Higgins v. United States

589 F. App'x 977
Court of Appeals for the Federal Circuit·Decided October 14, 2014·No. 2014-5025·Unpublished·Cited by 4 cases

Opinion

PER CURIAM.

Cheryl Higgins (“Higgins”) appeals from the decision of the United States Court of Federal Claims (the “Claims Court”) dismissing two of her claims as beyond the six-year statute of limitations and granting summary judgment in favor of the government on the third and remaining claim. See Higgins v. United States, No. 12-922C (Fed.Cl. Oct. 9, 2013) (“Opinion”). Because the Claims Court did not err in holding that it lacked jurisdiction over Higgins’ first two claims and in granting summary judgment on the third claim, we affirm.

BACKGROUND

The United States Department of Labor (“DOL”) awarded a grant in September 1999 to Devereaux Corporation (“Dever-eaux”), of which Higgins was the executive director. Id. at 2. The grant was for about $3 million, to be paid over a period of three years. Id. Months later, a DOL grant officer submitted a proposal to terminate the grant for “material failure to comply with the terms and conditions of a grant award” under 29 C.F.R. § 95.61(a)(1). Id. After considering Devereaux’s response, *979 DOL issued a Final Determination to terminate the grant. Id.

Devereaux submitted to the DOL Office of Administrative Law Judges (“ALJ Office”) a request for a hearing to review the Final Determination. Id. at 3. The ALJ Office issued a prehearing order requesting information from both parties. Id. Devereaux failed to comply, despite a show cause order, and the ALJ Office entered a default judgment in May 2001. Id.

After negotiations with Higgins, DOL prepared a Modification of the grant award to effectuate the termination by reducing the award amount and changing the expiration date to September 2000. Id. On October 24, 2001, Higgins and DOL signed the Modification, which was effective at execution, and the remainder of the negotiated amount was paid to Devereaux. Appellee’s App. 28, 38, 42. In May 2002, DOL officially closed the grant based on that settlement and payment. Id. at 42.

DOL subsequently sent closeout documents to Devereaux, but they were returned in the mail as undeliverable. Opinion at 3. After being notified that the corporation was defunct, DOL executed a unilateral closeout on May 12, 2004, adopting the terms of the Modification.. DOL then sent a preliminary settlement notice to Higgins on May 26, 2004 (“Settlement Notice”). Id. The Settlement Notice contained a paragraph that described certain situations in which further payment adjustments might be made for an amended settlement, including “[ujnresolved disputes or claims identified on the Grantee’s Release.” Id.

In November 2005,. Higgins sent a letter requesting over $1.5 million from the grant for reimbursement of various outstanding claims incurred by Devereaux. Opinion at 3. In February 2006, DOL responded with a letter stating that the grant had been closed out and no further funds were owed to Devereaux. Appellee’s App. 36-38. That letter noted the various documents and events concerning the grant termination and closure, including the Final Determination, the ALJ Office’s default judgment, and the Modification signed by both parties in October 2001. Moreover, the letter elaborated that the legislative authorization for the grant program had lapsed and that no additional funding was available. DOL and Higgins later had an in-person meeting and further written correspondence, in which DOL reiterated that the grant had been terminated, the Modification signed by Higgins reflected a negotiated settlement, the grant had been officially closed based on that settlement and payment of agreed costs, and no additional funds were available. Opinion at 3; Ap-pellee’s App. 42.

In October 2008, in response to another inquiry from Higgins, DOL sent a letter stating that the grant was terminated in accordance with 29 C.F.R. § 95.61(a)(2). Opinion at 3.

On December 28, 2012, Higgins filed suit against the government in the Claims Court alleging a breach of contract or, alternatively, entitlement to an amended settlement according to the Settlement Notice or a final settlement under § 95.61(a)(2). The court found that the breach of contract claim accrued on May 12, 2004, when DOL unilaterally closed out the grant. Id. at 4. Similarly, the court found that the amended-settlement claim accrued on May 26, 2004, when DOL sent the Settlement Notice. Id. at 6. The court also found that the termination occurred under § 95.61(a)(1) instead of § 95.61(a)(2). Id. at 5-6. The court thus dismissed the breach of contract claim and the amended-settlement claim as beyond the six-year statute of limitations, and granted summary judgment in favor of the government on the final-settlement claim *980 as arising under an inapplicable statutory provision. Id. at 7.

Higgins appealed to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).

Discussion

We review the Claims Court’s dismissal for lack of jurisdiction de novo. FloorPro, Inc. v. United States, 680 F.3d 1377, 1380 (Fed.Cir.2012). We also review the grant of summary judgment de novo. Holland v. United States, 621 F.3d 1366, 1374 (Fed. Cir.2010).

I. Claims Dismissed for Lack of Jurisdiction

Free access — add to your briefcase to read the full text and ask questions with AI

Higgins v. United States, 589 F. App'x 977 (Fed. Cir. 2014).

589 F. App'x 977 (Higgins v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mesa Grande Band of Mission Indians v. United States
121 Fed. Cl. 183 (Federal Claims, 2015)
Katzin v. United States
120 Fed. Cl. 199 (Federal Claims, 2015)