Highland Mechanical Industries, Inc. v. Herbert Construction Co.

216 A.D.2d 161, 628 N.Y.S.2d 655, 1995 N.Y. App. Div. LEXIS 6619
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 22, 1995
StatusPublished
Cited by5 cases

This text of 216 A.D.2d 161 (Highland Mechanical Industries, Inc. v. Herbert Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Highland Mechanical Industries, Inc. v. Herbert Construction Co., 216 A.D.2d 161, 628 N.Y.S.2d 655, 1995 N.Y. App. Div. LEXIS 6619 (N.Y. Ct. App. 1995).

Opinion

Order, Supreme Court, New York County (Beatrice Shainswit, J.), entered June 6,1994, to the extent that it denied the motion to dismiss the complaint pursuant to CPLR 3211 (a) (1) and (5), unanimously affirmed, with costs.

Article XX of the contract between defendant contractor and plaintiff subcontractor provides, in part, that "[i]n no event shall Subcontractor be entitled to receive any form of payment [162]*162prior to the Contractor’s actual receipt of that payment. Subcontractor waives all right of action until said monies are received by the Contractor.” Since any ambiguity in a contract must be construed against the party who drafted it (BT Commercial Corp. v Blum, 175 AD2d 43,44), which, in this instance, was defendant, the only reasonable interpretation of this clause is that it is implicit that the contractual limitation period only begins to run upon notification of payment by the contractor to its subcontractor. Certainly, "a defendant may be estopped to plead the Statute of Limitations where plaintiff was induced by fraud, misrepresentations or deception to refrain from filing a timely action” (Simcuski v Saeli, 44 NY2d 442, 448-449).

Plaintiff’s president has submitted an affidavit in which he states that, from August of 1989 through the commencement of this litigation in February of 1993, he personally telephoned defendant and was repeatedly advised that defendant had not yet received final payment from the owner. While defendant disputes this claim, the documentary evidence in the record, rather than supporting defendant’s motion to dismiss on the ground of contractual limitations, as well as waiver and release, is, at times, directly contradictory to it. At the very least, there are disputed questions of fact here that require resolution in further proceedings. Concur—Ellerin, J. P., Wallach, Nardelli, Tom and Mazzarelli, JJ.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stonewall Contr. Corp. v. Long Is. Rail Rd. Co.
2020 NY Slip Op 4505 (Appellate Division of the Supreme Court of New York, 2020)
Bank of New York Mellon v. WMC Mortgage, LLC
2017 NY Slip Op 3881 (Appellate Division of the Supreme Court of New York, 2017)
Greene v. City of New York
196 Misc. 2d 125 (New York Supreme Court, 2003)
Fink v. Regent Hotel, Ltd.
234 A.D.2d 39 (Appellate Division of the Supreme Court of New York, 1996)
Rodgard Corp. v. Miner Enterprises, Inc.
914 F. Supp. 907 (W.D. New York, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
216 A.D.2d 161, 628 N.Y.S.2d 655, 1995 N.Y. App. Div. LEXIS 6619, Counsel Stack Legal Research, https://law.counselstack.com/opinion/highland-mechanical-industries-inc-v-herbert-construction-co-nyappdiv-1995.