Himes v. Cameron County Construction Corp.

432 A.2d 1092, 289 Pa. Super. 143
CourtSuperior Court of Pennsylvania
DecidedSeptember 2, 1981
Docket1145
StatusPublished
Cited by6 cases

This text of 432 A.2d 1092 (Himes v. Cameron County Construction Corp.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Himes v. Cameron County Construction Corp., 432 A.2d 1092, 289 Pa. Super. 143 (Pa. Ct. App. 1981).

Opinion

MONTGOMERY, Judge:

The appeal in this case arises from an interpleader action instituted by the Carrolltown Borough Municipal Authority (hereinafter referred to as the “Authority”), as a result of a public works project. The work on the project was done by the Cameron County Construction Corporation (hereinafter referred to as “Contractor”). Pursuant to its contract 1 with the Contractor, the Authority withheld 10% of the agreed contract price, a sum of almost $44,000. That sum constitutes the fund in dispute in this case. One of the claimants was the Emporium Trust Company (hereinafter referred to as the “Bank”), which had loaned money to the Contractor to finance its work on the project. The Contractor had not completed its repayments to the Bank on the loan. In opposition to the claim of the Bank, claims were asserted by a group of several persons and business entities which provided labor and material to the Contractor for the project. The members of this latter group will be referred to collectively herein as the “Suppliers”. The lower court determined that the Suppliers should prevail and were entitled to *146 the fund held by the Authority after the completion of the project. The Bank has appealed the lower court’s rejection of its claim to a priority right to that fund.

A more detailed review is appropriate of what appear to be the undisputed facts of record. On October 18, 1972, the Contractor was awarded a construction contract by the Authority to construct sanitary sewers and related construction projects. The Contractor borrowed ninety five thousand eight hundred seventy dollars and seventy five cents ($95,870.75) from the Bank in order to begin work on the project. Simultaneously, the Contractor made an assignment of and granted a security interest in the proceeds of the contract to the Bank, as collateral for the loan. The Bank thereafter, in October and November, 1972, filed financing statements, pursuant to the provisions of the Uniform Commercial Code, 12A P.S. § 9-101 et seq., in the offices of the Prothonotary of Cambria County and the Department of State of the Commonwealth of Pennsylvania. 2

Pursuant to the requirements of the Public Works Contractors Bond Law of 1967, December 20, 1967, P.L. 869, 8 P.S. § 191 et seq., the Contractor obtained a bond from the Summit Insurance Company (hereinafter referred to as the “Insurer”), to insure the payment of bills from suppliers of labor or materials to the project.

In October, 1973, the Contractor commenced work on the project, which was completed in late November, 1974. At the time of the completion of the project, the Contractor owed the Bank more than $88,000 in principal and accumulated interest. The Authority had in its possession the sum of $43,694.50 representing the final payment due to the Contractor, which had been held pursuant to the following provisions of the construction agreement:

“In making partial payments there shall be retained 10% of the amount of each payment until final completion and *147 acceptance of all work covered by the contract . . . The entire balance found to be due the Contractor including retained percentages but excepting such sums as may be lawfully retained by [Authority] shall be paid to the Contractor. Such payments shall be conditioned, however, upon submission by the Contractor of evidence that all claims for labor, material and any other outstanding indebtedness in connection with this contract has been paid.”

The contract further provided:

“Payments Withheld. The Engineer [for the Authority] may withhold or, on account of subsequently discovered evidence, modify the whole or part of any estimate to such extent as may be necessary to protect [Authority] from loss on account of . . . (c) Failure of Contractor to make payments properly to subcontractors or for material or labor.”

As is evident from the facts recited thus far, the Contractor paid neither the Bank nor several Suppliers. While the Insurer would ordinarily have covered the Contractor’s debts to the Suppliers, the record shows that on May 28, 1975, the Insurer became insolvent and was placed in liquidation in the State of New York.

Cloyd Himes, a supplier, brought suit in assumpsit against the Contractor and obtained a judgment on September 27, 1975. 3 Himes then served the Authority with attachment proceedings and the Authority, in turn, filed for Interpleader relief pursuant to Pennsylvania Rules of Civil Procedure 2301 et seq. The Authority interpleaded all known creditors of the Contractor. Some of the creditors who were joined were later dismissed from the action for failure to file claims. On May 14, 1976, a hearing was held before the Court of Common Pleas of Cambria County. At that hearing, all counsel present agreed that there were no disputed *148 issues of fact before the Court. Each of the claimants submitted claims to the Court and the factual content of each claimant’s claim was stipulated as correct by each of the remaining claimants. Thereafter, the lower court ordered that the Suppliers, rather than the Bank, should receive the remaining fund of $43,694.50 from the Authority. Subsequently the Bank filed the instant appeal in our Court.

The Appellant Bank claims that Article 9 of the Pennsylvania Uniform Commercial Code 4 requires that it be accorded priority among the various claimants to the “proceeds” of the construction contract. Further, the Appellant argues that the lower court erred in placing reliance upon the decision in Jacobs v. Northeastern Corp., 416 Pa. 417, 206 A.2d 49 (1965), to support its order that the Suppliers were entitled to the fund in dispute in this case. Appellees do not deny that the Bank had a perfected security interest in the “proceeds” of the contract. However, they maintain that the fund in question never became “proceeds” to which the Bank could be entitled. After careful consideration of the facts and applicable law, we agree with the lower court and the Appellees.

Any analysis of this problem requires an initial review of the terms of the assignment from the Contractor to the Bank, on which the latter’s asserted security interest is based. The terms of that assignment provide:

[Contractor] does hereby transfer, set-over, and assign to The Bank, its successors and assigns, all moneys that are now, or may hereafter become due and payable to [Contractor] by [Authority] . .. under a contract between [Contractor] and [Authority] . . . for the construction of

The assignment reveals that the only “moneys” in which the Bank had a security interest were those which “. . . now or hereafter become due and payable ...” to the Contractor. Of course, the Contractor could not assign to the Bank any greater right than that which the Contractor itself possessed *149 or would attain under the agreement with the Authority.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trevdan Building Supply v. Toll Bros., Inc.
996 A.2d 520 (Superior Court of Pennsylvania, 2010)
United States Fidelity & Guaranty Co. v. United Penn Bank
524 A.2d 958 (Supreme Court of Pennsylvania, 1987)
Penn Equipment & Tool Corp. v. Chatham 90 Inc.
45 Pa. D. & C.3d 677 (Alleghany County Court of Common Pleas, 1986)
Himes v. Cameron County Construction Corp.
444 A.2d 98 (Supreme Court of Pennsylvania, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
432 A.2d 1092, 289 Pa. Super. 143, Counsel Stack Legal Research, https://law.counselstack.com/opinion/himes-v-cameron-county-construction-corp-pasuperct-1981.