Higgins Erectors & Haulers, Inc. v. E.E. Austin & Son, Inc.

714 F. Supp. 756, 1989 U.S. Dist. LEXIS 6770, 1989 WL 63976
CourtDistrict Court, W.D. Pennsylvania
DecidedJune 5, 1989
DocketCiv. A. 87-237 Erie, 88-127 Erie
StatusPublished
Cited by5 cases

This text of 714 F. Supp. 756 (Higgins Erectors & Haulers, Inc. v. E.E. Austin & Son, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Higgins Erectors & Haulers, Inc. v. E.E. Austin & Son, Inc., 714 F. Supp. 756, 1989 U.S. Dist. LEXIS 6770, 1989 WL 63976 (W.D. Pa. 1989).

Opinion

OPINION

GERALD J. WEBER, District Judge.

We are herein confronted with a classic example of what is commonly referred to as “passing the buck.” The particular “buck” with which we are concerned has been passed no less than seven times. The opportunity has now come for us to step in and determine where the buck stops.

I. Facts

The basic facts upon which these cases arise are fairly simple, and begin in May, 1984. Hammermill Paper Company selected E.E. Austin & Sons, Inc. as the prime contractor for some construction work in Erie, Pennsylvania. E.E. Austin in turn subcontracted some of the work out to Higgins Erectors & Haulers, Inc. Pursuant to the terms of the subcontract, Higgins was to complete performance of its work prior to November, 1984. This work, however, was not completed until April 2, 1985.

II. Procedural History

A. Higgins v. E.E. Austin — C.A. 87-237E

Unfortunately, the procedural history of this case is not as simple as its basic facts. Higgins initiated the chain of buck passing by filing a complaint against E.E. Austin. The complaint alleges that E.E. Austin breached the subcontract through a number of acts and omissions which delayed the completion of construction. These include the failure to timely furnish necessary equipment, machinery and materials, and the failure to provide Higgins timely access to certain areas of the project. As a result of E.E. Austin’s acts and omissions, Higgins claims to have sustained damages in the amount of $216,105.46. These damages primarily consist of added costs due to the extended construction period.

Refusing to accept responsibility for the delayed construction, E.E. Austin opted to pass the buck in two separate directions. First, it filed a counterclaim alleging that Higgins breached the subcontract thereby causing the delay in construction. The alleged breach of the subcontract included undermanning of certain aspects, lack of timeliness in completing work activities, inefficiencies in accounting, and poor work quality. In the counterclaim, E.E. Austin alleges damages of $75,052.00 caused by the delay.

The second manner in which E.E. Austin attempts to pass the buck is through a third party complaint against Hammermill, based upon a claimed breach of the prime contract. There, E.E. Austin alleges, inter alia, that the delays were caused by Ham-mermill’s failure to: provide equipment and machinery on a timely basis; provide access to the premises; and timely provide drawings and specifications. Higgins thereby seeks contribution and/or indemnity from E.E. Austin.

Not wishing to be outdone, Hammermill filed a counterclaim against both Higgins and E.E. Austin alleging that their acts and omissions caused Hammermill to suffer $264,600.00 in damages, due to the resultant delay in starting up its new pulp producing system. In addition, Hammermill *758 claims $6,300.00 in damages against Higgins, based upon an alleged breach of an entirely separate contract “to move a ‘dea-rator tank’ into service.”

In response to Hammermill’s counterclaim against it, E.E. Austin deemed it necessary to jump on the bandwagon for a second ride by filing a crossclaim against Higgins for contribution and/or indemnity should E.E. Austin be found liable for any damages claimed by Hammermill.

Hammermill, apparently concerned that not enough people had been invited to the party, also prepared an invitation list of its own joining the following as fourth party defendants: Sandwell International, Inc.; Swan Wooster Engineering, Inc.; and their successors, Schuchart & Associates, Inc.; Sandwell Swan Wooster, Inc. (a Canadian corporation); and Sandwell Swan Wooster, Inc. (a Georgia corporation). We will not attempt to embark upon an explanation of the interrelationships of these corporations. We will instead treat them as one entity which we will refer to as “Sandwell.” Sandwell was retained by Hammermill to perform engineering services relative to the project in which E.E. Austin was the prime contractor. The basis of the fourth party complaint is the allegation that Sand-well’s delay in providing Hammermill with drawings and specifications is the reason for Hammermill’s delay in supplying them to E.E. Austin.

Finally, our cast of characters becomes complete with the filing of a fifth party complaint by Sandwell against J.C. Williamson Company. Williamson had a separate contract with Hammermill which included providing design drawings and certain conveyor belts. Sandwell alleges that Williamson’s negligent delays in providing these to Hammermill led to Sandwell’s own delays in providing drawings and specifications for the foundation supports for the Williamson conveyors.

B. Higgins v. Hammermill — C.A. 87-127E

Apparently believing that the waters had yet to be muddied enough by the ongoing proceedings in its action against E.E. Austin, Higgins also initiated a separate cause of action directly against Hammermill. In its complaint, Higgins places the blame for the delayed construction upon Hammermill. Because, however, Higgins had no direct contractual relationship with Hammermill on the project, Higgins has pled a cause of action for unjust enrichment. Hammermill responded by filing a counterclaim identical to the one filed in C.A. 87-237E. It also filed a third party complaint against E.E. Austin and the Sandwell group, alleging the same causes of action against them as in C.A. 87-237E. Upon the motion of Ham-mermill, this action was consolidated with 87-237E, at that number.

III. Discussion

Presently, pending before us in these consolidated actions are several motions to dismiss. Having sorted through the intricate web of claims, counterclaims and crossclaims, and resolved the confusing question of “who’s on first?” we will now address these motions.

A. Motion to Dismiss Fifth Party Complaint Against J.C. Williamson Company — C.A. 88-237E

J.C. Williamson Company has moved to dismiss the fifth party complaint against it for failure to state a claim. In response to Williamson’s motion, Sandwell provides the following clarification of the basis of its claim for indemnity and/or contribution:

Sandwell’s stated indemnity cause of action against Williamson is not direct, but rather is secondary or derivative. While Sandwell readily admits that there is no contractual indemnity agreement between Sandwell and Williamson, if Sandwell is found liable, its liability is secondary to that of Williamson. See, e.g., Eckrich v. DiNardo, 283 Pa.Super. 84, 423 A.2d 727 (1980).
With regard to contribution, Sandwell recognizes that this cause of action only arises between joint tortfeasors. In Lasprogata v. Qualls, 263 Pa.Super. 174, 397 A.2d 803 (1979), the court defined tortfeasors by noting that “the parties must either act together in committing the wrong, or their acts, if independent of each other, must unite in causing a *759

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BAUM v. SCHLESINGER
W.D. Pennsylvania, 2023
EQT Production Co. v. Terra Services, LLC
179 F. Supp. 3d 486 (W.D. Pennsylvania, 2016)
Dunn v. Praiss
638 A.2d 875 (New Jersey Superior Court App Division, 1994)
Richardson v. John F. Kennedy Memorial Hospital
838 F. Supp. 979 (E.D. Pennsylvania, 1993)
University Patents, Inc. v. Kligman
762 F. Supp. 1212 (E.D. Pennsylvania, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
714 F. Supp. 756, 1989 U.S. Dist. LEXIS 6770, 1989 WL 63976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/higgins-erectors-haulers-inc-v-ee-austin-son-inc-pawd-1989.