Hibernian Banking Ass'n v. Bell & Zoller Coal Co.

181 Ill. App. 581, 1913 Ill. App. LEXIS 316
CourtAppellate Court of Illinois
DecidedJune 30, 1913
DocketGen. No. 17,032
StatusPublished
Cited by5 cases

This text of 181 Ill. App. 581 (Hibernian Banking Ass'n v. Bell & Zoller Coal Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hibernian Banking Ass'n v. Bell & Zoller Coal Co., 181 Ill. App. 581, 1913 Ill. App. LEXIS 316 (Ill. Ct. App. 1913).

Opinion

Mr. Presiding Justice Duncan

delivered the opinion of the court.

Hibernian Banking Association, trustee in bankruptcy of Cooke-Rutledge Coal Company, sought to recover damages in this suit from Bell & Zoller Coal Company for the latter’s failure to deliver a balance of 205 cars of coal according to contract. Verdict and judgment were rendered in favor of Bell & Zoller Coal Company and the trustee in bankruptcy sued out this writ of error.

The contract sued on bears date May 21,1902, and is an accepted proposition of defendant in error to plaintiff in error’s company in these terms:

“We agree to supply and you agree to take from us nine (9) cars per week of No. 2 Nut or Pea coal from date until April 1st, 1903, on the basis of $1.40 per ton, f. o. b. Illinois Central tracks, Chicago. Mine or Illinois Central Railroad weights at Chicago to govern settlements, which are to be made on or about the 15th of the month for previous month’s shipments. The above is subject to strikes or other contingencies beyond our control. Tour acceptance to the above to constitute a contract between us.”

The evidence for both parties shows that for the time mentioned in the contract only the following deliveries of No. 2 nut or pea coal were made by defendant in error to plaintiff in error’s company at the contract price, to wit: for the week ending May 27th, 15 ears; June 3rd, 10 cars; June 10th, 6 cars; June 17th, 28 cars; June 24th, none; July 1st, 16 cars; July 8th, 22 cars; July 15th, 5 cars; July 22nd, 4 cars; July 29th, none; Aug. 5th, 2 cars; Aug. 12th, none; Aug. 19th, 6 cars; Aug. 26th, 7 cars; Sept. 2nd, none; Sept. 9th, 2 cars; Sept. 16th, 15 cars; Sept. 23rd, 8 cars; Sept. 30th, 10 cars ;■ October 7th, 20 cars; October 14th, none; October 21st, 2 cars; from October 21st to October 23rd, 8 cars. Total delivered, 186 cars.

An inspection of the foregoing weekly deliveries of coal reveals the fact that for the time coal was delivered it was delivered irregularly. For some weeks no coal at all was delivered, for some of the weeks the deliveries were in excess of nine cars per week, while in others it was less than the contract rate of nine cars per week. Treating this contract as meaning that the deliveries should be made at an average of nine cars per week, the contract as to delivery was fully and exactly performed up to August 12, 1902, the end of the twelfth week, when exactly 108 cars had been delivered. Up to that date there were three weeks in which no deliveries were made, one each in the months of J une, July and August. There were five weeks in which more than nine cars per week were delivered, and four other weeks of those twelve weeks in which less than nine cars per week were delivered. From August 12, 1902, up to and including the week ending November 4, 1902, there were four weeks in which no coal at all was delivered, five other weeks in which the deliveries were less than nine cars per week and three weeks in which the deliveries exceeded nine cars per week.

