Hessan v. Gross

61 Pa. D. & C.2d 332, 1971 Pa. Dist. & Cnty. Dec. LEXIS 17
CourtPennsylvania Court of Common Pleas, Philadelphia County
DecidedFebruary 24, 1971
Docketno. 3831
StatusPublished

This text of 61 Pa. D. & C.2d 332 (Hessan v. Gross) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Philadelphia County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hessan v. Gross, 61 Pa. D. & C.2d 332, 1971 Pa. Dist. & Cnty. Dec. LEXIS 17 (Pa. Super. Ct. 1971).

Opinion

SAYLOR, J.,

— In this equity action plaintiff asked the court to issue an order, preliminarily until hearing and perpetually thereafter, restraining defendants, his former partners in two building construction projects, from disposing of the proceeds of the sale of a project at Wyomissing, Pa., and a project at Hatfield, Pa., to deposit such proceeds [333]*333at interest; declaring releases executed by plaintiff to be null and void; and restoring plaintiff to his status as a partner in both projects as their interests were originally designated.

Hearings on the application for a preliminary injunction based on the bill of complaint, answer, new matter and reply to new matter were held before Judge Greenberg on November 7 and 10, 1969, following which the hearing judge denied prayer of the petition.

On January 22, 25 and 26, 1971, at the trial of the action testimony of plaintiff and of defendants, the latter as in cross-examination, was taken and various exhibits were admitted into evidence. Defendants moved for a nonsuit.

Plaintiff is a real estate developer and broker. Defendants are engaged in various phases of the building and construction business.

In 1965 or 1966, plaintiff introduced defendant Gross to land at Wyomissing on which they planned the erection of apartments. Early in 1966 or 1967, Segal representing himself as a builder, agreed to make a cash capital contribution to the project.

The three parties executed a written agreement of partnership for the development of the Wyomissing land. Paragraph 5 of the agreement required Segal to take charge of all construction, Gross to take charge of all financing and marketing and Hessan to take charge of zoning changes, real estate sales and local municipal personnel management. Likewise, Hessan was to assist his two partners. Plaintiff procured the zoning change which permitted the erection of apartments in such fashion as to increase materially the value of the tract of land.

Later the three partners and a Mr. Dintenfass repeated substantially the process at Hatfield and entered into a written partnership agreement for the [334]*334development of garden-type apartments on the land there situated. Dintenfass later withdrew as a partner.

At Wyomissing financial difficulties arose as there was the likelihood that subcontractors would threaten suit and the construction lender would withhold advances. Whether or not representations of various kinds were made to plaintiff regarding the financial situation, plaintiff as a partner was in the position that his personal estate would be liable for any existing deficiencies. In any event, plaintiff agreed in writing to sell his interest in the Wyomissing project for $40,000. He executed a written agreement whereunder he withdrew as a partner.

In the case of the Hatfield project in order to supplement the financing there a New York firm acquired 50 percent of the project leaving each of the original three partners a 16Vs percent interest. Here too, financial difficulties arose and the partners were faced with the possibility that the New York firm would take over the entire project and hold them personally liable for their proportionate share of the partnership indebtedness to that firm.

Plaintiff agreed in writing to release his interest in the partnership with defendants, and, in the $15,000 balance remaining unpaid on the partners’ agreement made at the time, plaintiff withdrew from the Wyo-missing project. By the agreement concerning the Hatfield project plaintiff was released from liabilitv for obligations of the former partnership.

It is clear from the background of plaintiff that his primary responsibility to the partnership was to assist in the acquisition of land, the obtaining of such zoning as was necessary to develop it profitably as sites for apartments thereon to be erected, and to attend to the marketing of the units in the apartments when completed. Defendants’ responsibility was to arrange the [335]*335financing of the projects and to erect the apartments. However, all three partners were jointly responsible for the conduct of the partnership and the execution of the projects for which the partnerships were created.

Plaintiff complains that information in the possession of defendant partners during the construction of the building projects was improperly withheld from him with the result that he withdrew from the two partnerships without full knowledge of the facts, to which, as a partner, he was entitled; and that he has suffered serious financial loss because after his withdrawal in both instances the financial picture changed and, being no longer a partner, he was and is being deprived of the profits enjoyed by defendants by reason of their sale of the apartments at considerable advantage to them.

The testimony shows that in the progress of both building operations conducted by the partnerships difficulties arose. Failure of contractors to perform their obligations properly, the shortage of funds needed for the projects due to inadequate original financing, rising costs, hesitation of the construction lender to advance funds until units were under contract to tenants and failure to obtain adequate loans from the partners and other individuals. It is apparent from the record that the plaintiff who enjoyed a financial standing superior to that of defendants came to the conclusion that he should withdraw from the partnerships in order to escape his commitment to the financial success of the building ventures. After consulting with his attorney, in at least one of the instances of withdrawal, he voluntarily did so. In the first instance, that of the Wyomissing project, he was to be paid $40,000 of which sum in two payments he received $25,000. In the second instance, that at Hatfield, he was relieved of all financial liability [336]*336upon surrendering his right to receive the remaining $15,000 due under the prior release arrangement.

He has now come into court to contend that his former partners should restore him to the position he held prior to the withdrawals so that he can enjoy his share of the profit the partnership ultimately realized.

Plaintiff has contended that he was deceived. However, in his testimony he admits knowledge of the difficulties being experienced by the two partnerships prior to his withdrawal. He was aware that the construction lender was not going to advance more money unless other funds were found for the Wyomissing project. That was the time he agreed to sell his share in that project. He knew that there was a deficiency amounting to $280,000 in funds necessary to proceed with the Hatfield project and that such deficiency had to be supplied through the New York people who purchased a 50 percent interest in the partnership. He was aware of the unpaid claims of contractors that embarrassed the partnership. Bricklayers and plumbers were threatening suit. Loans had to be made from time to time from individuals outside the partnership to keep the project moving. He visited the scene of the operation from time to time. He attended meetings of the partners. He was advised of problems as they arose. He knew that it had become apparent that additional money was needed based upon what his partners and the contractors said. He knew that the Wyomissing project was behind schedule and that the construction lender would not advance more funds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Inman v. Parr
311 S.W.2d 658 (Court of Appeals of Texas, 1958)
Clement v. Clement
260 A.2d 728 (Supreme Court of Pennsylvania, 1970)
Stimson v. Stimson
29 A.2d 679 (Supreme Court of Pennsylvania, 1942)
William Goldstein Co. v. Joseph J. & Reynold H. Greenberg, Inc.
42 A.2d 551 (Supreme Court of Pennsylvania, 1945)
Geddes's Appeal
80 Pa. 442 (Supreme Court of Pennsylvania, 1876)
Nulton's Appeal
103 Pa. 286 (Supreme Court of Pennsylvania, 1883)
Wiley v. Brundred
28 A. 173 (Supreme Court of Pennsylvania, 1893)
Lyle v. Shay
30 A. 940 (Supreme Court of Pennsylvania, 1895)
Guenther v. Kutz
112 A. 919 (Supreme Court of Pennsylvania, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
61 Pa. D. & C.2d 332, 1971 Pa. Dist. & Cnty. Dec. LEXIS 17, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hessan-v-gross-pactcomplphilad-1971.