Higgins & Coufal v. Massachusetts Bonding & Insurance

112 F. Supp. 390, 1953 U.S. Dist. LEXIS 2782
CourtDistrict Court, D. Nebraska
DecidedMay 25, 1953
DocketCiv. A. No. 3-53
StatusPublished
Cited by1 cases

This text of 112 F. Supp. 390 (Higgins & Coufal v. Massachusetts Bonding & Insurance) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Higgins & Coufal v. Massachusetts Bonding & Insurance, 112 F. Supp. 390, 1953 U.S. Dist. LEXIS 2782 (D. Neb. 1953).

Opinion

DONOHOE, Chief Judge.

This action was originally instituted in the District Court of Colfax County, Nebraska, by Higgins and Coufal, a co-partnership, the members of which are citizens of Nebraska, against the Massachusetts Bonding and Insurance Company, a Massachusetts corporation, to recover on a construction contract bond. Pursuant to section 1442, Title 28 U.S.C.A., the defendant bonding company removed the action to this court which has jurisdiction by reason of the fact that there is diversity of citizenship and the amount involved exceeds $3,000, exclusive of interest and costs. 28 U.S.C.A. 1332. Before service of its answer the defendant bonding company by motion, proper in form, requested leave to bring into this action as third-party defendants, the Central Drainage and Construction Company, and Edward and Delores Cerovski, the principal obligors for whose benefit the indemnity bond was issued. The request was granted, rule 14, Federal Rules of Civil Procedure, 28 U.S. C.A.; and process was served upon the third-party defendants. However, they neither answered nor entered their appearance and consequently they are now in default. Rule 55(a), Federal Rules of Civil Procedure, 28 U.S.C.A. In the absence of a request by either party for a jury, this action was tried to the court, rules 38 and 39, Federal Rules of Civil Procedure, 28 U.S.C.A. The court, in keeping with rule 52, Federal Rules of Civil Procedure, 28 U.S.C.A., makes the following special

Findings of Fact.

On June 20, 1950, the Central Drainage and Construction Company, third-party defendants herein, entered into two contracts with the Department of Roads and Irrigation of the State of Nebraska covering certain construction work. The first contract related to work on the Platte River near Yutan in Saunders County, Nebraska. The second contract covered a project near Talmage in Otoe County, Nebraska. Before entering upon performance of either of these contracts, the Central Drainage and Construction Company filed performance bonds in the sum of $10,162, for the Yutan Project, and in the sum of $9,659.10, for the Talmage Project. These bonds were executed by the Central Drainage and Construction Company as principal and the Massachusetts Bonding and Insurance Company, defendant herein, as surety. Among other things, these bonds provided:

“It is expressly understood and agreed that this bond is given to secure and does secure not only the faithful performance by the principal herein named of said contract for the construction work as specified in said contract and in strict accordance with the terms of said contract and the plans and specifications made a part thereof; but that it is given to secure and does secure also the payment by the said bounden Central Drainage and Construction Company, of all just claims for materials, supplies, tools, fuel, lubricants, equipment rental, machinery, insurance premiums, and services used or consumed in the construction of the work by him or any of his subcontractors, and for all other just claims filed against him or any of his subcontractors in carrying out the provisions of this contract, and if such payments be made then this obligation^) shall be null and void; otherwise it shall remain in full force and effect.”

In connection with the performance of these construction contracts, the Central Drainage and Construction Company ordered certain materials and supplies from Higgins and Coufal, a copartnership dealing in building materials. These materials were delivered with the understanding and verbal agreement, between the Central [392]*392Drainage and Construction Company and Higgins and Coufal that the Construction Company need not pay for the materials until the projects were completed and the State had made payment in keeping with the terms of the construction contracts. However, both Higgins and Coufal and the Construction Company assumed as a basis for their agreement that the projects wouldbe completed in due course and within a reasonable time. In this connection, Mr. Cerovski, president of the Construction Company, testified (and his testimony was not rebutted nor contradicted) that he did not consider that abandonment of either or both of the projects would excuse his corporation from paying for the materials supplied.

Higgins and Coufal notified the Massachusetts Bonding and Insurance Company of the beforementioned understanding by a letter, dated June 24, 1950, to Mr. K. J. Folda, their agent, which reads as follows:

“Dear Kite:
“This will advise you we have agreed to carry Ed Cerovski’s account for material on the Talmage and Yutan jobs, until they are completed and he receives payment from the state.
“Sincerely
“Higgins and Coufal
“Martin J. Higgins /s/”

For the Talmage job the Construction Company ordered Creosote piling from the plaintiff partnership. Pending arrival of these materials, the Construction Company obtained some piling from the Midwest Lumber, Bridge and Supply Company of Lincoln, Nebraska, and used this material in the project. Later, when the material from Higgins and Coufal arrived at Talmage, the Construction Company used part of it (valued at $532.32) to repay in kind and quantity the Midwest Lumber, Bridge and Supply Company for the material previously furnished and used the balance of the materials to complete the Talmage Project. Thus, all of the material furnished to the Construction Company by Higgins and Coufal for the Talmage Project was used and consumed either directly or indirectly in the completion of that project. The agreed price, and fair and reasonable value, of the piling furnished by Higgins and Coufal to the Construction Company for this project was $2,602.38. On March 20, 1951, the president of the Construction Company, Ed Cerovski, paid $510.50 on this account; consequently, there is a balance of $2,091.88, with interest, still due and owing. The Talmage Project has been fully completed.

Higgins and Coufal also furnished the Construction Company material at the agreed price, and reasonable value, of $3,169.68, for the Yutan Project. All of this material was used and consumed in the project. Because of high river conditions and certain difficulties the Construction Company had with the State Engineers, the Yutan Project was not finished in due course; nor was it completed within a reasonable time. Although the project was started in 1950, it has not yet been completed; and the evidence indicates that in all probability, it will never be completed by the Central Drainage and Construction Company.

Having made demand upon the Central Drainage and Construction Company for payment, and having been refused payment, Higgins and Coufal instituted this action against the Massachusetts Bonding and Insurance Company.

Discussion.

The bond in suit is a statutory bond written in conformity with section 52-118; R.R.S.Neb., 1943, and must be construed and interpreted in connection with the provisions of this statute. Iddings Co. v. Lincoln Construction Co., 104 Neb. 124, 175 N.W. 643. The statute provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
112 F. Supp. 390, 1953 U.S. Dist. LEXIS 2782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/higgins-coufal-v-massachusetts-bonding-insurance-ned-1953.