Hightower and Co., Inc. v. US Fidelity and Guaranty Co.

527 So. 2d 698, 1988 Ala. LEXIS 269, 1988 WL 67341
CourtSupreme Court of Alabama
DecidedMay 13, 1988
Docket86-1499
StatusPublished
Cited by52 cases

This text of 527 So. 2d 698 (Hightower and Co., Inc. v. US Fidelity and Guaranty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hightower and Co., Inc. v. US Fidelity and Guaranty Co., 527 So. 2d 698, 1988 Ala. LEXIS 269, 1988 WL 67341 (Ala. 1988).

Opinion

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 700

Hightower and Company, Inc. (Hightower), appeals from a summary judgment awarding United States Fidelity and Guaranty Company (USF G) $1,135,079.75, plus other relief, against Hightower for its failure to exonerate and indemnify USF G from obligations under payment and performance bonds issued by USF G.

Hightower contracted with the United States Government on March 18, 1985, to construct housing units at Maxwell Air Force Base. The contract, being in excess of $2,000, was subject to the "Miller Act," 40 U.S.C. § 270a et seq., which required Hightower to provide the Government with payment and performance bonds from an acceptable surety to secure proper performance of the contract and prompt payment to all suppliers and subcontractors. As Hightower's surety on the Maxwell project, USF G provided a performance bond of $3,887,900 and a payment bond of $1,555,160 in favor of the Government with Hightower as principal.

Hightower encountered difficulties on the project, and the Government issued "deficiency cure" notices on November 15, 1985, and January 6, 1986. Each notice stated that, unless the deficiency was cured within 10 days, the Government would be entitled to terminate the contract under its default clause. The Government issued a third deficiency notice on April 10, 1986, and requested that Hightower accelerate its work and submit a revised completion schedule. Hightower responded that it would be unable to complete the project within the time remaining, and the Government declared Hightower in default on May 13, 1986.

USF G demanded that Hightower place it "in funds" before any payments under the bonds were made to the Government and suppliers and subcontractors. Hightower replied that it considered the termination unjustified and would treat payments by USF G pursuant to the bonds as not made in good faith. In response to USF G's request, however, Hightower either acknowledged the amounts due subcontractors and suppliers or asserted that the amounts were not presently payable because Hightower had not received progress payments from the *Page 701 Government after termination of the contract.

USF G entered into payment agreements with the subcontractors and suppliers on the project, but declined to become contractor of record. The Government awarded a new contract after it had inventoried stored materials and prepared a bid solicitation. Based on additional engineering costs, amounts payable under the new contract, remedial work, and costs incurred by the Government, USF G settled with the Government for $865,071.46 under the performance bond and with suppliers and subcontractors for $264,750.99 under the payment bond.

USF G sued in July 1986, asking that Hightower be required to exonerate and indemnify USF G for amounts paid pursuant to the bonds. Hightower denied liability and counterclaimed against USF G for breach of duty of good faith, wanton breach of good faith, interference with contract, breach of contract, negligence, and wantonness. The court granted USF G a summary judgment as to its complaint and granted USF G a summary judgment as to Hightower's counterclaim (upon conversion of USF G's motion to dismiss into a summary judgment motion); Hightower appeals the denial of its motion to alter, amend, or vacate those summary judgments.

Three issues are presented: First, whether the trial court erred in converting USF G's motion to dismiss Hightower's counterclaim into a motion for summary judgment; second, whether Hightower's counterclaim presented genuine issues of material fact so as to defeat a motion for summary judgment; and third, whether as to USF G's complaint there were raised genuine issues of material fact so as to defeat a motion for summary judgment.

In reviewing a summary judgment, we must determine whether the evidence, when viewed in a light most favorable to the nonmoving party, will support any one of the nonmoving party's theories of liability, and thus defeat summary judgment.Tolbert v. Gulsby, 333 So.2d 129 (Ala. 1978). The granting of summary judgment is a nondiscretionary function of the trial court, and no presumption of correctness attaches to its decision upon appellate review. Tolbert, supra.

The first issue involves the procedure by which a Rule 12(b)(6), A.R.Civ.P., motion to dismiss is converted into a motion for summary judgment. At the hearing on USF G's motion for summary judgment on its complaint and its motion to dismiss Hightower's counterclaim, USF G requested that the court convert the motion to dismiss into a motion for summary judgment. Hightower objected to the conversion and stated that, with respect to the counterclaim, the only issue before the court was whether its counterclaim stated a legally cognizable claim. At the hearing, the trial court gave no indication of its intention to convert the motion to dismiss into a motion for summary judgment, but, 12 days later, granted summary judgment in favor of USF G on its complaint and on Hightower's counterclaim.

