Hill Brothers Construction Company, Inc. v. Mississippi Transportation Commission

Mississippi Supreme Court·Decided December 12, 2008·No. 2009-CA-00053-SCT·Published

Opinion

IN THE SUPREME COURT OF MISSISSIPPI NO. 2009-CA-00053-SCT

HILL BROTHERS CONSTRUCTION COMPANY, INC.

v. MISSISSIPPI TRANSPORTATION COMMISSION

DATE OF JUDGMENT: 12/12/2008 TRIAL JUDGE: HON. WILLIAM F. COLEMAN COURT FROM WHICH APPEALED: HINDS COUNTY CIRCUIT COURT ATTORNEYS FOR APPELLANT: WILLIAM R. PURDY RALPH B. GERMANY, JR.

JUSTIN JOHN PETERSON

ATTORNEYS FOR APPELLEE: ALAN M. PURDIE BETTY RUTH FOX

JAMES T. METZ

MICHAEL EDWIN D’ANTONIO, JR.

DION JEFFERY SHANLEY

NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: REVERSED AND REMANDED - 06/17/2010 MOTION FOR REHEARING FILED: MANDATE ISSUED:

BEFORE CARLSON, P.J., DICKINSON AND PIERCE, JJ.

DICKINSON, JUSTICE, FOR THE COURT:

¶1. This is a dispute over a cost-adjustment provision of a highway construction contract between Hill Brothers Construction Company and the Mississippi Transportation Commission. While we agree with the Commission’s interpretation of the provision at issue, we find that it violates the mandate and scope of its enabling statute. We therefore reverse

the trial court’s grant of summary judgment in favor of the Commission, and remand for proceedings consistent with this opinion.1 FACTS AND PROCEDURAL HISTORY

¶2. The Commission awarded D. B. Johnson Construction Company, Inc. (“Johnson”) a contract for construction of approximately 6.25 miles of highway. After Johnson defaulted, the Commission called upon Johnson’s bonding company, Traveler’s Casualty and Surety Company of America (“Travelers”), to complete the contract.

¶3. Travelers and Hill Brothers Construction Company, Inc. (“Hill Brothers.”) entered into a completion agreement that incorporated all the contract documents and special provisions contained in the contract between Johnson and the Commission. Special Provision #907-109-01 entitled “Measurement & Payment for Changes in Costs of Construction Materials (Fuel and Asphalt),” hereinafter referred to as the “FAC,” required certain monthly cost-adjustments for the purposes of reimbursing Hill Brothers for diesel fuel and asphalt used in the project.

¶4. The provision established a fuel base price to be used during the bidding process so that all contractors bidding on the project would have a level playing field with regard to pricing fuel costs into their bids. Actual reimbursements during the contract period would be determined by comparing the base price to a cost index published monthly by the Mississippi Department of Transportation and, where the difference exceeded five percent,

1 The dissent’s concern about our remand is misplaced. We remand because we are reversing summary judgment, and this matter must now proceed to trial.

reimbursement rates would be adjusted accordingly. With respect to adjustments in reimbursement rates after the contract period, the last sentence of the FAC provided:

After the expiration of contract time, including all extensions, adjustments will be computed using fuel and material prices that are in effect at the expiration of the contract time.2

¶5. At the time of the completion agreement, Hill Brothers estimated that the work defaulted upon and left unperformed on the Johnson contract would take more than two years to finish, even though less than a month of allowable contract time remained. The Commission extended the contract to March 13, 2004. Hill Brothers completed the contract on March 13, 2006, two years past the expiration of the contract time.

¶6. Prior to the expiration of the contract time, the Commission, through its subordinate and operating entity, the Mississippi Department of Transportation (MDOT), calculated monthly payments for designated pay items affected by oil prices by adjusting the baseline price of petroleum products (established when the contract was originally awarded). The amount of adjustment was controlled by then-current prices as reflected in the index published monthly by MDOT.

