Hilsenroth v. Kessler

16 Fla. Supp. 2d 76
CourtCircuit Court for the Judicial Circuits of Florida
DecidedJanuary 9, 1985
DocketCase Nos. 75-39659 CA 12 and 79-6349 CA 12 (Consolidated)
StatusPublished

This text of 16 Fla. Supp. 2d 76 (Hilsenroth v. Kessler) is published on Counsel Stack Legal Research, covering Circuit Court for the Judicial Circuits of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hilsenroth v. Kessler, 16 Fla. Supp. 2d 76 (Fla. Super. Ct. 1985).

Opinion

OPINION OF THE COURT

CHARLES D. EDELSTEIN, Acting Circuit Judge.

THE FACTS

In 1972 sellers (Kessler et. al) purchased a tract of undeveloped land in North Miami Beach for approximately $500,000. They acquired the property subject to a first mortgage after making a minimal down [77]*77payment. In 1973 sellers sold the property to the buyer (Hilsenroth) for $1 million. Buyer assumed the first mortgage, gave the seller a $200,000 down payment and executed a note and mortgage for the difference. Buyer demanded a clause forgiving interest and deferring principal payments during the duration of any moratorium which prevented construction on the property. Buyer’s expressed intention was to build multi-family units on the property.

After the closing, he spent approximately $11,000 toward development, stopping three months later when he discovered a sewer moratorium on the property. The buyer sued successfully to enforce the interest waiver and principal deferment clause. He then unsucessfully sought recession. The court there held he had elected his remedy by his earlier suit and left him to sue for damages.

Buyer later sued for damages, meanwhile the moratorium was lifted and seller sought foreclosure. These two actions have been consolidated. During this period buyer claimed he expended over $400,00 to pay real estate taxes, interest and principal on the first mortgage, legal fees and the like. He sought damages and pre-judgment interest on the benefit of the bargain theory and also sought damages and pre-judgment interest on the out-of-pocket theory. Moreover, he demanded his damages be paid in current dollars as opposed to 1973 dollars.

Prior to the trial, the Judge then sitting considered the seller’s statute of limitations defense to the buyer’s complaint for damages and subsequently heard testimony relating to damages. He did so sitting without a jury. By stipulation, the undersigned heard testimony on liability, read the transcripts from the hearing on damages, and rendered a decision. The court found sellers had breached the warranty and that seller (Kessler) committed fraud by failing to disclose his knowledge of the moratorium.

The buyer did not seek loss of profits since had there been no moratorium and had the units been constructed, they would have hit the market during the 1974-75 recession. In fact, there might have even been a loss.

The trial court awarded punitive damages for the fraud and compensatory damages representing Buyer’s out-of-pocket expenses incurred from the date of closing till the discovery of the moratorium. The trial court stated:

. . HILSENROTH’S compensatory damages upon both the breach of contractual warranty and the fraud and deceit causes of action is limited to his out-of-pocket expenses incurred in reliance upon the development of the property from the time of the closing [78]*78on June 27, 1973, until the filing of the suit for declaratory relief to enforce the moratorium on payment of principal and interest under the purchase money mortgage in October, 1973.
Such damages include neither the “out-of-pocket” or “benefit of the bargain” theories of recovery sought by HILSENROTH, as he ratified the purchase by filing the declaratory relief suit in October, 1973.
... In effect, HILSENROTH seeks to make defendants guarantors of a successful outcome. If the moratorium were lifted early he might have been able to develop the property as planned and reap anticipated profits. If the moratorium remained longer than expected, then under his theory of damages he could recoup his expected profits from the defendants. . .”

An appeal ensued. The appellate court affirmed the finding of fraud and breach of warranty. It reversed the punitive damages awarded as time barred. On compensatory damages the Court held:

“Accordingly, we must remand to the trial court for a determination of the amount of reduction which the purchaser is entitled to because of the seller’s fraud. In doing so, we direct that the trial court should allow a setoff for out-of-pocket expenses or damages for loss of the benefit of the bargain. See DuPuis v. 79th St. Hotel, Inc., 231 So.2d 532 (Fla. 3d DCA 1970), cert. denied, 238 So.2d 105 (Fla. 1970).”

As to the buyer’s duty to mitigate, the Court stated:

“We reject the seller’s contention that Hilsenroth’s failure to mitigate damages by building his own sewage plant precluded damages based on these theories. Were we to require that such action be taken by the purchaser, we would be rewriting the parties’ contract which contemplated a governmental sewage plant. See Richard v. A. Waldman & Sons, Inc., 323 A.2d 307 (Conn. 1967) (parties are not required to give up a substantial right of their own to minimize the loss).”

On motion for clarifications, the District Court of Appeal added a footnote:

“The fact that Hilsenroth was not required to mitigate his damages by building his own sewage plant does not relieve him of the duty to keep his damages as low as reasonably possible. See Richard v. A. Waldman & Sons, Inc., at 310-311. Accordingly, except as noted, the trial court is free to apply the doctrine of mitigation of damages, if applicable.”

[79]*79On remand the parties agreed to submit the issue of damages to the undersigned solely upon the testimony presented to the Judge who heard that testimony. Since the undersigned is in no better position to judge the credibility of those witnesses than the appellate court, the normal presumption of correctness attaching to a trial court’s findings of fact disappears. In effect the hearing on appeal will be de novo.

THE LAW

In awarding damages the court should award a sum as will compensate the injured party for the loss sustained with the least burden to the wrongdoer consistent with the idea of fair compensation. See e.g. 25 CJS Damages § 71.

In DuPuis v. The 79th Street Hotel, Inc., 231 So.2d 532 (Fla. 3d DCA 1970) (noted with approval in the District Court’s opinion in the case at bar at 446 So. 2d 147) the Court adopted the language of 34 Am. Jur. Fraud & Deceit § 352, thereby settling for Florida what has been a topic of much dispute among the cases. See Annot. 13 ALR 3d 881 Damages-Fraudulent Representation.

“It would appear that the Florida courts have adopted and followed both rules [benefit of the bargain & out-of-pocket] in order to do such justice as the circumstances may demand.
This is in accordance with the flexibility theory set forth in 37 Am. Jur. 2d Fraud and Deceit, § 352. This formula is stated as follows:
“ . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fox v. Wilson
507 P.2d 252 (Supreme Court of Kansas, 1973)
Vise v. Foster
247 S.W.2d 274 (Court of Appeals of Texas, 1952)
Conner v. Atlas Aircraft Corporation
310 So. 2d 352 (District Court of Appeal of Florida, 1975)
Dupuis v. 79th Street Hotel, Inc.
231 So. 2d 532 (District Court of Appeal of Florida, 1970)
Hilsenroth v. Kessler
446 So. 2d 147 (District Court of Appeal of Florida, 1984)
525 Main Street Corp. v. Eagle Roofing Co.
168 A.2d 33 (Supreme Court of New Jersey, 1961)
Selman v. Shirley
91 P.2d 312 (Oregon Supreme Court, 1938)
Hargrove v. Frommeyer & Co.
323 A.2d 300 (Superior Court of Pennsylvania, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
16 Fla. Supp. 2d 76, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hilsenroth-v-kessler-flacirct-1985.