Hir v. Kaye

26 Mass. L. Rptr. 2
CourtMassachusetts Superior Court
DecidedAugust 11, 2009
DocketNo. 062063
StatusPublished

This text of 26 Mass. L. Rptr. 2 (Hir v. Kaye) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hir v. Kaye, 26 Mass. L. Rptr. 2 (Mass. Ct. App. 2009).

Opinion

Billings, Thomas P., J.

The plaintiffs (the “builders”) are home builders; the defendants (the “homeowners”), former clients. There has already been an arbitration hearing and award on the plaintiffs’ claim for [3]*3compensation due under the contract. The issue presented in this case concerns a second demand for arbitration, this time by the defendant homeowners, who are seeking damages for alleged defects in the construction. The plaintiffs seek a declaratory judgment that the new claims are, in whole or in part, precluded by the prior arbitration and award.

For the reasons that follow, judgment shall enter declaring the rights of the parties, as set out in the Order below.

FINDINGS OF FACT

Based on the credible evidence and the reasonable inferences therefrom, and accepting as fact certain stipulations recorded as paragraphs 1-7 at pp. 1-2 of the Joint Pretrial Memorandum, I find the following facts.

1. Stephen Hir and William Willhoite are contractors. Joanne Kaye and Sheri Foreman are homeowners whose Lexington home was accidentally destroyed by fire. In the spring of 2003, therefore, they contracted with Hir and Willhoite to construct a new home on the same lot, using drawings and specifications drawn up by their architect, Eva Kasell.

2. The written contract, titled “Agreement for Design and Construction,” was signed by both parties on April 8, 2003. Substantial completion was to occur no later than thirty-one weeks from the issuance of all necessary permits. The price of $408,000.00 plus $35,000 in owners’ allowances for specified items was payable in installments tied to specified construction milestones.

3. In Article XV, the contract contained an arbitration clause:

If a dispute arises between the parties relating to or arising out of any provisions of this Agreement or any breach or alleged breach of this Agreement, either parly may request arbitration. Either party may invoke the dispute resolution procedure of this clause by giving written notice to the other. The notice should include a brief description of the disagreement. An arbitrator will be promptly selected by mutual consent of the parties from the Commercial Division of the American Arbitration Association, and any such Arbitration shall take place in Boston, Massachusetts or such closer location to the Project Site as may be available from AAA. The parties agree to participate in good faith in the arbitration to conclusion. The cost of arbitration, including fees and expenses, shall be borne equally by the parties.

4. Such a dispute arose in early 2004. The Town had issued a Certificate of Occupancy on or about January 30,2004; the homeowners had moved in; and the builders asserted that the next progress payment was due. The homeowners, pointing to substantial uncompleted work, disagreed.1

5. On February 4, 2004 the builders ceased work. Further discussions with the homeowners resulted in a partial payment of $20,000,2 but the parties still could not agree on how to finish the project: the homeowners, now that they, their two children, and their belongings and furnishings were moved in, wanted advance notice of any further work, preferred that it be done on weekends, and asked that all keys to the house be returned. The builders felt that a weekend schedule was unrealistic, and unfair to their subcontractors, and were unable to account for the outstanding keys to the homeowners’ satisfaction.

6. The homeowners changed the locks. Thereafter, the builders came by one day when the homeowners were not home, let themselves in through an open door, collected their supplies and equipment, and took video footage to document their claim for compensation.

7. The Rubicon had now been crossed, by both sides. The homeowners did not thereafter ask the builders, and the builders did not offer, to correct or complete any work, except once when the homeowners discovered, as the weather got warm, that the air conditioning didn’t work. (The builders put them in touch with the HVAC subcontractor, but he would not deal with them because he understood the proj ect was in litigation. The homeowners got someone else to come and charge the air conditioner.)

8. The builders served the homeowners with a Demand for Arbitration dated March 1,2004, claiming $64,686.00 as the full amount unpaid on the contract price. By the time of the arbitration hearing in September, the parties had stipulated that the unpaid balance of the contract price was $56,626.00.

9. The homeowners asserted no counterclaims, but defended the arbitration on the ground that some or all of the work for which the builders claimed payment was uncompleted.

10. The arbitration hearing extended over two days about a week apart, concluding on September 22, 2004. On November 18 the arbitrator, James W. Savage, issued his decision, awarding the builders the sum of $33,519.73. This he arrived at as follows (quoting from the one-page Award):

Stipulated Balance of Contract $56,626.00
For the Respondents (homeowners) to complete:
1. Landscaping 9,180.00
2. Irrigation 1,425.00
3. Painting 1,000.00
4. Carpentry 5,612.31
5. HVAC 548.35
6. Plumbing 690.61
7. Electrical 900.00
8. Credit: Custom Media Cabinet Work 450.00
9. Credit: Kitchen Tile Backsplash Work 300.00
10. R&RMiscellaneous Ext. & Int. Work 3.000.00
Total $23,106.27

The $23,106.27 in credits due the homeowners, subtracted from the $56,626.00 contract balance, meant that $33,519.73 was due the builders.

[4]*411. The Award (as is customary) provides no further guidance as to what issues were litigated, what facts the Arbitrator found, and what deficiencies resulted in the credits to the Homeowners. Nor is there a transcript or other record of the hearings. From the Arbitrator’s reference to items “to complete,” however, and also from the testimony received in the jury-waived trial before me, I believe, and therefore find, that the credits in the Arbitrator’s award were for uncompleted items, not for correction of construction defects (with the one possible exception of the extra irrigation required due to the foundation mislocation; see below).

12. Taking judicial notice of the dockets of this Court, I find that the homeowners have paid the arbitration award.

13. The homeowners allege various defects in the construction, at least some of which have manifested themselves after the builders commenced their arbitration proceeding and, in some cases, after the hearing and award. The alleged defects are as follows.

14. Leaking Roof. Water has entered the roof and caused yellow stains around two ceiling light fixtures in the master bedroom. The staining first became apparent in January or February of 2005.

15. Plaster “boils” andpeeling. The interior walls are' plastered, not sheetrocked.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrews v. Wade & De Young, Inc., P.C.
950 P.2d 574 (Alaska Supreme Court, 1997)
Gloucester Marine Railways Corp. v. Charles Parisi, Inc.
631 N.E.2d 1021 (Massachusetts Appeals Court, 1994)
Louison v. Fischman
168 N.E.2d 340 (Massachusetts Supreme Judicial Court, 1960)
Wright MacHine Corp. v. Seaman-Andwall Corp.
307 N.E.2d 826 (Massachusetts Supreme Judicial Court, 1974)
Heacock v. Heacock
520 N.E.2d 151 (Massachusetts Supreme Judicial Court, 1988)
Yentile v. Howland
525 N.E.2d 689 (Massachusetts Appeals Court, 1988)
Blanchette v. School Committee of Westwood
692 N.E.2d 21 (Massachusetts Supreme Judicial Court, 1998)
O'Neill v. City Manager
700 N.E.2d 530 (Massachusetts Supreme Judicial Court, 1998)
TLT Construction Corp. v. A. Anthony Tappe & Associates, Inc.
716 N.E.2d 1044 (Massachusetts Appeals Court, 1999)
Mancuso v. Kinchla
806 N.E.2d 427 (Massachusetts Appeals Court, 2004)
Beals v. Commercial Union Insurance
808 N.E.2d 824 (Massachusetts Appeals Court, 2004)
Rudell v. Comprehensive Accounting Corp.
802 F.2d 926 (Seventh Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
26 Mass. L. Rptr. 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hir-v-kaye-masssuperct-2009.