Highway Specialties, Inc. v. State, Department of Transportation

2009 MT 253, 215 P.3d 667, 351 Mont. 527, 2009 Mont. LEXIS 388
CourtMontana Supreme Court
DecidedAugust 3, 2009
DocketDA 08-0093
StatusPublished
Cited by5 cases

This text of 2009 MT 253 (Highway Specialties, Inc. v. State, Department of Transportation) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Highway Specialties, Inc. v. State, Department of Transportation, 2009 MT 253, 215 P.3d 667, 351 Mont. 527, 2009 Mont. LEXIS 388 (Mo. 2009).

Opinion

JUSTICE LEAPHART

delivered the Opinion of the Court.

¶1 Highway Specialties, Inc., (HS) appeals from the order of the First Judicial District Court, Lewis and Clark County, awarding summary judgment to the State of Montana, Department of Transportation, Maintenance Division (MDT) and enforcing a liquidated damages clause in a contract for a federally funded highway project. We affirm.

¶2 We restate the issue on appeal as follows:

¶3 Did the District Court err in awarding summary judgment to MDT and enforcing a liquidated damages clause in a contract for a federally funded highway project?

FACTUAL AND PROCEDURAL BACKGROUND

¶4 The following facts are undisputed. In April 2003, MDT issued an invitation for bids (IFB) for a federally funded highway re-striping project on 575 miles of highway in northeastern Montana. The project required the contractor to furnish surface preparation and apply epoxy pavement lines, words and symbols on U.S. Highway 2, Montana Highways 13 and 24 and various connector streets near Glasgow, Sydney, and Wolf Point, Montana. Because of safety concerns and reduced visibility in Montana’s winter months, MDT wanted the project completed before the 2003-2004 winter.

¶5 MDT awarded the contract to HS as the low bidder on the project. According to the terms of the written contract, HS agreed to complete the project for $370,134.79 and was required to complete the work on or before August 15, 2003. The completion date was capitalized and bolded in the contract. If HS failed to complete the work on or before August 15, 2003, the contract authorized MDT to assess liquidated damages for each workday the project went over schedule. The liquidated damages clause stated the following:

In the event the Contractor does not complete the work by the designated contract date or within the designated working days, liquidated damages will be assessed in the form of a daily charge for each day, except Saturdays, Sundays and legal holidays which exceed the designated contract date or working days. The daily charge will be determined from the schedule in Standard Specification Article 108.08 under fixed date. This charge will be *529 deducted from money due the Contractor.

At the time the parties entered into the agreement, MDT’s Standard Specification Article 108.08 (Article 108.08) set the daily charge rate at $387 for ‘fixed date” projects with a contractual sum of $100,000 to $500,000.

¶6 Despite its contractual agreement with MDT to complete the project on or before August 15, 2003, HS did not begin working on the project until at least October 27, 2003, over two months after the project was scheduled to be complete. On November 19, 2003, HS stopped working on the project altogether because of winter weather conditions. By this time, HS had striped less than 50 miles of the project’s total length. HS then asked MDT’s maintenance chief for a change in the completion date but MDT denied the request. Neither the IFB nor the contract authorized a work-stoppage because of inclement weather. HS resumed working on the project on March 29, 2004, and completed the project a month later.

¶7 After HS completed the project, MDT assessed HS $68,122 in liquidated damages for the 176 workdays the project went over schedule. The damages were assessed in accordance with MDT’s Article 108.08, which, as noted above, set the daily charge rate for the size of the project at $387 per working day. HS disputed the amount of liquidated damages assessed by MDT, claiming that the amount far exceed the actual cost to MDT. MDT denied Highway’s request for relief and the Montana Transportation Commission did not take action on the request.

¶8 HS commenced this action to recover the liquidated damages assessed by MDT. HS subsequently moved for summary judgment, claming the liquidated damages provision was unconscionable and unenforceable under this Court’s decision in Arrowhead School Dist. No. 75, Park Co., Montana v. Klyap, 2003 MT 294, 318 Mont. 103, 79 P.3d 250. MDT also moved for summary judgment. MDT argued that the liquidated damages clause-a clause which MDT was required to include pursuant to federal lawwvas not unconscionable under Arrowhead. The District Court granted MDT’s motion for summary judgment and enforced the total amount of liquidated damages assessed against HS. In reaching its decision, the District Court concluded that HS could not demonstrate that “the provisions of the contract were not within HS’ [sic] reasonable expectations or were unduly oppressive, unconscionable or against public policy,” in part because contractors may provide input on MDT’s contractual terms on an annual basis. The court also noted that federal law required MDT *530 to include the liquidated damages clause in the contract and that Montana law requires contractors to unconditionally accept public bids. HS appeals.

STANDARD OF REVIEW

¶9 We review a district court’s grant of summary judgment de novo, applying the same standard used by the district court under M. R. Civ. P. 56. Smith v. Burlington Northern & Santa Fe Ry., 2008 MT 225, ¶ 10, 344 Mont. 278, 187 P.3d 639. Summary judgment is appropriate when there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. M. R. Civ. P. 56.

¶10 Whether a stipulated damages provision in a contract is an enforceable liquidated damages provision or an unenforceable penalty is a question of law which we review for correctness. Arrowhead, ¶ 10.

DISCUSSION

¶11 Did the District Court err in awarding summary judgment to MDT and enforcing a liquidated damages clause in a contract for a federally funded highway project?

¶12 In Arrowhead we recognized a lack of clarity in Montana case law regarding pre-determined or liquidated damages provisions and thus, set forth a new test for determining whether such provisions are enforceable in this state. After Arrowhead, liquidated damages provisions are presumed enforceable and will be enforced unless the party opposing the provision has established that it is unconscionable “as indicated by the nature of the bargaining process between the parties ’’ Arrowhead, ¶¶ 48, 54. Unconscionability is a two-step inquiry: (1) whether the provision fits the doctrine of a contract of adhesion such that the weaker bargaining party had no meaningful choice regarding its acceptance; and (2) whether the contractual terms are unreasonably favorable to the drafter, usually the party with superior bargaining power. Arrowhead, ¶ 48. Under the second step, courts will inquire into whether the provision “is within the reasonable expectations of the weaker party or is unduly oppressive to the weaker party ’’ Arrowhead, ¶ 48. Since the test for unconscionability focuses on the nature of the bargaining process, we will only strike a liquidated damages clause ‘if the bargaining process itself had some inherent unfairness that actually prevented the contract from being freely negotiated ....” Arrowhead, ¶ 49.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lenz v. FSC Securities
2018 MT 67 (Montana Supreme Court, 2018)
Day v. CTA, Inc.
2014 MT 119 (Montana Supreme Court, 2014)
Kelker v. Geneva-Roth Ventures, Inc.
2013 MT 62 (Montana Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2009 MT 253, 215 P.3d 667, 351 Mont. 527, 2009 Mont. LEXIS 388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/highway-specialties-inc-v-state-department-of-transportation-mont-2009.