HILL v. UNITED STATES ARMY CORPS OF ENGINEERS

CourtDistrict Court, M.D. Pennsylvania
DecidedMarch 3, 2022
Docket1:17-cv-00508
StatusUnknown

This text of HILL v. UNITED STATES ARMY CORPS OF ENGINEERS (HILL v. UNITED STATES ARMY CORPS OF ENGINEERS) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HILL v. UNITED STATES ARMY CORPS OF ENGINEERS, (M.D. Pa. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF PENNSYLVANIA TAMARA E. HILL : Civil No. 1:17-CV-508 : v. : : UNITED STATES OF AMERICA, et : al. : Judge Sylvia H. Rambo M E M O R A N D U M Before the court is Defendant Westinghouse Electric Corporation’s motion for summary judgment. (Doc. 74.) For the reasons set forth below, the motion will be granted. I. BACKGROUND This wrongful death action arises from claims by Plaintiff Tamara Hill that Defendant Westinghouse defectively designed a 1500 kVA transformer that was in

operation at a military installation in Franklin County, Pennsylvania from 1984 until approximately 2015. (See Doc. 16.) The amended complaint alleges that in September 2015, Plaintiff’s husband, Michael S. Hill, was injured and later died from his injuries following an arc flash electrical incident that occurred while he was

working near the transformer. (See id. ¶¶ 27–34.) The transformer at issue was built by Westinghouse in 1983–1984 as the central component of an interconnected array, or “line-up,” of Westinghouse

electrical equipment for the U.S. Department of the Army’s Raven Rock Mountain Complex, known as “Site R”, in Fairfield, Pennsylvania. (Doc. 76 ¶¶ 16–17, 21, 44; Doc. 79 ¶ 78.) In addition to the transformer, the line-up of Westinghouse equipment

included a high-voltage switch, current-carrying metal bus duct, and low voltage switchgear with circuit breakers, which were provided to the USA as part of its

design of a secure underground electrical substation located in its 7th Signal Corps Computer facility. (Doc. 76 ¶¶ 16, 19). The USA sought to ensure a secure and continuous “uninterrupted power supply” (“UPS”) to Site R with a redundant “double-ended” configuration of equipment in the underground substation known as the “UPS Substation.” (Id. ¶¶ 18, 19.) It thus ordered from Westinghouse two line-

ups for the UPS Substation, which included identical or essentially identical transformers, high voltage switch, low voltage switchgear, and bus ducts. (Id. ¶ 19). The double-ended substation design allowed one line-up to continue delivering

power to Site R when the other was shut down for any reason, thereby avoiding a power loss that might jeopardize Site R’s operations. Under normal conditions, however, both line-ups remained in operation together. (Id. ¶ 20; Doc. 77-2 ¶ 78.) In 1984, the transformer was shipped to Site R, where it was installed by a

contractor in the UPS Substation. (Id. ¶ 21.) Upon installation, the transformer sat on a concrete pad that was ten feet long and six inches thick, without bolts or anything else securing it to the ground or pad. (See id. ¶ 28; Doc. 77-3 p. 108.) The

transformer remained in operation, in its original location, until shortly after the September 2015 accident, when it was removed along with its sister transformer. (See id. ¶¶ 48, 57, 58; Doc. 77-2 ¶¶ 76, 79; Doc. 79 ¶¶ 76, 79.)

Westinghouse has filed a motion for summary judgment, which argues that it is entitled to dismissal under Pennsylvania’s statute of repose. (Doc. 74.) The motion has been fully briefed and is ripe for disposition.

II. STANDARD OF REVIEW Rule 56(a) of the Federal Rules of Civil Procedure directs that the court “shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to summary judgment as a matter of

law.” See Celotex Corp. v. Catrett, 477 U.S. 317, 322-23 (1986). A factual dispute is “material” if it might affect the outcome of the suit under the applicable substantive law and is “genuine” only if there is a sufficient evidentiary basis for a

reasonable factfinder to return a verdict for the non-moving party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). When evaluating a motion for summary judgment, a court “must view the facts in the light most favorable to the non-moving party” and draw all reasonable inferences in favor of the same. Hugh v.

