HIGH TECH RAIL AND FENCE, LLC v. CAMBRIDGE SWINERTON BUILDERS, INC. N/K/A SWINERTON BUILDERS, INC.
Opinion
THIRD DIVISION DOYLE, P. J., REESE and BROWN, JJ.
NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed.
https://www.gaappeals.us/rules
March 10, 2022
In the Court of Appeals of Georgia A21A1566. HIGH TECH RAIL AND FENCE, LLC v.
CAMBRIDGE SWINERTON BUILDERS, INC.
REESE, Judge.
In this contract dispute, High Tech Rail and Fence, LLC (“High Tech”) appeals
from the trial court’s grant of partial summary judgment in favor of Cambridge
Swinerton Builders, Inc., n/k/a Swinerton Builders, Inc. (“Cambridge Swinerton”).
On appeal, High Tech argues that the trial court erred in: (1) finding that Cambridge
Swinerton properly terminated High Tech in accordance with the subcontract
agreement; (2) finding that High Tech waived all other claims under the contract; and
(3) granting summary judgment on High Tech’s tortious interference claim. For the
reasons set forth infra, we affirm.
Viewed in the light most favorable to High Tech, as the nonmoving party
below,1 the record shows the following. In June 2016, Cambridge Swinerton, as a
general contractor, entered into a subcontract agreement with High Tech. The
agreement provided that High Tech would furnish and install aluminum railings for
the Centennial Park Project (the “Project”) in Atlanta. Article 14 of the agreement
provided the conditions in which Cambridge Swinerton could terminate High Tech
from the Project:
14. Termination. If, in the opinion of [Cambridge Swinerton], [High Tech] shall at any time (1) refuse or fail to provide sufficient properly skilled workers, adequate supervision, or materials of proper quality, (2) fail in any material respect to prosecute the work according to [Cambridge Swinerton’s] schedule, (3) cause in any way, the stoppage or delay or interference with the work of [Cambridge Swinerton] or any other contractor or subcontractor, (4) file bankruptcy, become insolvent, or generally be unable to pay its creditors, (5) fail to comply with any material provision of this Subcontract or the Contract Documents, then, [Cambridge Swinerton] may, forty-eight (48) hours after written notice to [High Tech], cure any such defect or default in [High Tech]’s performance and deduct the cost thereof from any money then due, or thereafter to become due, to [High Tech]. [Cambridge Swinerton] may also, at its option, terminate this Agreement, and [Cambridge Swinerton]
1 See Griffin v. State Bank, 312 Ga. App. 87 (718 SE2d 35) (2011).
shall have the further right to take possession of the materials and equipment of [High Tech] for the purpose of completing the work.
Article 14 further provided that, in the event of a termination under that article,
then High Tech was not entitled to receive payment until the work was fully
completed and accepted by Cambridge Swinerton and the Project owner. Cambridge
Swinerton would then pay High Tech the excess, if any, of the “unpaid balance” over
“the expenses incurred by [Cambridge Swinerton] as a result of the default, plus
reasonable charges for overhead and profit[.]” If the “expenses, overhead and profit
exceed the unpaid balance, [High Tech] shall pay [Cambridge Swinerton] the
difference upon demand.”
Article 14 also included a waiver provision:
[High Tech] hereby waives all claims against [Cambridge Swinerton] for lost profits, rent on equipment or other alleged damages related to any proceeding which [High Tech] might institute for wrongful back charges or wrongful termination under this Agreement. The parties agree that the termination and/or back charges shall be binding if [Cambridge Swinerton] has, in good faith, made a decision that [High Tech]’s performance is inadequate. The parties agree that such determinations are difficult to make, and must be made, under pressing circumstances and agree to be bound in accordance with this Article in light of the circumstance confronting [Cambridge Swinerton] at the time such a decision is made.
Finally, the agreement contained a work-through provision, which stated that
“no dispute shall interfere with the progress of construction, and [High Tech] shall
proceed with its work as directed.”
Over the course of the Project, Cambridge Swinerton sent notices to cure to
High Tech on June 29, 2017, September 20, 2017, and November 27, 2017. The
notices referenced High Tech’s inability to provide materials and complete the work
on schedule. Then, from November 27 to November 29, High Tech did not send any
laborers to the Project. On November 30, Cambridge Swinerton terminated the
agreement pursuant to Article 14 for lack of progress under the project schedule,
failure to procure materials in a timely manner, and abandonment of the job site.
Around this time, Cambridge Swinerton directly contacted High Tech’s aluminum
supplier, Ultra Manufacturing (“Ultra”), in order to buy enough material to complete
the Project.
In February 2019, High Tech filed a complaint against Cambridge Swinerton,
alleging, inter alia, claims for breach of contract, quantum meruit, unjust enrichment,
and tortious interference with contract. Cambridge Swinerton counterclaimed for
damages due to High Tech’s default. Cambridge Swinerton filed a motion for partial
summary judgment on High Tech’s claims, which the trial court granted. This appeal
followed.
Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. A de novo standard of review applies to an appeal from a grant or denial of summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant.2
“Contract disputes are particularly well suited for adjudication by summary judgment
because construction of contracts is ordinarily a matter of law for the court.”3
Construing the language of a contract presents a question of law for the court, unless the language presents an ambiguity that cannot be resolved by the rules of construction. The cardinal rule of construction is to ascertain the contracting parties’ intent, and where the terms of a written contract are clear and unambiguous, the court will look to the contract alone to find the intention of the parties.4
With these guiding principles in mind, we now turn to High Tech’s claims of error.
2 Griffin, 312 Ga. App. at 87 (citation and punctuation omitted).
3 Brazeal v. NewPoint Media Group, 331 Ga. App. 49 (769 SE2d 763) (2015)
(citations and punctuation omitted).
4 Id. at 53 (citations and punctuation omitted).
1. High Tech argues that the trial court erred in finding that Cambridge
Swinerton properly terminated the contract under Article 14. High Tech contends that
there was a question of fact as to whether Cambridge Swinerton terminated the
contract in good faith.
“[W]here the manner of performance is left more or less to the discretion of one
of the parties to the contract, that party is bound to the exercise of good faith.”5 The
question of good faith is generally a question for the jury.6 However, “[f]irms that
have negotiated contracts are entitled to enforce them to the letter, even to the great
discomfort of their trading partners, without being mulcted for lack of good faith.”7
“‘Good faith’ is a compact reference to an implied undertaking not to take
opportunistic advantage in a way that could not have been contemplated at the time
of drafting[; it does] not block use of terms that actually appear in the contract.”8
5 Shelnutt v. The Mayor & Aldermen of the City of Savannah, 333 Ga. App.
446, 453 (3) (776 SE2d 650) (2015) (citations and punctuation omitted).
6 See Camp v. Peetluk, 262 Ga. App. 345, 350 (2) (585 SE2d 704) (2003).
7 Martin v. Hamilton State Bank, 314 Ga. App. 334, 335 (723 SE2d 726)
(2012) (citations and punctuation omitted).
8 Id. (citation and punctuation omitted).
Here, it is undisputed that High Tech did not send workers to the Project for
three days after Cambridge Swinerton sent High Tech a notice to cure. Pursuant to
Free access — add to your briefcase to read the full text and ask questions with AI
HIGH TECH RAIL AND FENCE, LLC v. CAMBRIDGE SWINERTON BUILDERS, INC. N/K/A SWINERTON BUILDERS, INC. (HIGH TECH RAIL AND FENCE, LLC v. CAMBRIDGE SWINERTON BUILDERS, INC. N/K/A SWINERTON BUILDERS, INC.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.