereof, then upon written notice to Hoare from said board that the contract was not being properly performed, the interest of Glann in the contract should cease, and that Hoare might thereupon inform the board that the assignment had been terminated and immediately proceed to complete the work himself. There was an oral agreement between Glann and Hoare, at the time of the assignment, that Glann should purchase from Hoare the *311 crushed rock to be used in performing the contract, to be delivered by Hoare on the cars at Petaluma at the price of eighty cents per ton. In pursuance of the assignment Glann entered upon the performance of the contract and did a large amount of work thereunder. Under the oral agreement he purchased from Hoare a large quantity of crushed rock which was delivered to him at Petaluma, and by him was carried from Petaluma to the place of work, along the streets, ready for use. He had not paid therefor in full, and the amount sued for in the complaint was the balance unpaid upon the rock so purchased. Glann had also procured rock from others and some of this rock had been delivered for use on the street. When Hoare took charge of the work after the default of Glann a large quantity of this rock lay along the line of work ready for use. There was evidence tending to prove that the value of this rock, in place, as it lay ready for use, was $6,590.64, as alleged in. the counterclaim. After partly completing the work Glann was notified by the town board that the work was not being done to the satisfaction of the engineer, and the board also gave written notice to Hoare that the contract was not being properly performed. The board refused to allow Glann to proceed, and directed that Hoare should complete the work under the original contract with the town. Hoare proceeded to complete the work after taking charge thereof, and used in such completion the whole of the rock so provided by Glann therefor and lying along the line of the- work.

The court below made findings to the effect that Hoare had not appropriated, taken, or used any rock or other property belonging to Glann, and held that Glann was not entitled to anything bn account of the rock provided by him along the„ street and used by Hoare in the completion of the improvement.

' The original contract with the town of Larkspur provided that if Hoare, the original contractor, failed to perform the work to the satisfaction of the town authorities, the town itself could take possession thereof and proceed to complete the work, and that if it did so, the material provided for its completion by the contractor and delivered upon and along the work should become the property of the town, and could be used by it in such completion without allowing the contractor anything therefor; The court below was of the *312 opinion that when Hoare took charge of the work to complete the contract he did so as agent of the town of Larkspur; that he was entitled to all the rights of said town, and that in using the material already provided by Glann he was not appropriating the property of Glann to that use, but was taking property which belonged to the town of Larkspur, and that he owed Glann nothing therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Hoare v. Glann, 168 P. 346, 176 Cal. 309, 1917 Cal. LEXIS 518 (Cal. 1917).

168 P. 346 (Hoare v. Glann) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hill v. Superior Court
106 P.2d 876 (California Supreme Court, 1940)
Runkle v. Lane
105 P.2d 373 (California Court of Appeal, 1940)
Los Angeles Drug Co. v. Superior Court
63 P.2d 1124 (California Supreme Court, 1936)