Highpoint Townhouses, Inc. v. Rapp

423 A.2d 932, 1980 D.C. App. LEXIS 413
CourtDistrict of Columbia Court of Appeals
DecidedDecember 3, 1980
Docket79-296
StatusPublished
Cited by13 cases

This text of 423 A.2d 932 (Highpoint Townhouses, Inc. v. Rapp) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Highpoint Townhouses, Inc. v. Rapp, 423 A.2d 932, 1980 D.C. App. LEXIS 413 (D.C. 1980).

Opinion

FERREN, Associate Judge:

Highpoint Townhouses, Inc. (Highpoint) appeals a trial court order enforcing a subcontractor’s mechanic’s lien against its property filed by Lee Rapp, Sr., trading as Rapp Contracting Company (Rapp Co.). See D.C.Code 1973, § 38-101. Highpoint argues that Rapp Co. has no right to a mechanic’s lien because its underlying claim is based on an illegal contract with the general contractor authorizing Rapp Co. to provide plumbing services without the required master plumber’s license. 1 We agree; thus, we reverse.

I.

On or about September 20, 1977, Rapp Co. contracted with Columbia Construction and Development, Inc. (Columbia) to do certain construction work on Highpoint’s property, where Columbia, as general contractor, was building townhouses. The contract called for Rapp Co. to install a “water system,” specifying the size and amounts of piping to be installed. Following completion of the work, Rapp Co. sent Highpoint notice of a mechanic’s lien it had filed on the property.

At trial in a suit to enforce the lien, Lee Rapp, Jr. (Rapp), vice-president and superintendent/foreman of Rapp Co., testified about the work performed under the contract, explaining that his company was to “install the sanitary sewer mains and the water mains.” Moreover, according to Rapp, “[t]o the best of my knowledge . .. [w]e ran individual sewer and water services to each unit.” Rapp’s testimony, as well as Rapp Co.’s timesheets, confirmed that the work included excavation, laying pipe, and tying the system into the District mains. Specifically, Rapp stated that his company “did the whole on-site system before we did the tie-in,” and that “[t]he actual water tie-in was performed by us.”

Rapp admitted that neither Rapp Co. nor its employees had a master plumber’s license: “we are not master plumbers, we are utility contractors ± ± ± ±" Rapp Co. and Columbia were conscious of this fact when they entered into the contract; because only a master plumber can obtain a permit to tap into the District mains, their contract specifically excluded the costs for a master plumber to “pull a permit.” Columbia, therefore, contracted with James A. Federline, a master plumber, to obtain the permit. According to Rapp, however, “we [did the installation] under their permit” and had no contact with Federline.

The following colloquy between appellants’ counsel and Rapp on cross-examination provides the clearest description of Rapp Co.’s relationship with the master plumber:

[RAPP]: It is an accepted practice for a plumber to pull the permit, and let us do the work, because the sanitary sewer was deep, they are not set up to do underground excavation the same way a utility contractor is.
[HIGHPOINT’S COUNSEL]: So, in this case, you required the acquiescence or authority of a master plumber to complete the job?
[RAPP]: The job required one; yes.
*934 [HIGHPOINT’S COUNSEL]: Were you required by the master plumber to put up a bond covering your work?
[RAPP]: We were not. I had no contact with the master plumber at all on the job, with regards to that permit. [HIGHPOINT’S COUNSEL]: Well, excuse me, Mr. Rapp, I don’t want to get into this too deeply, but you’re saying you acted under his authority, but you had no contact?
[RAPP]: I figured you’d take that. Now, look, what I am saying is this: We had nothing to do with the permit. Columbia knew that there had to be a permit drawn. Where they drew it from was not up to me. I merely did the installation work, and it so happened on this particular case, I believe that Feder-line [a master plumber] pulled the permit and it stopped at that. Federline had no contact with me. I had none with them.

II.

