Hirschfeld v. Borchard Affiliations, Inc.

20 Misc. 2d 680, 190 N.Y.S.2d 588, 1959 N.Y. Misc. LEXIS 3474
CourtNew York Supreme Court
DecidedJune 16, 1959
StatusPublished
Cited by3 cases

This text of 20 Misc. 2d 680 (Hirschfeld v. Borchard Affiliations, Inc.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hirschfeld v. Borchard Affiliations, Inc., 20 Misc. 2d 680, 190 N.Y.S.2d 588, 1959 N.Y. Misc. LEXIS 3474 (N.Y. Super. Ct. 1959).

Opinion

Abraham N. Geller, J.

At the close of the trial the court

rendered an oral decision on the record making findings of fact relating to plaintiff purchaser’s causes of action for the return of his deposit and for damages and defendant seller’s counterclaim for specific performance, and concluding that plaintiff’s causes were dismissed on the merits and that defendant was entitled to a decree of specific performance. The question of adjustments and the effective date thereof was expressly left open, the parties being directed, in the absence of agreement thereon, to submit briefs on the subject “with due regard to the facts in this litigation.” After such submission the court set the matter down for a further hearing, at which additional evidence bearing on the subject of adjustments was received, and in addition, subsequently requested and received a letter from defendant’s attorneys giving undisputed particulars of a fact previously stated in general terms only, which letter has been marked as court’s Exhibit AA.

Superficially it would appear that since the court has found that defendant is entitled to specific performance and that since [682]*682March 12, 1958 it has been ready, willing and able to convey title to the premises in question to plaintiff, the adjustments should be simply computed as of that date. However, there are equitable considerations arising from the particular facts in this case which impel the court to probe more deeply into the question of the relative equities of the parties in order to serve the ends of justice — the proper function of the court when granting relief by a decree requiring specific performance of a contract.

“ Once the jurisdiction of equity has attached, it will itself proceed to round out the whole circle of the controversy, and decide every other contention connected with the subject matter of the suit essential to do complete justice.” (49 Am. Jur., Specific Performance, § 170, p. 192.) In decreeing specific performance equity requires not only that the contract provisions to be enforced be just and equitable but that the consequences of specific performance likewise be just and equitable and grants relief only on terms that do the other party equity (49 Am. Jur., Specific Performance, pp. 72, 201).

Actually the problem here is divisible into two parts, as suggested by the court in its oral decision. Defendant is entitled to a decree of specific performance of the terms of the contract, but with closing and current adjustments of the items therein enumerated to be effectuated as of the time of the decree in place of the date originally fixed in the contract. The second — and more complex — problem is the assessment of responsibility and damages for the delay in closing from March 12, 1958, when the seller had cleared up the defect, to the date of decree.

The right of the court to grant such additional, incidental or ancillary relief as is necessary to work out the equities of the parties has been uniformly recognized (81 C. J. S., Specific Performance, p. 762). In Powell on Real Property (vol. 6, § 930, p. 341) it is said: “ The equitable elasticity of the procedure for specific performance makes it possible for a court to supplement its basic decree for the completion of the transaction by an assessment and award of damages for the wrongful delay of one of the parties, or by an accounting of the respective losses and gains during the period of litigation ”.

The pertinent facts bearing on the issue of delay found by the court are as follows:

On December 3, 1957, the original date of closing, the seller requested an adjournment in order to verify buyer’s claim of defect with regard to an alteration of two apartments into a single doctor’s office, but insisted that all adjustments should nevertheless be retroactive as of the original closing date. It [683]*683is conceded that the buyer was willing to grant the adjournment provided adjustments be made as of the date of actual closing and that he stated that he was willing to close then and there if seller gave him a letter undertaking that the obligation to correct the defect, if confirmed, would survive the closing of title. The seller refused to accept either offer and the parties separated with a formal tender by the seller of the deed and a request by the buyer for the return of his deposit. On December 9, 1957 seller’s attorneys wrote to buyer’s attorney that its architect had advised that he would proceed with the necessary measures to procure an amendment of the certificate of occupancy to clear up the objection and that their client was now ready to deliver appropriate undertaking to so amend at its own expense and was prepared to close on December 11, 1957. The response by letter of buyer’s attorney dated December 11 reviewed his client’s offers at the December 3 closing, pointing out that seller had taken the position that any adjournment be subject to retroactive adjustments, and concluded with the statement that thereby seller had repudiated the contract. Buyer then commenced this suit to recover the deposit and damages on December 13, 1957 and seller counterclaimed for specific performance. In the meantime seller, after expending the sum of $2,145.50 to make the necessary changes, obtained an amended certificate and on March 12, 1958 forwarded a copy thereof to buyer’s attorney together with a demand for closing on not less than two days’ notice, which was rejected in view of the “ time ” and “ nature thereof.”

At no time did seller indicate that it had receded from its fixed position that all adjustments should be as of original closing date. Under these circumstances, especially in view of the adamant attitude of seller on December 3 and the tenor of buyer’s letter of December 11, it was incumbent upon seller to make clear that it now agreed that adjustments be computed as of the date of actual closing when it would be enabled to give clear title. That obligation was not satisfied by seller’s vague reference in its March 12 offer to transfer title ‘ ‘ in full, complete and technical compliance with the requirements of the contract.” Indeed, the wording of that phrase might suggest that it was still insisting on retroactive adjustments. There is no question but that seller failed to make a clear, unequivocal commitment as to the date of adjustments being March 12, 1958 — the appropriate equitable date under the authorities for adjustments in a case where a seller has perfected title and made a proper tender, time not being of the essence and no prejudice to buyer having taken place (Pakas v. [684]*684Clarke, 136 App. Div. 492, affd. 203 N. Y. 534). Further proof of defendant’s equivocal attitude is furnished by its trial memorandum, submitted as late as May, 1959, which urged that it was entitled to specific performance as of December 11, 1957, although in its memorandum accompanying the proposed judgment it now requests a closing date as of March 12, 1958. It is true that the buyer did not make reasonable response to seller’s offer of March 12 and that the court has determined that he is required to specifically perform the contract, but it is also clear that seller’s failure to make an unequivocal offer may have contributed in great measure to the resultant delay. Had it done so, buyer’s refusal to complete the deal at that time would have cast all responsibility for the delay upon him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bregman v. Meehan
125 Misc. 2d 332 (New York Supreme Court, 1984)
In Re North Broadway Funding Corp.
6 B.R. 133 (E.D. New York, 1980)
Gettinger v. Lattingtown Harbor Development Co.
17 A.D.2d 629 (Appellate Division of the Supreme Court of New York, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
20 Misc. 2d 680, 190 N.Y.S.2d 588, 1959 N.Y. Misc. LEXIS 3474, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hirschfeld-v-borchard-affiliations-inc-nysupct-1959.