Highland Crossing, Lp v. Ken Laster Co.
This text of 2010 OK CIV APP 124 (Highland Crossing, Lp v. Ken Laster Co.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
HIGHLAND CROSSING, L.P., an Oklahoma limited partnership, Plaintiff/Appellant,
v.
KEN LASTER COMPANY, an Oklahoma corporation, Defendant/Appellee,
v.
Royce Wright, General Partner of Highland Crossing, L.P., Third Party Defendant.
Court of Civil Appeals of Oklahoma, Division No. 3.
*568 Kenneth M. Smith, Riggs, Abney, Neal, Turpen Orbison & Lewis, Tulsa, OK, for Plaintiff/Appellant.
Joe M. Fears, Barber & Bartz, Tulsa, OK, for Defendant/Appellee.
BAY MITCHELL, Judge.
¶ 1 Highland Crossing, L.P., Plaintiff/Appellant ("Owner"), seeks review of an order confirming an arbitration award in favor of Defendant/Appellee Ken Laster Company ("Subcontractor").[1] The trial court denied *569 Owner's Petition to Vacate the arbitration award and granted Subcontractor's Cross-Application for Order Confirming Arbitration Award against Owner.
¶ 2 Owner was a developer of a construction project in Sand Springs, Oklahoma, which secured the services of Texas BBL, L.P. ("General Contractor"). In furtherance of this project, in August 2005, Owner entered into a written contract ("Contract") with General Contractor for the construction of multi-family apartments. This Contract contained an express agreement to arbitrate "any claim arising out of or related to the Contract." Subsequently, in furtherance of the apartment construction project, General Contractor entered into a subcontract agreement ("Subcontract") with Subcontractor in September 2005 whereby Subcontractor agreed to perform the dirt work, underground utilities and infrastructure work for a lump sum price of $825,384. The Subcontract expressly included an agreement to arbitrate "in the same manner and under the same procedure as provided in the Contract." The construction project was completed in the spring of 2007. During the course of construction, Subcontractor submitted claims to the General Contractor, some of which were denied. In 2007, Subcontractor commenced an arbitration proceeding against General Contractor seeking to recover over $200,000 it claimed remained due pursuant to the Subcontract. Later, Subcontractor filed a motion to join Owner in the arbitration to which Owner filed an objection on the basis that Owner had "no known contract with any of the parties" that would require Owner's participation in arbitration.[2] After Subcontractor filed a response to Owner's objection, the arbitrator held a hearing then ruled in Subcontractor's favor, ordering that Owner be joined as an additional party.
¶ 3 Arbitration hearings were held in December 2007 and January 2008. The arbitrator entered his award on April 28, 2008 (and modified on May 27) which determined that Subcontractor was entitled to judgment against Owner in the amount of $67,940.75 plus reasonable attorney fees of $50,000 and expenses in the amount of $11,000. Additionally, the arbitrator awarded Subcontractor $3,700 against General Contractor. Owner was also ordered to pay the administrative fees for the arbitration and the expenses and compensation of the arbitrator. Owner thereafter filed its Petition to Vacate the arbitration award in the district court based upon the lack of an agreement to arbitrate claims of the Subcontractor pursuant to 12 O.S. Supp.2008 § 1874(a)(5). Ultimately, the trial court confirmed the modified arbitration award and entered judgment against Owner in the amount of $67,940.75, with interest, together with arbitration attorney fees in the amount of $50,000 and arbitration expenses of $22,097.67. The trial court further found Subcontractor entitled to an award of reasonable attorney fees incurred in the trial court proceeding in accordance with 12 O.S. Supp. 2008 § 936 and costs pursuant to 12 O.S.2001 § 928.
¶ 4 The only issue on appeal is whether the Owner was subject to an agreement to arbitrate upon which the arbitration award could be based.[3] We hold that under the facts of this case, Owner was a party to an agreement to arbitrate the disputes arising from the Contract and Subcontract, and the trial court correctly confirmed the arbitration award.
*570 ¶ 5 The interpretation of an arbitration agreement is governed by state law principles of general contract interpretation. Wilkinson v. Dean Witter Reynolds, 1997 OK 20, 933 P.2d 878. The courts will read the provisions of a contract in their entirety, Mortgage Clearing Corp. v. Baughman Lumber Co., 1967 OK 232, ¶ 11, 435 P.2d 135, 138, to give effect to the intention of the parties as ascertained from the four corners of the contract, and where the language is ambiguous, it will be interpreted in a fair and reasonable sense. Id., at ¶ 13, 435 P.2d at 139.
¶ 6 Generally, the courts will enforce arbitration agreements according to the terms of the parties' contract, as arbitration "is a matter of consent, not coercion." Volt Info. Sciences, Inc. v. Bd. Of Trustees, 489 U.S. 468, 479, 109 S.Ct. 1248, 103 L.Ed.2d 488 (1989). To ensure that the parties have consented to arbitration, the courts will decide whether there is a valid enforceable arbitration agreement, whether the parties are bound by the arbitration agreement, and whether the parties agreed to submit a particular dispute to arbitration. Oklahoma Oncology & Hematology, P.C. v. U.S. Oncology, Inc., 2007 OK 12, ¶ 22, 160 P.3d 936, 944-45; See First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 115 S.Ct. 1920, 131 L.Ed.2d 985 (1995). There is a "strong presumption in favor of arbitration." Towe, Hester & Erwin, Inc. v. Kansas City Fire & Marine Ins. Co., 1997 OK CIV APP 58, ¶ 24, 947 P.2d 594, 599. "Ambiguities are resolved in favor of finding the dispute is arbitrable." Farrell v. Concept Builders, Inc., 2008 OK CIV APP 34, ¶ 7, 208 P.3d 483, 485; City of Muskogee v. Martin, 1990 OK 70, ¶ 8, 796 P.2d 337, 340 ("Arbitration should be allowed unless the court can say with `positive assurance' the dispute is not covered by the arbitration clause."). The question as to the existence of a valid, enforceable agreement to arbitrate is a question of law reviewed de novo. Oklahoma Oncology & Hematology, P.C., ¶ 19 at p. 944.
¶ 7 In Oklahoma, there are limited circumstances set forth by statute under which a party's motion to vacate an arbitration award may be granted. See 12 O.S. Supp.2008 § 1874(A). That statute provides in pertinent part as follows:
(A.) Upon an application and motion to the court by a party to an arbitration proceeding, the court shall vacate an award made in the arbitration proceeding if:...
(5.) There was no agreement to arbitrate, unless the person participated in the arbitration proceeding without raising the objection under subsection C of Section 16 of this act not later than the beginning of the arbitration hearing; ....
(Emphasis added). 12 O.S. § 1874(A)(5).
¶ 8 In this case, Owner argues it did not sign and was not a party to the Subcontract, and thus should not be required to arbitrate disputes arising from the Subcontract.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2010 OK CIV APP 124, 242 P.3d 567, 2010 Okla. Civ. App. LEXIS 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/highland-crossing-lp-v-ken-laster-co-oklacivapp-2010.