¶7. When the contract time expired on March 13, 2004, and the work was not completed. the Commission began to make monthly adjustment payments based on the contract provision recited above. Because prices did not vary to any great extent for a period of time,

2 Hill Brothers had been a party to nine previous contracts with the Commission in which the same clause was included. However, Hill Brothers asserts that it has experienced inconsistent interpretations and applications of this provision, varying “from one MDOT District to another, within the same MDOT District at different times, and even with regard to the same MDOT contract.” Hill Brothers argues that it never challenged this because, in the past, the price differential had been insignificant.

this change in the method of determining adjustments had little effect on Hill Brothers’ total reimbursements. However, in August 2005, Hurricane Katrina struck the Mississippi Gulf Coast, causing the price of petroleum products to skyrocket.3 Because the Commission interpreted the contract provision to mean that all reimbursements would be determined using prices in effect at the end of the contract period, Hill Brothers received reimbursements which were far less than amounts actually expended for petroleum products. According to Hill Brothers, the Commission’s interpretation cost them nearly $500,000 in unreimbursed petroleum costs. Travelers and Hill Brothers both protested the application of this provision to no avail.

¶8. Hill Brothers filed suit against the Commission, asserting the Commission breached its contract by improperly applying the FAC and underpaying Hill Brothers. Hill Brothers contended that the proper interpretation of the FAC was for the Commission to replace the bidding baseline in the contract with the actual price of petroleum products at the end of the contract period, and then make monthly adjustments.

¶9. On September 4, 2008, the Commission moved for summary judgment, arguing that the FAC was unambiguous and that Hill Brothers was not entitled to any damages for the alleged underpayment relating to the FAC. Hill Brothers moved for partial summary judgment, arguing that its interpretation of the FAC was correct or, in the alternative, that the provision was ambiguous and should be construed against the Commission. The

3 The dissent incorrectly assumes that the contract provision at issue would always work to the detriment of the contractor. To the contrary, if at the end of the contract period fuel prices were lower than at the beginning, the Commission would be required to pay Hill Brothers more for each gallon of fuel than Hill Brothers actually spent. This would result in a windfall for Hill Brothers.

Commission then filed a motion for complete summary judgment, arguing the FAC was not ambiguous.

¶10. In a September 26, 2008, order, the trial court found that the FAC contract provision was unambiguous as interpreted by the Commission and denied Hill Brothers’ motion for partial summary judgment. On October 2, 2008, Hill Brothers filed its response to Commission’s motion for summary judgment along with its own cross-motion for summary judgment, arguing that the Commission’s interpretation of the provision was in conflict with and contrary to Section 31-7-13(i) of the Mississippi Code and therefore should be struck from the contract. Hill Brothers additionally argued that the provision – as the Commission sought to apply it – was unconscionable.

¶11. Following a hearing, the trial court found that the FAC as written, interpreted, and applied by the Commission was not ambiguous, contrary to the statute, or unconscionable. The court found there were no genuine issues of material fact and therefore, the Commission was entitled to summary judgment as a matter of law. From that ruling, Hill Brothers appeals, raising two issues: (1) whether the trial court properly interpreted the fuel adjustment provision; and (2) whether the commission’s interpretation violates the authorizing statute such that the limitation on adjustments provided for in the last sentence of the FAC should be struck.

ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

Hill Brothers Construction Company, Inc. v. Mississippi Transportation Commission, (Mich. 2008).

Hill Brothers Construction Company, Inc. v. Mississippi Transportation Commission (Hill Brothers Construction Company, Inc. v. Mississippi Transportation Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

MISSISSIPPI PSC v. Miss. Power & Light
593 So. 2d 997 (Mississippi Supreme Court, 1991)
Williams v. Puckett
624 So. 2d 496 (Mississippi Supreme Court, 1993)
Kuiper v. Tarnabine
20 So. 3d 658 (Mississippi Supreme Court, 2009)
Kerr-McGee Chemical Corp. v. Buelow
670 So. 2d 12 (Mississippi Supreme Court, 1995)
Gill v. Dept. of Wildlife Conservation
574 So. 2d 586 (Mississippi Supreme Court, 1990)
Farrish Gravel v. MISS. STATE HIGHWAY COM'N
458 So. 2d 1066 (Mississippi Supreme Court, 1984)