With the same interpretation of the contract defendant in error owed the following deliveries of coal up to the time it ceased to deliver coal to wit: for the week ending August 19th, 3 cars; August 26th, 2 cars; September 2nd, 9 cars; September 9th, 7 ears; or a total of 21 ears. With the foregoing losses supplied the delivery of coal would be completely and exactly carried out up to October 28, 1902, the twenty-third week of the contract, with a total delivery of 207 cars of coal. For the remaining twenty-two weeks of the contract no coal at all was delivered under the contract in question, that is to say, 198 additional cars were never delivered on the contract. The first week of this delinquency ended Nov. 4, 1902, and the last week ended March 30,1903. Under the contract the end of the first week was May 28, 1902, and the end of the last week of the contract, April 1, 1903, and all the weeks intervening those dates ended one day later than the indications above which are given as the showing under the evidence. Three witnesses for plaintiff in error testified that the market price of No. 2 nut coal, f. o. b. cars Chicago, for week ending November 5, 1902, was from $2.15 to $2.60 per ton, while two witnesses for defendant in error testified that the market price was from $1.75 to $2.25 per ton. The evidence further showed that the market price for that coal so delivered continued to increase until the week ending February 28,1903, at which last date the market price per ton in Chicago, as testified to by plaintiff in error’s witnesses, was from $3.25 to $5.25 per ton, and by defendant in error’s witnesses at from $2.10 to $2.50 per ton; that-the price then began to gradually decline until March 31, 1903, at which date plaintiff in error’s witnesses testified that the market price was from about $1.70 to $2.25 per ton, while defendant in error’s witnesses testified that it slumped to as low as $1.40 per ton. The evidence of defendant in error’s witnesses also showed that the prices of that coal through September, 1902, ranged from $1.40 to $1.55, and through the next month of October, from $1.65 to $2.00 per ton. The only evidence in the record concerning the market for that coal in Chicago for the other months of the contract was given by Mr. Bell for defendant in error, in substance, that the market in May, 1902, was dull, duller in July, 1902, and dullest in the month of August, 1902.

The weight of the evidence in this record shows clearly that the parties to said contract by their conduct interpreted it to mean that defendant in error was required to deliver, and that plaintiff in error’s company was required to accept, nine cars of No. 2 nut coal on an average per week at the contract price; that the contract was recognized by both parties and treated by them as in full force until September 4, 1902, when defendant in error sought to have the contract rescinded and canceled as shown by its letter of that date to Cooke-Rutledge Coal Company, in which it said:

“We judge from the fact that what coal you have taken on your contracts with us for No. 2 nut and Carterville egg coal, that we have been obliged to call you up on the telephone and beg you to take it, that it is a hardship for you to handle this coal and as you are aware, you have not taken anywhere near the amount of coal provided for in the contracts, some weeks not taking any at all, and as we notice you are taking similar grades of coal from others, we wish to consider these contracts cancelled without a loss to either party.”

That on or about September 5, 1902, Mr. Cooke, the general manager of plaintiff in error’s company, visited Mr. Bell, the president of the defendant in error, and after protesting that his company had not violated any terms of the contract, secured an agreement from Mr. Bell for the defendant in error that it would resume the shipping of said coal under said contract on Monday, September 8, 1902, and would carry out the remainder of the contract until it was completed, according to the written terms thereof; that the defendant in error did resume the shipment of coal under said- contract as it agreed through Mr. Bell and continued to ship coal in accordance therewith until about October 23, 1902, when it ceased to ship coal thereon entirely and refused so to do on request of plaintiff in error’s company, basing its refusal on the sole grounds that the contract was canceled as per its said letter of September 4th. It is true that Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CONTINENTAL NAT'L BK. OF FORT WORTH v. Schiller
411 N.E.2d 593 (Appellate Court of Illinois, 1980)
Kitsos v. Terry's Chrysler-Plymouth, Inc.
388 N.E.2d 1054 (Appellate Court of Illinois, 1979)
Fuhrer v. State
22 Ill. Ct. Cl. 144 (Court of Claims of Illinois, 1955)
Schmahl v. Aurora National Bank
35 N.E.2d 689 (Appellate Court of Illinois, 1941)
Craft v. Calmeyer
274 Ill. App. 296 (Appellate Court of Illinois, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
181 Ill. App. 581, 1913 Ill. App. LEXIS 316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hibernian-banking-assn-v-bell-zoller-coal-co-illappct-1913.