Butler Cnty. Family YMCA, 418 F.3d 265, 267 (3d Cir. 2005). The moving party bears the initial burden of demonstrating the absence of a disputed issue of material fact. See Celotex, 477 U.S. at 324. “Once the moving party

points to evidence demonstrating no issue of material fact exists, the non-moving party has the duty to set forth specific facts showing that a genuine issue of material fact exists and that a reasonable factfinder could rule in its favor.” Azur v. Chase

Bank, USA, Nat’l Ass’n, 601 F.3d 212, 216 (3d Cir. 2010). The non-moving party may not simply sit back and rest on the allegations in its complaint; instead, it must “go beyond the pleadings and by [its] own affidavits, or by the depositions, answers

to interrogatories, and admissions on file, designate specific facts showing that there is a genuine issue for trial.” Celotex, 477 U.S. at 324 (internal quotation marks omitted); see also Saldana v. Kmart Corp., 260 F.3d 228, 232 (3d Cir. 2001). Summary judgment should be granted where a party “fails to make a showing

sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden at trial.” Celotex, 477 U.S. at 322–23. “Such affirmative evidence—regardless of whether it is direct or circumstantial—must

amount to more than a scintilla, but may amount to less (in the evaluation of the court) than a preponderance.” Saldana, 260 F.3d at 232 (quoting Williams v. Borough of West Chester, 891 F.2d 458, 460–61 (3d Cir. 1989)). III. DISCUSSION

Westinghouse’s motion argues that it is entitled to summary judgment because Plaintiff’s claims are barred by Pennsylvania’s statute of repose. Under the statute of repose, any civil action brought against a person performing or furnishing

the design, planning, supervision, or observation of construction, or construction of any improvement to real property, “must be commenced within 12 years of completion of construction of such improvement,” in order to recover damages for

deficiency in the design or construction of the improvement, or for injury “to the person or for wrongful death arising out of any such deficiency.” 42 Pa.C.S.A. § 5536(a)(1), (a)(3). The party seeking protection under the statute of repose must

demonstrate: “(1) what is supplied is an improvement to real property; (2) more than twelve years have elapsed between the completion of the improvements to the real estate and the injury; and (3) the activity of the moving party must be within the class which is protected by the statute.” Noll by Noll v. Harrisburg Area YMCA, 537

Pa. 274, 280 (Pa. 1994) (citations omitted). Here, Westinghouse satisfies the first factor for the statute of repose because its motion demonstrates that the transformer supplied to Site R was an improvement

to real property. An improvement to real property is a valuable addition that is “more than mere repairs or replacement” and is “intended to enhance its value, beauty or utility or to adapt it for new or further purposes . . .” McCormick v. Columbus Conveyer Co., 522 Pa. 520, 524 (1989) (citation omitted); see Noll, 537 Pa. at 286–

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Azur v. Chase Bank, USA, National Ass'n
601 F.3d 212 (Third Circuit, 2010)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Cherie Hugh v. Butler County Family Ymca
418 F.3d 265 (Third Circuit, 2005)
Schmoyer v. Mexico Forge, Inc.
621 A.2d 692 (Superior Court of Pennsylvania, 1993)
McCormick v. Columbus Conveyer Co.
564 A.2d 907 (Supreme Court of Pennsylvania, 1989)
Schmoyer by Schmoyer v. Mexico Forge
645 A.2d 811 (Supreme Court of Pennsylvania, 1994)
Beaver v. DANSK INDUSTRI SYNDICAT A/S (DISA)
838 F. Supp. 206 (E.D. Pennsylvania, 1993)
Noll by Noll v. Harrisburg Area YMCA
643 A.2d 81 (Supreme Court of Pennsylvania, 1994)
Rabatin v. Allied Glove Corp.
24 A.3d 388 (Superior Court of Pennsylvania, 2011)
Williams v. Borough of West Chester
891 F.2d 458 (Third Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
HILL v. UNITED STATES ARMY CORPS OF ENGINEERS, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hill-v-united-states-army-corps-of-engineers-pamd-2022.