HL Properties, Inc. v. AEROJET-GENERAL CORPORATION

331 F. Supp. 1006, 1971 U.S. Dist. LEXIS 13285
CourtDistrict Court, S.D. Florida
DecidedMay 14, 1971
Docket68-136-Civ-CA
StatusPublished
Cited by12 cases

This text of 331 F. Supp. 1006 (HL Properties, Inc. v. AEROJET-GENERAL CORPORATION) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HL Properties, Inc. v. AEROJET-GENERAL CORPORATION, 331 F. Supp. 1006, 1971 U.S. Dist. LEXIS 13285 (S.D. Fla. 1971).

Opinion

MEMORANDUM OPINION AND ORDER

ATKINS, District Judge.

THIS CAUSE came on for trial before the Court without a jury on April 27, 1971. The Court heard testimony, received exhibits, has reviewed the depositions of Benjamin A. Simmons, Jack D. Sohl, Willis Sprattling, Jr., and John Amaral as well as the Answers to Interrogatories Propounded by Aerojet-General Corporation to United States of America filed September 22, 1970 and is otherwise fully informed in the premises.

Subsequent to the pretrial conference but prior to trial the Court granted plaintiff’s motion for summary judgment against the defendant Aerojet-General Corporation without opposition by said defendant. The trial, therefore, was limited to the question of liability of the United -States of America (hereinafter the Government) pursuant to the Federal Tort Claims Act, Title 28 U.S.C.A. Section 2671, et seq. and Title 28 U.S.C.A. Section 1346.

It is well-established that the Government cannot be held liable without fault. Dalehite v. United States, 346 U.S. 15, 73 S.Ct. 956, 97 L.Ed. 1427 (1953). However, under the rationale of Emelwon, Inc. v. United States, 391 F.2d 9 (5th Cir. 1968), cert. den. 393 U.S. 841, 89 S.Ct. 119, 21 L.Ed.2d 111, the Government could be held liable under either of two theories of Florida law, both of which impose liability upon ah employer of an independent contractor for its own negligence.

The first theory of Florida law imposes a duty upon an employer who discovers a dangerous situation created by its independent contractor either to halt the operation or otherwise remove the danger. Maule Industries, Inc. v. Messana, 62 So.2d 737 (Fla.1953); Peairs v. Florida Publishing Co., 132 So.2d 561 (1st D.C.A.Fla.1961).

The second theory of Florida law imposes a non-delegable duty on the employer to exercise reasonable care to prevent harm to third persons when the independent contractor is performing inherently or intrinsically dangerous work. Florida Power & Light Co. v. Price, 170 So.2d 293 (Fla.1964).

Liability is sought to be imposed upon the Government by virtue of the August 29, 1966 contract between the National Aeronautics and Space Administration, an agency of the Government, and Aerojet-General Corporation concerning the design, fabrication and testing of an improved 260-inch SL-3 solid rocket motor. The contract provided that the subject rocket motor would be tested on or before June 30, 1967. In fact, such rocket motor was tested on June 17, 1967 at Aerojet-General Corporation’s test-firing site located in South Dade County, Florida. The parties have stipulated that as a result of the test firing on July 17, 1967, the rocket motor emitted hydrogen chloride gas into the atmosphere which mixed with rain or moisture thus forming hydrochloric acid which caused some damage to the fruit and plants of certain of the plaintiffs. For the purposes of the trial on liability it was stipulated that the plaintiffs are owners or lessees of property located in Dade County, Florida. Additionally, it was stipulated that the plaintiffs have complied with the jurisdictional requirements of the Federal Tort Claims Act. Hence, plaintiffs may proceed against the Government.

*1008 The parties have likewise stipulated that the test-firing of the 260-inch SL-3 solid rocket motor on June 17, 1967 was an ultra hazardous activity and Aerojet-General Corporation has conceded that it was negligent. The Court finds both of these items to be the fact and considers that the ultrahazardous activity is at least what is meant by inherently dangerous within the meaning of the non-delegable duty rule of the Price case. The court finds that the Government had a non-delegable duty to assure that Aerojet-General Corporation performed its task in a non-negligent manner. The sole question for decision is whether the Government negligently breached this duty.

Under Article III of the contract between the defendants, NASA retained technical direction of the project. The evidence shows that this clause merely gave NASA the power to assure that the technical results of the test-firing would be as contemplated under the contract.

The contract also gave the Contracting Officer the authority both to terminate the contract and to impose upon Aerojet-General Corporation any safety and health requirements deemed necessary. The Court notes these provisions only to show that the Government had not relinquished total control of the operation to its independent contractor. Throughout the trial the Government asserted that it was bound by its contract which, it was argued, did not give the Government the right to cancel or postpone the test-firing of July 17. The evidence shows that NASA’s only concern with these two clauses was additional expense to be incurred in a postponement of the test-firing and with the safety of those employees of both Aerojet-General Corporation and NASA involved in the project, respectively. It is not necessary to decide this point nor to resolve the total conflict between the testimony of the Aerojet-General Corporation witnesses and those of the government concerning the authority of Carl C. Cieplueh, the NASA project manager, to stop the test-firing.

Every witness who was present at the test-firing testified that throughout the morning of July 17, 1967 there was intermittent rain and that at the time of the test-firing (12 o’clock noon) there was a very light shower. The weather data sheet (Plaintiff’s Exhibit 2) confirms this testimony and further demonstrates that the sky was overcast at about 1500 feet and winds were out of the south at about ten knots with gusts to thirty-four knots on the surface. The Court does not believe it necessary to review the evidence any further.

Aerojet-General Corporation, through Jack D. Sohl, was in virtual constant contact with the Homestead Weather Station and the FAA Miami Approach Control during the countdown stages. All of the pertinent weather data was available to Mr. Sohl and, in fact, was communicated to him. Mr. Bankaitas, the NASA sub-project manager, whose duty it was to monitor the work of Mr. Sohl, had this data available to him.

The effect of the prevailing weather conditions was three-fold: (1) the overcast sky inhibited diffusion of the hydrogen chloride gas into the atmosphere; (2) the rain mixed with the gas to create the damaging hydrochloric acid; and (3) the Southerly winds caused the rocket motor exhaust plume and, consequently, the hydrochloric acid fallout to move in a northerly direction over the property of the plaintiffs. It was clearly negligence to proceed with the test-firing under these weather conditions.

Further, the uncontradieted evidence is that the sole concern of all people involved in the project was that nothing should interfere with the collection of good test data. Whether, in particular, was a concern only in its effect upon photography and the performance of certain delicate data recording devices. It was determined, without objection by any NASA representative, that the light showers would not impede the success of the test-firing. No consideration was given at that point to the possible inju *1009

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
331 F. Supp. 1006, 1971 U.S. Dist. LEXIS 13285, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hl-properties-inc-v-aerojet-general-corporation-flsd-1971.