HF Sinclair Refining & Marketing LLC v. NextEra Energy Marketing LLC

District Court, N.D. Texas·Decided April 17, 2025·No. 3:23-cv-01798·Unknown

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF TEXAS DALLAS DIVISION

HF SINCLAIR REFINING & § MARKETING, LLC, § § Plaintiff, § § v. § Civil Action No. 3:23-CV-1798-X § NEXTERA ENERGY MARKETING, § LLC, § § Defendant. §

MEMORANDUM OPINION AND ORDER

Before the Court is Defendant NextEra Energy Marketing, LLC’s (NextEra) motion to compel (Doc. 84) and HF Sinclair Refining & Marketing, LLC’s (Sinclair) motion to exclude certain opinions of Bob Broxson (Doc. 94). The Court has reviewed the parties’ briefs and the law and GRANTS IN PART and DENIES IN PART the motion to compel (Doc. 84) and DENIES the motion to exclude (Doc. 94). I. Factual Background This is a natural gas contract dispute arising from Winter Storm Uri. The parties had a contract under which NextEra would provide Sinclair with natural gas at the OGT Pool, a pipeline system in Oklahoma. When Uri hit, NextEra declared a force majeure and did not fulfill its delivery obligation to Sinclair for three days. NextEra seeks the following information from Sinclair: “(1) additional sources of gas supply that [Sinclair] had available to it during Winter Storm Uri, (2) how much that gas cost [Sinclair], and (3) how much gas [Sinclair] reasonably required during Uri, that all goes to the heart of its claimed damages in this case.”1 In addition, NextEra wants testimony from an adequately prepared Sinclair representative who can speak to the topics above.

II. Legal Standards “[U]nder Fifth Circuit law, the party resisting discovery must show specifically how each discovery request is not relevant or otherwise objectionable.”2 Federal Rule of Civil Procedure 26 defines to scope of discovery as “any nonprivileged matter that is relevant to any party’s claim or defense and proportional to the needs of the case.”3

III. Analysis There are three issues in this discovery dispute: (1) whether NextEra’s discovery requests untimeliness is excusable, (2) whether the discovery is relevant, and (3) whether Sinclair’s corporate representative was prepared at the deposition. A. Timeliness This motion to compel came after the deadline for discovery.4 Courts consider different factors when deciding whether a late motion to compel should nevertheless

be permitted. Those are: (1) the length of time since the expiration of the deadline, (2) the length of time that the moving party has known about the discovery,

1 Doc. 84 at 1. 2 Samsung Elecs. Am. Inc. v. Yang Kun “Michael” Chung, 325 F.R.D. 578, 593 (N.D. Tex. 2017) (Horan, M.J.) (citing McLeod, Alexander, Powel & Apffel, P.C. v. Quarles, 894 F.2d 1482, 1485 (5th Cir. 1990)). 3 Fed. R. Civ. P. 26(b)(1). 4 Even though discovery was open for depositions, it was no longer open for documents. Doc. 57 at 1; Doc. 69 at 1. (3) whether the discovery deadline has been extended, (4) the explanation for the tardiness or delay, (5) whether dispositive motions have been scheduled or filed, [6] the age of the case, [7] any prejudice to the party from whom late discovery was sought, and [8] disruption of the court’s schedule.5 NextEra did not file this motion to compel until nearly a month after the document discovery deadline, which is longer than the two-week delay in Days Inn.6 NextEra has known since at least August 7, 2024, that Sinclair could have used other sources of fuel at the Tulsa Refinery7; has known since at least May 2, 2024, about pool imbalances8; and has known since at least August of 2024 that Sinclair “ramped down” the Tulsa Refinery.9 The parties extended their deposition deadline to September 30, 2024,10 and then again the parties extended the deadline for expert depositions to October 17, 2024.11 NextEra sought this discovery eleven days before dispositive motions were due.12 This case is not exceedingly old, just middle-aged; the information sought does not appear unjustifiably prejudicial to Sinclair; and the Court’s schedule will be disrupted as it waits for discovery, supplemental briefing, and likely further motions to seal on top of that. Given that these other factors are a mixed bag, NextEra’s

explanation becomes very important.