In pertinent part, Rule 12(b), A.R.Civ.P., states:

"If, on a motion asserting the defense numbered (6) to dismiss for failure of the pleading to state a claim upon which relief can be granted, matters outside the pleading are presented to and not excluded by the court, the motion shall be treated as one for summary judgment and disposed of as provided in Rule 56, and all parties shall be given reasonable opportunity to present all material made pertinent to such a motion by Rule 56." (Emphasis added.)

In pertinent part, Rule 56(c), A.R.Civ.P., states:

"Motion and Proceedings Thereon. The motion shall be served at least 10 days before the time fixed for the hearing. The adverse party prior to the day of hearing may serve opposing affidavits." (Emphasis added.)

In Hales v. First Nat. Bank of Mobile, 380 So.2d 797, 799 (Ala. 1980), this Court stated:

"It is clear from the above quoted portions of Rule 12 and 56 that: if a motion *Page 702 under Rule 12(b)(6) is converted into a motion for summary judgment, both parties shall be given a reasonable opportunity to submit affidavits and other extraneous proofs to avoid a party being taken by surprise through conversion of the motion to dismiss to one for summary judgment. [Citations omitted.] It is also clear that the spirit of Rule 56 requires the same notice and hearing where the court contemplates summary judgment on its own initiative as it does when a party moves for summary judgment; i.e., ten days' notice. [Citations omitted.]"

Hales cites with approval the following language from Davisv. Howard, 561 F.2d 565 (5th Cir. 1977):

" 'We do not hold that a notice to convert a 12(b)(6) motion into a summary judgment must be by written order, but the record must adequately demonstrate that all counsel were aware of the intentions of the district judge to treat the motion as converted, together with a reasonable opportunity afforded to the nonmoving party to present, by way of affidavit or otherwise, anything necessary to rebut the contention of the moving party. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin v. Hodges Chapel, LLC
89 So. 3d 756 (Court of Civil Appeals of Alabama, 2011)
Ex Parte Jefferson Cty. Dept. of Human Res.
63 So. 3d 621 (Supreme Court of Alabama, 2010)
A.W. ex rel. Hogeland v. Wood
57 So. 3d 751 (Supreme Court of Alabama, 2010)
Ashley's Seining v. Jmk Farms
9 So. 3d 491 (Court of Civil Appeals of Alabama, 2008)
Middleton v. Caterpillar Indus., Inc.
979 So. 2d 53 (Supreme Court of Alabama, 2007)
Lary v. Work-Loss Data Institute
911 So. 2d 18 (Court of Civil Appeals of Alabama, 2005)
Wal-Mart Stores, Inc. v. Hepp
882 So. 2d 329 (Supreme Court of Alabama, 2003)
Radenhausen v. Doss
819 So. 2d 616 (Supreme Court of Alabama, 2001)
Praus Ex Rel. Praus v. MacK
2001 ND 80 (North Dakota Supreme Court, 2001)
Stone Bldg. Co. v. Star Elec. Contractors, Inc.
796 So. 2d 1076 (Supreme Court of Alabama, 2000)
Wal-Mart Stores, Inc. v. Smitherman
743 So. 2d 442 (Supreme Court of Alabama, 1999)
New York Life Ins. Co. v. Robinson
735 So. 2d 463 (Supreme Court of Alabama, 1999)
Ex Parte CSX Transp., Inc.
735 So. 2d 476 (Supreme Court of Alabama, 1999)
Hornsby v. Sessions
703 So. 2d 932 (Supreme Court of Alabama, 1997)
Young v. La Quinta Inns, Inc.
682 So. 2d 402 (Supreme Court of Alabama, 1996)
Rhodes v. Tractor & Equipment Co.
677 So. 2d 194 (Supreme Court of Alabama, 1995)
Lipham v. General Motors Corp.
665 So. 2d 190 (Supreme Court of Alabama, 1995)
International Fidelity Ins. Co. v. Gilliam
659 So. 2d 24 (Supreme Court of Alabama, 1995)
Carruth v. Pittway Corp.
643 So. 2d 1340 (Supreme Court of Alabama, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
527 So. 2d 698, 1988 Ala. LEXIS 269, 1988 WL 67341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hightower-and-co-inc-v-us-fidelity-and-guaranty-co-ala-1988.