Highland Al Hujaz Co., Ltd.

CourtArmed Services Board of Contract Appeals
DecidedJuly 13, 2015
DocketASBCA No. 59746, 59818
StatusPublished

This text of Highland Al Hujaz Co., Ltd. (Highland Al Hujaz Co., Ltd.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Highland Al Hujaz Co., Ltd., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Highland Al Hujaz Co., Ltd. ) ASBCA Nos. 59746, 59818 ) Under Contract No. W917PM-09-C-0049 )

APPEARANCES FOR THE APPELLANT: Herman M. Braude, Esq. Edward D. Manchester, Esq. Braude Law Group, P.C. Washington, DC

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Daniel B. McConnell, Esq. Assistant Counsel U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE THRASHER ON APPELLANT'S MOTION FOR AN ORDER DIRECTING THE GOVERNMENT TO FILE THE COMPLAINT

This matter comes before the Board on appellant's motion for an order requiring the government to file the complaint in this appeal. The government opposes the motion. For the reasons that follow we grant the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. The government awarded Contract No. W9 l 7PM-09-C-0049 (contract) to Highland Al Hujaz Co., Ltd. (HLH), on 3 June 2009, for design and construction of the Afghanistan National Army Corps Support Battalion, Camp Hero, Kandahar, Afghanistan (R4, tab 11 ). • The government terminated the contract for default on 23 April 2012 (R4, tab 2). On 18 August 2012, the government issued an invitation for bids to reprocure the uncompleted portion of the contract and to correct defects in the work completed (R4, tab 903). Five bids were received and the government awarded the reprocurement contract on 24 September 2012 (ASBCA No. 58243, R4, tab 841).

• The Rule 4 file in ASBCA Nos. 59746 and 59818 is consolidated with the Rule 4 file in ASBCA No. 58243, the appeal on the associated default termination action giving rise to the demand for excess reprocurement costs. The work under the reprocurement contract was completed and accepted by the government on 31January2014 (R4, tab 904).

2. On 21 May 2014 the government issued HLH a demand letter to collect the excess reprocurement costs in completing the work which was deficient and/or left unfinished as of the date of termination for default of the contract. The demand letter asserted the government's right to assess excess reprocurement costs, that the reprocurement contract was competitively awarded, identified the reprocurement contractor and described how the asserted amount of excess reprocurement costs were calculated. (R4, tab 889) HLH responded on 23 May 2014 rejecting the government's right to excess reprocurement costs (R4, tab 901 ). In addition to the issue of the propriety of the underlying default termination being litigated in ASBCA No. 58243, HLH's response asserted a number of reasons why the government's demand for excess reprocurement costs was erroneous or questionable. Further, the letter asked the government to confirm the demand letter was not a contracting officer's final decision (COFD) (R4, tab 901).

3. Two years earlier, on 18 June 2012, the government issued HLH a demand letter for reimbursement of $903,553.79 in overpayments to HLH during performance of the contract (R4, tab 98). HLH responded disagreeing with the government's assessment and requested further information (R4, tab 900). There is no record of a request for a COFD, issuance of a COFD or an appeal to the Board on this issue.

4. The government issued HLH a second demand letter on 30 May 2014 that mirrored the 21May2014 demand letter but also addressed each issue raised by HLH in its response. However, the second demand letter did not address whether it was a COFD. (R4, tab 893) Again on 4 June 2014, HLH rejected the government's demands and repeated its arguments for the rejection of the assessment of excess costs (R4, tab 902). On 20 June 2014 HLH requested issuance of a COFD on the government's claim for excess reprocurement costs (R4, tab 921 at 2). Having not received a COFD by 21 October 2014, HLH asked the government to confirm when it would issue a COFD (R4, tab 922). No response or COFD was forthcoming so HLH filed a notice of appeal with the Board on 15 December 2014 which was docketed as ASBCA No. 59746. On 22 January 2015, the government issued a COFD repeating its demand for excess reprocurement costs. The COFD referenced the overpayment issue asserted on 18 June 2012 in a recitation of facts but did not appear to include the amount of overpayment within the excess reprocurement calculations or otherwise address entitlement to any amount for the overpayment issue in its decision. HLH appealed the COFD to the Board on 5 February 2015 which was docketed as ASBCA No. 59818. HLH' s notice of appeal only referenced excess reprocurement costs; there was no reference to the overpayment demand.

2 5. On 20 February 2015, HLH filed a motion to extend time for filing the complaint until 30 days after the government files the Rule 4 file. The motion was not opposed by the government and was granted by the Board on 11 March 2015. The Board received its copy of the Rule 4 file on 15 April 2015. On 23 April 2015, HLH filed a motion for order directing the government to file the complaint in this appeal. The government responded on 19 May 2015 opposing the motion asserting that both the excess reprocurement cost and overpayment issues were before the Board in the appeals, and HLH replied to the government's response on 2 June 2015.

DECISION

Under the unique procedural requirements of the Contract Disputes Act (CDA), all claims, whether contractor or government claims, must be the subject of a COFD. 41 U.S.C. § 7103. The contractor, however, is the only party who may initiate proceedings at the Board, 41 U.S.C. § 7104, and Board Rule 6(a) requires appellant to file the complaint in an appeal. If the contractor appeals from a final decision on a government claim, the contractor typically files a complaint with enough information about the government claim to form a sufficient predicate for the government's answer and allow for adequate framing of the issues. Therefore, the fact the appeal involves a government claim alone, is not enough to compel the government to file the complaint.

Nonetheless, we have recognized that there may be situations when the proceedings would be facilitated by the government filing the complaint or initial pleading. E.g., Kellogg Brown & Root Services, Inc., ASBCA No. 59557, 15-1 BCA ii 35,865; Beechcraft Defense Co., ASBCA No. 59173, 14-1BCAii35,592; RO. Vl.B. Sri, ASBCA No. 56198, 09-1BCAii34,068. Ifwe determine that the proceeding would not be facilitated, we do not order the government to file the initial pleading. See, e.g., General Dynamics Corp., ASBCA No. 49339, 96-1BCAii28,244 (contractor in possession of information upon which government claim is based).

While ordinarily we might look with disfavor on the instant motion when appellant has acknowledged its responsibility to file the complaint and requested an extension to do so (SOF ii 5), the fact that it is unclear whether the appeals concern excess reprocurement costs alone, or these costs plus an overpayment claim by the government, present a unique situation. As near as we can determine on the present record, the only issue before us is the government's affirmative claim for excess reprocurement costs. However, a substantial portion of the government's 19 May 2015 response addresses a government demand for collection of overpayments during performance of the contract. The government did assert a demand for overpayments during performance (SOF ii 3) but there is no record of a COFD or an appeal to the Board on this issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Highland Al Hujaz Co., Ltd., Counsel Stack Legal Research, https://law.counselstack.com/opinion/highland-al-hujaz-co-ltd-asbca-2015.