Hilt Constr. & Mgmt. Corp. v. Permanent Mission of Chad

CourtCourt of Appeals for the Second Circuit
DecidedJune 16, 2021
Docket19-2971-cv
StatusUnpublished

This text of Hilt Constr. & Mgmt. Corp. v. Permanent Mission of Chad (Hilt Constr. & Mgmt. Corp. v. Permanent Mission of Chad) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hilt Constr. & Mgmt. Corp. v. Permanent Mission of Chad, (2d Cir. 2021).

Opinion

19-2971-cv Hilt Constr. & Mgmt. Corp. v. Permanent Mission of Chad

UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT SUMMARY ORDER Rulings by summary order do not have precedential effect. Citation to a summary order filed on or after January 1, 2007, is permitted and is governed by Federal Rule of Appellate Procedure 32.1 and this court’s Local Rule 32.1.1. When citing a summary order in a document filed with this court, a party must cite either the Federal Appendix or an electronic database (with the notation “summary order”). A party citing a summary order must serve a copy of it on any party not represented by counsel.

At a stated term of the United States Court of Appeals for the Second Circuit, held at the Thurgood Marshall United States Courthouse, 40 Foley Square, in the City of New York, on the 16th day of June, two thousand twenty-one.

PRESENT: Robert D. Sack, Gerard E. Lynch, Steven J. Menashi, Circuit Judges. ____________________________________________

HILT CONSTRUCTION & MANAGEMENT CORPORATION,

Plaintiff-Counter-Defendant-Appellee,

v. No. 19-2971

THE PERMANENT MISSION OF CHAD TO THE UNITED NATIONS IN NEW YORK,

Defendant-Counter-Claimant-Appellant. * ____________________________________________

* The Clerk of Court is directed to amend the caption as set forth above. For Defendant-Counter-Claimant-Appellant: Ryanne Konan, Ryanne Konan Law Office and Legal Services, Wappingers Falls, New York

Appeal from a judgment of the United States District Court for the Southern

District of New York (Briccetti, J.).

Upon due consideration, it is hereby ORDERED, ADJUDGED, and

DECREED that the judgment of the district court is AFFIRMED.

Defendant-Counter-Claimant-Appellant The Permanent Mission of Chad to

the United Nations in New York (the “Mission”) appeals from the judgment

entered on August 7, 2019, following a five-day bench trial, awarding Plaintiff-

Counter-Defendant-Appellee Hilt Construction & Management Corporation

(“Hilt”) damages in the amount of $100,335.62 (including prejudgment interest)

for breach of contract and denying the Mission’s counterclaim against Hilt for

breach of the same contract. On appeal, the Mission argues that the district court

erred in concluding that Hilt was entitled to the equitable adjustment of contract

time and price under the express terms of the contract between the parties and by

relying on an unreliable exhibit to calculate damages. We disagree and affirm the

2 decision of the district court. We assume the parties’ familiarity with the

underlying facts, the procedural history of the case, and the issues on appeal.

I

On August 12, 2016, Hilt, a resident of New Jersey, filed a complaint against

the Mission alleging state law claims of breach of contract, quantum meruit, and

account stated. Hilt alleged that it had entered into a contract with the Mission to

provide construction materials and services at a property in Westchester owned

by the Mission that would eventually serve as the Ambassador’s residence (the

“Contract”). Hilt further alleged that it provided $3,862,368 worth of services of

which $1,400,460 remained due and unpaid. The Mission asserted a counterclaim

for breach of contract against Hilt for failure to complete the project in the

timeframe purportedly agreed upon by the parties. The Mission sought damages

in the amount of $360,000 for rent that it had to pay for housing and office space

due to delays in the project’s completion and $1,000,000 for the new contractor that

it ultimately hired to complete the project.

From June 17 to June 21, 2019, the district court conducted a bench trial. On

July 22, 2019, the district court stated on the record its findings of fact and

conclusions of law. First, the court held that Hilt was entitled to damages in the

3 amount of $75,000 on its breach of contract claim. Second, the court held that Hilt

was entitled to judgment on the Mission’s breach of contract counterclaim because

§ 10.3 and § 11.2 of the Contract required an equitable adjustment of the contract

time and price for work done on four “concealed or unknown physical conditions”

which were unknown to the parties at the time the Contract was made and which

were discovered during the renovation. App’x 868. Third, the court held that the

Mission was entitled to judgment on Hilt’s quantum meruit and account stated

claims.

Because the district court determined that Hilt was entitled to an equitable

adjustment of the contract price for the four concealed or unknown physical

conditions, it calculated the cost of that additional work, including overhead costs,

to be $284,625. The court adjusted the award upward by an additional $2,275 for

certain costs that were not precisely reflected in the evidence at trial, and it

deducted $211,900 for work for which the Mission had paid but that Hilt did not

complete. The court therefore determined that Hilt is entitled to $75,000 in

damages. The court also awarded Hilt prejudgment interest in the amount of

$25,335.62.

4 The Mission timely appealed. 1

II

On appeal, the Mission disputes the district court’s grant of judgment

against the Mission and in Hilt’s favor on the parties’ competing breach of contract

claims. The Mission’s arguments are unavailing.

“When reviewing a district court’s judgment following a bench trial, we

review the court’s findings of fact for clear error and its conclusions of law de novo.”

Church & Dwight Co., Inc. v. SPD Swiss Precision Diagnostics, GmbH, 843 F.3d 48, 62

(2d Cir. 2016). In order to recover for breach of contract under New York law, 2 “a

plaintiff must prove, by a preponderance of the evidence, (1) the existence of a

contract between itself and that defendant; (2) performance of the plaintiff’s

obligations under the contract; (3) breach of the contract by that defendant; and

(4) damages to the plaintiff caused by that defendant’s breach.” Diesel Props S.R.L.

v. Greystone Bus. Credit II LLC, 631 F.3d 42, 52 (2d Cir. 2011). “In reviewing a written

contract, a trial court’s primary objective is to give effect to the intent of the parties

1 Hilt attempted to respond to the Mission’s appeal and to cross-appeal the district court’s judgment, but it failed to properly file any brief in either matter. 2 It is undisputed that New York law governs the Contract.

5 as revealed by the language they chose to use.” Seiden Assocs. v. ANC Holdings, Inc.,

959 F.2d 425, 428 (2d Cir. 1992). Indeed, “[t]he best evidence of what parties to a

written agreement intend is what they say in their writing.” Greenfield v. Philles

Records, 98 N.Y.2d 562, 569 (2002). When a written agreement “is complete, clear

and unambiguous on its face,” it “must be enforced according to the plain meaning

of its terms.” Id.

First, the Mission argues that equitable adjustment should not apply to

extend the contract time or to increase the contract price because, as a factual

matter, “[i]t was not the unknown conditions that caused the delay in completion

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Hilt Constr. & Mgmt. Corp. v. Permanent Mission of Chad, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hilt-constr-mgmt-corp-v-permanent-mission-of-chad-ca2-2021.