Higgins v. Drucker

22 Ohio C.C. 112
CourtOhio Circuit Courts
DecidedJanuary 15, 1901
StatusPublished

This text of 22 Ohio C.C. 112 (Higgins v. Drucker) is published on Counsel Stack Legal Research, covering Ohio Circuit Courts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Higgins v. Drucker, 22 Ohio C.C. 112 (Ohio Super. Ct. 1901).

Opinion

Marvin, J.

This petition m error is brought for the purpose of reversing a judgment rendered in favor of Augusta Drucker against George G. Higgins and The United States Fidelity & Guaranty Company. By proper proceedings the case is here, together .with a bill of exceptions containing all the evidence introduced in the court below, and we are asked to reverse the judgment on the ground that errors which, it is said, exist, are shown in the record of the case.

The terms “plaintiff” and “defendant” used in this opinion, refer to the parties as they stood in the original action..

The defendant, Higgins, entered into a contract in writing with the plaintiff on the 14th day of Eebruary, 1898, a copy of‘which contract is attached to the petition in the case. The contract required of Higgins that for the sum of $4,520 he should “at his own proper charge and expense, well and substantially erect, build and furnish the carpenter work of a certain brick and stone building on the east side of Case Avenue, corner of Scovill, in Cleveland, Ohio, according to the specifications, drawings and plans made and prepared by “certain architects named in the contract.”

A further stipulation to be performed by Higgins is in these words: “Said George G. Higgins for himself, his heirs, executors and administrators, agrees that he will furnish and provide, at his own proper charge and expense, all iron, stone, brick, tile, lime, and timber, and all other material not hereinbefore mentioned, and also all work and labor-, necessary for the erection, building and furnishing of carpenter .work of said building.”

On the 29th of April, 1898, and after the said Higgins had performed a part of the stipulations on his part to be perform[114]*114ed under the contract hereinbefore mentioned, he entered into a bond to the plaintiff in the penal sum of two thousand dol;lars, the defendant, the United States Fidelity & Guaranty] -Company executing said bond as surety for the said Higgins. The following is a quotation from said bond:

“Whereas, said principal has entered into, a certain written 'contract bearing, date the 14th day of February, 1898, by and between him and the said Augusta Drucker to erect, build and •finish the Carpenter work of a certain brick and stone building on the east side of Case Avenue, corner of Scovill Street, in the -city of Cleveland, Ohio, according to the specifications, drawings and plans made and prepared by George A. Steffens, Paul G. Séarles, and Willard Hirsh, said contract being made ■a'part thereof as- fully to' all intents and purposes as if set forth at length herein.

" “Now, therefore, the condition of the foregoing obligation is such that if the said principal shall well, truly and faithfully comply with all the terms, covenants and conditions of said "contract on his part to be kept and performed according to its tenor, then this obligation is to be null and void, otherwise ¿to be remain in full forcé and virtue in law.”

Higgins did not complete his contract; but the work hav■ing progressed' to a given point, he discontinued work under 'the contract about the 1st of September, 1898. At that time or up to that time he had received in payment upon the contract a little less than four thousand dollars. The plaintiff proceeded to complete the work, which was to have been done under the contract, at an expense of something like $3,500, and then brought her suit against Higgins and the surety company, and recovered, judgment against the Company for the sum of $2,186.66, being'the amount of the penalty named in the bond, with interest lip to the first day of the term of court at which the judgment was rendered.

One of-the-complaints made of the action of the trial court, is the overruling of the motion for a new trial, on the ground that by reason of interruptions during its progress the defend'ants -failed to have a fair trial. The evidence upon this, as .shown by affidavits filed in the court below, is to the effect ‘that the-trial, began on the 26th day of October, 1900, which [115]*115•was some ten days before'the presidential électiÓn’óf that' year. The case was submitted’to tlie jury oil'the-8th day of November following. The election took place oh 'thé 6th úP November. Almost immediately Upon the beginning of the' trial, there were interruptions by reason of the' appíicatiórP' of persons to the court for liatúralization, arid thé applicants' came in great numbers into the court room arid the court* stopped the hearing of this'case-a-good many-times,! and for’a Considerable time on several such interruptions»’ devbtiiig such’ time to the naturalization of these applicants fof- citizenship-; so that but a little time each day was occupied' in’the actual' trial of the case up to and-including the ist' of November..' On that day, by reason of these numerous interruption’s arid of the fact 'that such interruptions were likely to' continue up' to the day of the election, counsel on both sideis ■'requested thel Court to postpone the further hearing of the case until the 7th day of November, which'was'accordingly done'byt'he cori-rtv The case being taken up on the last named date, proceeded' without interruption until the trial was concluded.- . That' these interruptions and delays were most urifortunate arid very annoying to the parties in the case as well as to the court/ is manifest. That the defendants were prejudiced in thel final result by reason of such interruptions, is not so inanifest. The trial judge, upon the motion -for a new-trial, having personal knowledge- of the entire situation,' did not - find that such was the case, and we are not prepared to say that; the court was wrong .. ' '• .

Another complaint is made that the court in its ’charge to’ the jury gave a wrong construction to the bond given by thd Surety Company. The language of the bond -to which attention is now called, reads:

“Provided, * * * that if the said principals shall fail t©\ comply with all the conditions of said contract to' súch. an.ex-* tent that the same shall be forfeited, then said Su'rety’shall' have the'right and privilege to assuime said contract'-arid fo submit or complete same, whichever said Surety -may' elect to' do, provided it is done in accordance- with said contract/

Provided, '-furtherthat .in- the' 'event of any -brfeách of theí conditions of this bond, said Surety shall be subrogated td all» [116]*116the rights and properties of said principal arising out of said contract, and all deferred payments and any and all moneys and properties at that time due and payable, or that may thereafter become due and payable to the said principal, under and by virtue of said contract, shall be credited upon any «claim the said Augusta Drucker may .make upon said surety because of said surety.”

. Qn the part of the plaintiff it is urged that there being about $6oo unpaid upon the contract price at the time said Higgins discontinued the work, that amount should be credited to the defendant, the Surety Company, thereby reducing the amount to which the plaintiff, if entitled to recover at all, should have been permitted to recover against the Surety Company. And the court was requested by the Surety Company to charge:

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
22 Ohio C.C. 112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/higgins-v-drucker-ohiocirct-1901.