5 Days Inn Worldwide Inc. v. Sonia Invs., 237 F.R.D. 395, 398 (N.D. Tex. 2006) (Ramirez, M.J.). 6 Id. 7 Doc. 150 at App. 67. 8 Doc. 129 at 37. 9 Doc. 150 at App. 176, 178. 10 Doc. 69 at 1. 11 Doc. 78 at 1. 12 Doc. 84 at 17. As for NextEra’s explanation for the delay, it only provides one for the long imbalance issues, not the “ramped down” issue. NextEra did not learn of the long imbalance’s presence on the spreadsheet until September 30, 2024, and discovered

on that day (the day NextEra deposed Sinclair’s corporate representative) that Sinclair had drawn roughly half of the gas needed at the Tulsa Refinery from the long imbalance.13 Sinclair provided NextEra a less-redacted version of the spreadsheet— in the middle of the deposition.14 Therefore, the Court finds that the late motion to compel is excused as to the first two categories of information—the ones dealing with the long imbalance—but

not with respect to documents relating to the “ramped down” state of the Tulsa Refineries. B. Relevance As for relevance, one part of the contractual damages remedy is key: the Cover Standard, which is used to determine a component of the damages calculation. Crucially, the “Cover Standard” means “that if there is an unexcused failure to take or deliver any quantity of Gas pursuant to this Contract, then the performing party

shall use commercially reasonable efforts to . . . obtain Gas . . . at a price reasonable for the delivery or production area . . . .”15 The Cover Standard also contemplates the “immediacy of the Buyer’s Gas consumption needs.”16

13 Doc. 84 at 9–10. 14 Doc. 84 at 9. 15 Doc. 84-1 at App. 22. 16 Doc. 84-1 at App. 22. Here, it is possible that information concerning replacement gas would factor into the damages calculation, because it could reveal the prices Sinclair paid for gas obtained, which goes directly to the Cover Standard. For its part, Sinclair says this

information is irrelevant because the contractual obligation is to provide gas to the OGT Pool, not Sinclair’s downstream refineries. Therefore, Sinclair argues, information concerning gas obtained at the refineries is irrelevant to show replacement gas. At this preliminary stage, it is inappropriate to conduct a full and binding contractual interpretation. Here, it is enough that obtaining gas under the contract possibly refers to downstream replacement.

NextEra argues that the extent to which Sinclair “ramped down” the Tulsa Refineries reveals that Sinclair could have operated the Tulsa Refineries on the non- NextEra gas alone. NextEra connects this with the contractual term in the Cover Standard that considers “the immediacy of the Buyer’s Gas consumption needs.”17 But Sinclair never addresses this contractual term or shows that it is disconnected from the present dispute such that it renders the information irrelevant to the damages calculation.

C. Corporate Representative Preparedness NextEra does not defend its position that Sinclair’s corporate representative (Aaron Smedley) was unprepared as to the “ramped down” state in its reply brief. Even if it did, it could not succeed in arguing it is entitled to another deposition of a corporate representative on that point. NextEra seeks a corporate representative to

17 Doc. 84-1 at App. 22. testify to the “ramped down” state of the Tulsa Refineries. The corporate representative did testify to the ramped down state—and it appears NextEra simply did not like the answer Smedley gave.

Free access — add to your briefcase to read the full text and ask questions with AI

HF Sinclair Refining & Marketing LLC v. NextEra Energy Marketing LLC, (N.D. Tex. 2025).

HF Sinclair Refining & Marketing LLC v. NextEra Energy Marketing LLC (HF Sinclair Refining & Marketing LLC v. NextEra Energy Marketing LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related