Heslep v. Forrest & Cotton, Inc.

449 S.W.2d 181, 247 Ark. 1066, 1970 Ark. LEXIS 1393
CourtSupreme Court of Arkansas
DecidedJanuary 26, 1970
Docket5-5046
StatusPublished
Cited by2 cases

This text of 449 S.W.2d 181 (Heslep v. Forrest & Cotton, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heslep v. Forrest & Cotton, Inc., 449 S.W.2d 181, 247 Ark. 1066, 1970 Ark. LEXIS 1393 (Ark. 1970).

Opinion

J. Fred Jones, Justice.

Jack R. Heslep was employed as an oiler, driver and hookup man on a mobile crane belonging to his employer, Paul N. Howard Co. A fellow employee, Eddy Faulkner, was the crane operator. As Heslep started to attach a steel cable line from the crane boom to a joint of sewer pipe under an electric power line, the crane line became energized from the overhead power line and Heslep was injured. He filed suit for personal injuries against Forrest and Cotton, Inc. and Garver and Garver, Inc., the consulting and resident engineers. A jury trial resulted in a verdict in favor of Heslep for $7,500. The trial court granted a motion by the engineers for judgment notwithstanding the verdict and Heslep has appealed. He relies on tlie following point for reversal:

“The trial court erred in directing a judgment for defendants notwithstanding the jury verdict.”

Heslep states that the sole issue in this case is whether or not there was substantial evidence from which the jury could find that the engineers owed a duty to require the contractor to provide safety devices on the mobile crane in question while it was being operated in close proximity to 13,000 volt power lines. We are of the opinion that there was no substantial evidence from which the jury could find that the engineers owed such duty under the facts and circumstances of this case.

Heslep’s employer, Paul N. Howard Co., had a general contract with the City of Little Rock to install a new underground sewer system. The system was to be installed according to plans and specifications prepared by the out of state engineering firm, Forrest and Cotton, Inc. The local firm, Garver and Garver, Inc., was employed as resident engineers to see that the plans and specifications were complied with as the work progressed. One section of the sewer system was constructed of joints of pipe five feet long and three feet in diameter which were lowered into a ditch and cemented into place under the center of North Street. The joints of sewer pipe were shipped in from out of state and delivered to the job site by truck. The pipe joints were inspected for cracks and flaws upon delivery at the job site, and all rejected joints were returned to the manufacturer as the trucks made return trips for additional pipe.

On the day of Heslep’s injury, a truck had delivered a load of pipe and was ready to leave on the return trip about noon. There were two rejected joints of pipe to be returned on the truck, and by the use of a front end loader they had been moved out of the way and placed together near the intersection of North and Ringo Streets. They were placed on the ground between the sidewalk and street curb, which was also about 30 feet beneath an electric power line strung on light poles also set between the sidewalk and curb. The truck on which the joints of pipe were to be returned was too high for the pipe to be placed on the truck by the front end loader, so the front end loader was used to move the rejected pipe joints from under the power line and out into the street where they could then be picked up by the mobile crane and lifted onto the truck.

The operator of the crane was Eddy Faulkner, who was also an employee of Paul N. Howard Co. It was his duty to actually operate the crane boom and it was Heslep’s duty to drive the crane from place to place and spot it as directed by Faulkner. Heslep would then fasten the cable from the crane boom to the object to be moved, and would release the cable from the object after it had been moved. It was also Heslep’s duty to keep the crane oiled and greased. On the day of Heslep’s injury he and Faulkner had been ordered by their foreman, R. L. Webb, to move the crane to the intersection of Ringo and North Streets and hoist the rejected joints of pipe onto the truck to be hauled away. The crane was moved into position for this purpose about 12:30. The crane was equipped with either a 50 foot boom, as testified by Webb, or a 70 foot boom, as testified by Faulkner, and the joints of pipe were lifted by means of a swing cable attached to the joints of pipe and also to the lift cable on the crane.

One joint of the rejected pipe had been moved from under the power line into the street by the front end loader when the operator of the front end loader went to lunch, leaving one rejected joint of pipe in the street to be hoisted onto the truck and leaving the other joint still under the power line and still to be removed by the front end loader. When Heslep and Faulkner arrived with the crane, they loaded the joint of pipe from the street onto the truck. The truck was ready to leave as soon as the other rejected joint of pipe was loaded, so Heslep and Faulkner did not wait for the operator of the front end loader to return from lunch and remove the additional joint of pipe from under the power line, but instead, after loading the first joint onto the truck, Heslep pulled or carried the swing cable, which was still attached to the lift cable on the crane boom, over to the remaining joint of reject pipe under the power line. As he was attempting to fasten the sling cable to the joint of pipe, the lift cable, or boom, came in contact with the overhead power line and Heslep was injured.

The contractual arrangements between the parties are lengthy and will not be set out here. Some of the provisions on which Mr. Heslep seems to rely, and as read into the record by Engineer Van Meter, are as follows:

“Paragraph SC. 15, entitled ‘Public Utilities and Other Property to be Changed. In case it is necessary to change or move the property of any owner or of a public utility, such property shall not be moved or interfered with until ordered to do so by the Engineer. The right is reserved to the owner of public utilities to enter upon the limits of the project for the purpose of making such changes or repairs of their property that may be made necessary by performance of this Contract.’
This is General Conditions, Paragraph 2.11, ‘Defects and Their Remedies. It is further agreed that if the work or any part thereof, or any material brought on the site of the work for use in the work or selected for the same, shall he deemed by the Engineer as unsuitable or not in conformity with the specifications, the Contractor shall, after receipt of written notice thereof from the Engineer, forthwith remove such material and rebuild or otherwise remedy such work so that it shall be in full accordance with this contract. ’
# # *
Paragraph 2.04, ‘Contractor’s Duty and Superintendence. The Contractor shall give personal attention to the faithful proscecution and completion of this contract and shall keep on the work, during its progress, a competent superintendent and any necessary assistants, all satisfactory to the Engineer. The superintendent shall represent the Contractor in his absence and all directions given to him shall he as binding as if given to the Contractor. Important directions shall be confirmed in writing to the Contractor. Other directions shall he so confirmed on written request in each case.’
# * *
‘Protection Against Accident to Employees and the Public.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Krieger v. J. E. Greiner Co.
382 A.2d 1069 (Court of Appeals of Maryland, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
449 S.W.2d 181, 247 Ark. 1066, 1970 Ark. LEXIS 1393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heslep-v-forrest-cotton-inc-ark-1970.