Higgins v. Standard Federal Savings & Loan Ass'n

188 Cal. App. 2d 68, 10 Cal. Rptr. 200
CourtCalifornia Court of Appeal
DecidedJanuary 6, 1961
DocketCiv. 6358
StatusPublished
Cited by4 cases

This text of 188 Cal. App. 2d 68 (Higgins v. Standard Federal Savings & Loan Ass'n) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Higgins v. Standard Federal Savings & Loan Ass'n, 188 Cal. App. 2d 68, 10 Cal. Rptr. 200 (Cal. Ct. App. 1961).

Opinion

SHEPARD, J.

Plaintiff-appellant Higgins brought two actions against defendant-respondent Desert Braemar, Inc., a corporation (hereinafter called “Desert”); one was to recover the reasonable value of plaintiff’s services as general contractor in the construction of apartment buildings near Palm Springs; the other was to foreclose a claim of general contractor’s lien on the same property against the same defendant for the same services. Other defendants were originally named, but all defendants except Desert were dismissed prior to trial. The two actions were consolidated for trial. From a judgment of nonsuit for defendant in each case, plaintiff appeals.

The rule of evidentiary weight on a motion for non-suit is clearly delineated by our Supreme Court in Mitchell Camera Corp. v. Fox Film Corp., 8 Cal.2d 192, 197 [2-3] [64 P.2d 946], as follows:

“ ‘Every favorable inference fairly dedueible and every favorable presumption fairly arising from the evidence adduced must be considered as facts proved in favor of the plaintiff. Where evidence is fairly susceptible of two constructions, or if one of several inferences may reasonably be made, the court must take the view most favorable to the plaintiff. If contradictory evidence has been given it must be discarded. [Citation.] The plaintiff must be given the benefit of every piece of evidence which tends to sustain his averments and such evidence must be weighed in ■a light most favorable to plaintiff’s claim. [Citation.] *71 Evidence whether erroneously admitted or not, if relevant to the issues joined, must be given the credit and benefit of its full probative strength, and any question arising from 'the fact of variation between the evidence of the witnesses cannot be raised or considered.’ [Citation.]” (See also Wulfjen v. Dolton, 24 Cal.2d 878, 879-880 [1] [151 P.2d 840] ; Van Buskirk v. McClenahan, 163 Cal.App.2d 633, 636 [1-4] [329 P.2d 924].)

Reviewing the evidence with the rule in mind that every favorable inference fairly dedueible and every favorable presumption fairly arising from the evidence adduced must be considered as facts proved in favor of plaintiff and that where evidence is fairly susceptible of two constructions or if one of several inferences may reasonably be made, the court must take the view most favorable to the plaintiff, the facts shown by the record are as follows: Desert is a corporation whose purposes include building, owning and operating cooperative apartment dwellings. Braemar Construction Company (hereinafter called “Braemar”) is a corporation whose purposes include organizing, promoting and constructing cooperative apartment dwellings. It was wholly owned by Paul J. Broman and Mr. Hanousek and their wives. Paul J. Broman (hereinafter called “Broman”) was the guiding spirit in the formation and operational conduct of both corporations and was, during all of the times herein mentioned, treasurer or president and managing agent of both Desert and Braemar.

In 1956 Desert sold stock to the amount of $624,800 and borrowed $900,000 from Standard Federal Savings and Loan Association (hereinafter called “Standard”). The total of both of these sums was placed in the custody of Standard to pay bills for construction of a 100-unit apartment dwelling near Palm Springs. Braemar, at the behest of Desert, secured subcontractor bids for the proposed construction, and in April 1956 approached Higgins for the purpose of securing subcontractor bids on framing, hardware and clean-up. Higgins was accepted ultimately as the subcontractor on framing and clean-up.

Broman was later warned by a state inspector of the necessity for a general contractor’s license for Desert. Broman knew that neither he nor Desert nor Braemar had such license. He approached Higgins to take over the whole general contract. He knew that Higgins held a general contractor’s license. Negotiations were had. He represented to Higgins that he held a general contractor’s license. Later, on July *72 21, 1956, Broman, as president and moving spirit of both Desert and Braemar, caused a construction contract to be executed from Desert to Braemar whereby Braemar purported to become general contractor for the construction of the apartments. Broman signed the contract as president of Desert and also as president of Braemar. Both Desert and Braemar knew that neither Desert nor Braemar nor Broman had a general contractor’s license. Higgins did not know this. The knowledge of Broman, in the ease here at bar, is clearly chargeable to both Desert and Braemar. (McKenney v. Ellsworth, 165 Cal. 326, 329-330 [132 P. 75] ; Dicker v. Italo-American Oil Corp., 119 Cal.App. 451, 456 [6] [6 P.2d 550]; Verder v. American Loan Society, 1 Cal.2d 17, 27 [2] [33 P.2d 1081] ; Frankish v. Federal Mortgage Co., 30 Cal.App.2d 700, 721 [8] [87 P.2d 90].)

Responsive to Broman’s representations and urgings, Higgins, early in July 1956, entered into an oral agreement to act as general contractor and commenced the work of construction. A tentative condition was attached to this contract that Higgins would secure a bond in the sum of $1,000,000. However, when it eventually developed that Higgins could not secure the bond, Higgins ’ work was not stopped. Higgins had, immediately after the date of the oral contract, taken out all construction permits in his own name. He continued right on with the work of general contractor in charge of construction with control of voucher approval for payrolls and other expenses, nominally in Braemar, as before.

August 16, 1956, the parties purported to enter into a written- contract making Higgins associate general contractor. No change in the management, operation or control which had theretofore obtained was made at the time this writing was executed, nor at any time thereafter until completion.

Broman visited the job occasionally and to a minor degree improperly interfered with a few of the workmen to the detriment of the job and added difficulty for Higgins. Higgins did at times defer to Broman’s requests respecting priorities to some particular preferred tenant. This deference, however, was no greater than might be expected from any general contractor in an attempt to keep the owner happy. No complaint is made of the work of construction done by Higgins. Higgins was never paid for his services as general contractor.

Both the contracts of July 21,1956, and of August 16, 1956, were void, and no action could be maintained on either of them. If upon a trial of the merits, the court should find that *73 Higgins’ claim is, in truth and in fact, grounded on these illegal contracts, it would have no option but to deny him relief '; not even a claim of estoppel would help him. (Holm v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Associated Creditors' Agency v. Davis
530 P.2d 1084 (California Supreme Court, 1975)
Felix v. Workmen's Compensation Appeals Board
41 Cal. App. 3d 759 (California Court of Appeal, 1974)
Higgins v. Desert Braemar, Inc.
219 Cal. App. 2d 744 (California Court of Appeal, 1963)
Levelon Builders, Inc. v. Lynn
194 Cal. App. 2d 657 (California Court of Appeal, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
188 Cal. App. 2d 68, 10 Cal. Rptr. 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/higgins-v-standard-federal-savings-loan-assn-calctapp-1961.