Under D.C. Code 1973, § 2-1406, it is “unlawful for any person to engage in the work of plumbing or gas-fitting in the District of Columbia unless he is licensed . . . or is an employee of a licensed master plumber.” According to D.C. Code 1978 Supp., § 2-1405, “[a]ny licensee may apply for and receive a license for or on behalf of any firm, copartnership, or corporation that he is a bona fide member of or a substantial stockholder in; but all plumbing ... done pursuant to such license shall be done under the immediate personal supervision of the licensed man.” The District of Columbia Plumbing Code, 5C DCRR §§ 101-817 (1972, with amendments through July 1979), defines “plumbing” to include the following functions:

all work done and materials used (1) in introducing, maintaining and extending a supply of water through a pipe or pipes, or any appurtenance thereof, in any building lot, premises, or establishment, whether from a public or private source of supply; (2) in connecting or repairing any system of drainage whereby foul waste or surplus water, gas, vapor, or other fluid is discharged or proposed to be discharged through a pipe or pipes from any building, lot, premises, or establishment into any public or house sewer, drain, pit, box, filter bed, or other receptacle, or into any natural or artificial watercourse flowing through public or private property; (3) in ventilating any house sewer, or any fixture or appurtenance connected therewith; (4) in excavating in any public, or private street, avenue, highway, road, court, alley, or space for the purpose of connecting any building, lot, premises, or establishment with any service pipe, house sewer, public water main, public sewer, gas main, subway, conduit, or other underground structure; and generally (5) in performing all classes of work usually done by plumbers and drain layers including the removal of plumbing fixtures, pipes, and fittings, except as otherwise provided for in these regulations. [5C-2 DCRR § 115-1.]

The work that Rapp Co. performed under its contract — excavating and laying pipe for the purpose of connecting Highpoint buildings to the public water main, and actually connecting each unit to the public main— was well within this definition of plumbing. As is clear from Rapp’s testimony, however, neither Rapp Co. nor any of its employees had a plumbing license. Nor was there any evidence that Federline or any other master plumber hired or supervised Rapp Co. The mere fact that Rapp Co. was working under a permit obtained by a master plumber does not, in itself, satisfy or excuse Rapp Co. from the licensing requirement; the issuance of a permit to Federline cannot mask the character of the work performed by Rapp Co.

Even were we to assume, solely for the sake of argument, that Rapp Co. would not violate the plumbing statute if its operations were “under the immediate personal supervision” of a master plumber, D.C. Code 1978 Supp., § 2-1405, 2 Rapp Co.’s lien could not be saved here, for it had no such *935 supervision. In La Covey v. District of Columbia, D.C.Mun.App., 107 A.2d 374

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HVAC Specialist, Inc. v. Dominion Mechanical Contractors, Inc.
201 A.3d 1205 (District of Columbia Court of Appeals, 2019)
Michael Francis and Queue, LLC v. Munir Rehman and HAK, LLC
110 A.3d 615 (District of Columbia Court of Appeals, 2015)
Ruiz v. New Garden Township
376 F.3d 203 (Third Circuit, 2004)
Remsen Partners, Ltd. v. Stephen A. Goldberg Co.
755 A.2d 412 (District of Columbia Court of Appeals, 2000)
Cevern, Inc. v. Ferbish
666 A.2d 17 (District of Columbia Court of Appeals, 1995)
Saul v. Rowan Heating & Air Conditioning, Inc.
623 A.2d 619 (District of Columbia Court of Appeals, 1993)
A-L Associates, Inc. v. James F. Jorden
963 F.2d 1529 (D.C. Circuit, 1992)
Capital Construction Co. v. Plaza West Cooperative Ass'n
604 A.2d 428 (District of Columbia Court of Appeals, 1992)
Jackson v. Holder
495 A.2d 746 (District of Columbia Court of Appeals, 1985)
Family Const. v. DC DEPT. OF C. & R. AFFAIRS
484 A.2d 250 (District of Columbia Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
423 A.2d 932, 1980 D.C. App. LEXIS 413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/highpoint-townhouses-inc-v-rapp-dc-1980.